Gujarat High Court
Property and Real Estate LawAdministrative and Public Law

LPG pipeline laid illegally on private land to stay, but GAIL must acquire the land and pay compensation, Gujarat HC rules

USHABEN HARILAL NANDHA vs UNION OF INDIA

Gujarat High CourtJUDGMENT: August 04, 20265 MIN READSOURCE JUDGMENT
LPG pipeline laid illegally on private land to stay, but GAIL must acquire the land and pay compensation, Gujarat HC rules. USHABEN HARILAL NANDHA vs UNION OF INDIA. Gujarat High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioners claimed ownership of Revenue Survey No. 140, subsequently renumbered as Survey No. 174, situated at Village Moti Khavdi, Jamnagar. In 1998, the Union of India issued a notification under Section 6 of the Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962 (“1962 Act”) acquiring the right of user over several adjoining survey numbers for the Jamnagar–Loni Pipeline Project, but the petitioners’ land was not included in that notification. Compensation was paid to the concerned landowners and corresponding revenue entries were made.

Source reference: p.2; paras. 2–3

GAIL (India) Ltd. nevertheless laid a six-inch LPG pipeline over the petitioners’ land in 2007–2008 without acquiring the right of user or issuing a notification in respect of that land. The petitioners claimed that they became aware of the pipeline only in 2016, after applying for non-agricultural permission. A survey by the District Inspector of Land Records confirmed that the pipeline passed through their land.

Source reference: p.3; paras. 4–5

Subsequently, preliminary and final notifications dated 02 July 2018 and 06 December 2018 were issued for acquisition of the right of user for laying a parallel pipeline. GAIL informed the petitioners on 04 January 2019 about the acquisition and compensation process.

Source reference: p.4; paras. 6–8

In its affidavit, GAIL admitted that the original pipeline had been laid in 2007–2008, although the relevant land had not been notified for acquisition, and explained that the wrong land had allegedly been used because constructions had come up on the notified land during the intervening period.

Source reference: p.5; paras. 9–10

The petitioners sought removal of the pipelines, quashing of the 2018 acquisition notification, and compensation, mesne profits and damages of ₹86,00,000.

Source reference: p.1; para. 1
02

Issues

Whether GAIL’s utilisation of the petitioners’ land and laying of the original pipeline in 2007–2008, without acquisition of the right of user under the 1962 Act, was illegal and violative of the petitioners’ constitutional property rights.

Source reference: p.7; paras. 13–15

Whether the Court should direct removal of the operational LPG pipeline despite its having been laid without due process of law.

Source reference: p.8; para. 15

Whether the acquisition notifications dated 02 July 2018 and 06 December 2018, issued for laying the parallel pipeline, were liable to be quashed.

Source reference: p.4; paras. 6–8; p.9; paras. 17–18

What compensation and consequential relief were payable to the petitioners for the unauthorised use of their land.

Source reference: p.8; paras. 15–16
03

Law Applied

The Court applied the Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962, under which the State or an authorised entity must follow the statutory notification and acquisition process before acquiring a right of user in private land for laying petroleum pipelines; the relevant notifications under Sections 3 and 6 provide the statutory basis for such acquisition.

Source reference: pp. 2, 4, 8–9; paras. 2, 6, 16–18

The Court further applied Article 300A of the Constitution, which protects a person from deprivation of property except by authority of law. Consequently, unauthorised occupation or use of private land for laying a pipeline cannot be retrospectively regularised merely because the project is of public or national importance; lawful acquisition and payment of compensation are required.

Source reference: p.7; paras. 13–15

Where physical removal of an essential public utility is impracticable, the Court may mould relief by directing a lawful acquisition and payment of compensation, including applicable interest and statutory benefits.

Source reference: pp. 8–9; paras. 15–16
04

Reasoning

GAIL’s affidavit amounted to an admission that the original pipeline had been laid over the petitioners’ land in 2007–2008, although no acquisition notification covered that land.

Source reference: p.7; para. 13

The Court rejected GAIL’s explanation that the wrong land had been used because permanent constructions had subsequently arisen on the notified land, holding that the consequences of the intervening delay were attributable to GAIL. If the originally notified alignment had become impracticable, GAIL was required to initiate fresh acquisition proceedings before using the petitioners’ land.

Source reference: p.7; para. 14

Such unauthorised use deprived the petitioners of the full enjoyment of their property and violated Article 300A.

Source reference: p.7; para. 15

Although the pipeline had been illegally laid, the Court declined to order its removal because it was an operational LPG pipeline forming part of a project supplying LPG across substantial parts of the country; removal was considered technically and practically infeasible and would adversely affect a project of national importance.

Source reference: p.6; para. 11; p.8; para. 15

To balance the public interest with the petitioners’ property rights, the Court directed GAIL to commence acquisition proceedings under the 1962 Act for the original pipeline and treated 27 March 2019, the date of filing of the petition, as the relevant date for determining market value. The Court also directed inclusion of interest from the date of dispossession until payment.

Source reference: p.8; para. 16

As to the parallel pipeline, the Court found no sufficient ground to invalidate the 06 December 2018 notification. The petitioners were permitted to seek payment under the award and to pursue the statutory appellate remedy if dissatisfied with the determination of compensation.

Source reference: p.9; paras. 17–18
05

Holding

The Court held that GAIL had illegally utilised the petitioners’ land and laid the original pipeline without following the acquisition process under the 1962 Act, thereby affecting the petitioners’ Article 300A rights.

However, it declined to direct removal of the pipeline. GAIL was directed to undertake acquisition proceedings for the right of user relating to the original pipeline within three months, with market value determined as on 27 March 2019, and with interest from the date of dispossession until payment, along with all other lawful compensation benefits.

Source reference: p.8; para. 16

The challenge to the 06 December 2018 notification for the parallel pipeline was rejected, while the petitioners were left free to claim the awarded compensation and invoke the statutory appellate remedy regarding its computation.

Source reference: p.9; paras. 17–18

There was no order as to costs, with liberty granted to the petitioners to approach the Court in case of non-compliance with the directions.

Source reference: p.9; paras. 19–20
06

Acts & Sections Cited

2 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.

Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 19622

Gujarat High Court

Original Court PDF

USHABEN HARILAL NANDHAvsUNION OF INDIA

Gujarat High Court · August 04, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment