APTEL
Administrative and Public LawCommercial and Corporate Law

O&M treatment must follow precedent recognizing mandated network augmentation charges as uncontrollable.

Torrent Power Limited vs Gujarat Electricity Regulatory Commission & Ors

APTELJUDGMENT: September 23, 20262 MIN READSOURCE JUDGMENT
O&M treatment must follow precedent recognizing mandated network augmentation charges as uncontrollable.. Torrent Power Limited vs Gujarat Electricity Regulatory Commission & Ors. APTEL. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

Torrent Power Limited, a distribution licensee in Gujarat, challenged the Gujarat Electricity Regulatory Commission’s Tariff Order dated 4 April 2018 concerning the true-up for FY 2016–17 and determination of tariff for FY 2018–19.

Source reference: p. 3

The sole challenge concerned the Commission’s treatment of the Appellant’s Operation and Maintenance (“O&M”) expenses as controllable. During the appeal, both the Appellant and the Commission accepted that the matter was covered by the Tribunal’s earlier judgment dated 9 May 2019 in Torrent Power Limited v. Gujarat Electricity Regulatory Commission, Appeal No. 256 of 2016.

Source reference: p. 3
02

Issues

Whether the Commission was correct in treating the Appellant’s O&M expenses as controllable while determining the true-up and tariff.

Source reference: p. 3

Whether the impugned Tariff Order was required to be set aside and the matter remanded for reconsideration in accordance with the Tribunal’s judgment in Appeal No. 256 of 2016.

Source reference: pp. 3–4
03

Law Applied

The Tribunal applied the principles laid down in its judgment dated 9 May 2019 in Torrent Power Limited v. Gujarat Electricity Regulatory Commission, Appeal No. 256 of 2016. Under that judgment, variation in O&M expenses is ordinarily treated as controllable; however, expenses incurred for network augmentation required by the State Transmission Utility for connectivity may, in appropriate exceptional circumstances, be treated as uncontrollable.

Source reference: p. 3

The Tribunal further held that deductions from O&M expenses contrary to the applicable statutory regulations are impermissible and that the Commission must adopt a consistent approach in comparable matters, including matters concerning O&M expenses and technical and commercial losses.

Source reference: p. 4
04

Reasoning

The Tribunal did not independently examine the merits of the Commission’s treatment of the O&M expenses because both the Appellant and the Commission agreed that the controversy was governed by the Tribunal’s earlier decision.

Source reference: p. 3

The Commission expressly accepted that it was bound by the principles laid down in Appeal No. 256 of 2016 and requested a fresh determination on that basis. In view of the admitted legal position and the parties’ consensus, the Tribunal held that the appropriate course was to set aside the impugned order and remit the issue to the Commission for reconsideration in accordance with the earlier judgment.

Source reference: p. 4
05

Holding

The Tribunal allowed the appeal, set aside the Tariff Order dated 4 April 2018 to the extent challenged, and remanded the matter to the Gujarat Electricity Regulatory Commission for a fresh decision on the treatment of the Appellant’s O&M charges in accordance with the judgment dated 9 May 2019 in Appeal No. 256 of 2016.

The appeal and the pending interlocutory application were disposed of accordingly.

Source reference: p. 5
APTEL

Original Court PDF

Torrent Power LimitedvsGujarat Electricity Regulatory Commission & Ors

APTEL · September 23, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment