01Facts
The petitioners sought transfer into their names of one 10 MW and two 5 MW solar power plants, and issuance of Noted-for-Record approvals to energise the plants at the 110/33 KV Srimoolakarai Renfra Pooling Sub-Station.
pp. 6–7They stated that, despite an earlier order directing the respondents to process pending requests and issue the requisite certificates, their requests remained undecided.
pp. 6–7Relying on a similar order in W.P. No. 45524 of 2026, the petitioners sought mandamus directing the relevant respondents to effect the transfers and issue the approvals.
pp. 4–5, 7–802Issues
i.1. Whether the respondents should be directed to process the petitioners’ requests to transfer the solar plants into their names and issue Noted-for-Record approvals for energisation
pp. 4–6, 8–9ii.2. Whether those requests should be processed following submission of a consolidated application and within a specified period
pp. 8–903Law Applied
The petitions invoked the High Court’s jurisdiction under Article 226 of the Constitution to seek mandamus.
pp. 4–5The Court relied on its order in W.P. No. 45524 of 2026, dated 10 November 2026, under which the petitioner was directed to submit a consolidated application and the respondent was to complete the specified stages within three weeks of receiving it.
pp. 7–8The Court also noted an earlier order in W.P. No. 21524 of 2026, dated 19 August 2026, directing the respondents to process pending requests and issue requisite certificates expeditiously.
p. 704Reasoning
The Court considered the requested reliefs similar to those addressed in W.P. No. 45524 of 2026 and recorded the respondents’ submission that the transfer and energisation-approval requests would be considered upon receipt of a consolidated application.
pp. 7–9Applying the approach in that precedent, the Court required the petitioners to submit one consolidated application and directed the fourth respondent, in consultation with the third respondent, to complete both stages within three weeks of receiving it.
p. 905Holding
The Court disposed of all three writ petitions on the stated terms.
p. 9The petitioners were directed to submit a consolidated application forthwith; the fourth respondent, in consultation with the third respondent, was directed to complete the name-transfer and Noted-for-Record approval stages within three weeks of receipt.
p. 9No costs were awarded, and the connected miscellaneous petitions were closed.
p. 9Original Court PDF
M/s.Glacious Energy Solutions Private Limted.,vsTHE TAMIL NADU POWER DISTRIBUTION CORPORATION LIMT
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in