01Facts
The petitioner sought transfer into its name of a 3.3 MW wind mill, purchased from its developer, and approval to energise it through the developer’s pooling sub-station.
pp. 3–4It had applied for the name transfer on 27 May 2026, paid the required charges, and obtained the developer’s consent; however, the application remained pending following a circular directing that approvals for wind and solar connectivity not be granted.
pp. 3–4After the site was inspected and found fit for commissioning, the petitioner sought a direction compelling the respondents to effect the transfer and issue the “Noted-for-Record” approval.
pp. 4–5The respondents’ counsel stated that the three related stages—name transfer, the approval, and execution of an Energy Wheeling Agreement—could be considered on receipt of a consolidated application.
p. 502Issues
i.1. Whether the respondents should be directed to process the petitioner’s request for name transfer and “Noted-for-Record” approval for the wind mill.
p. 1 · pp. 4–5ii.2. Whether the related Energy Wheeling Agreement should also be addressed as part of processing the petitioner’s application.
p. 503Law Applied
The petition invoked the High Court’s jurisdiction under Article 226 of the Constitution of India, seeking a writ of mandamus.
p. 1The operative basis for the order was the respondents’ submission that the three stages would be considered upon receipt of a consolidated application.
p. 504Reasoning
Rather than determine the petitioner’s entitlement to the approvals on the merits, the Court acted on the respondents’ representation that all three stages could be considered together.
p. 5It directed the petitioner to submit a consolidated application and required the fourth respondent, in consultation with the third respondent, to complete the three stages within three weeks of receiving it.
pp. 5–605Holding
The Court disposed of the writ petition by directing the petitioner to submit a consolidated application for the name transfer, “Noted-for-Record” approval, and Energy Wheeling Agreement.
p. 6The fourth respondent, in consultation with the third respondent, was directed to complete all three stages within three weeks of receipt of that application.
p. 6No costs were awarded, and the connected miscellaneous petition was closed.
p. 6Original Court PDF
M/S. ADITYAA ENERGY RENEWABLES (INDIA) PVT LTDvsTHE TAMIL NADU POWER DISTRIBUTION CORPORATION LIMT
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in