01Facts
The petitioner applied to the Bihar Real Estate Regulatory Authority (RERA) to register its proposed project, “Chhabilchandra Enclave.” The judgment records the application date as 19 June 2025, although other parts refer to 9 June 2025.
p. 3, 5, 40RERA raised queries, including demands for the housing society’s bye-laws, approval from the Registrar of Co-operative Societies for multi-storey construction, and any amendment to the 1982 sale deed. The petitioner responded to the queries and relied on a municipal building-plan sanction and a society-issued NOC.
pp. 3–5, 24RERA issued a notice proposing rejection on 18 December 2025; after a hearing on 8 January 2026, it rejected the application by Form D dated 16 February 2026.
pp. 4–5The petitioner sought to quash those actions and obtain recognition of deemed registration under Section 5(2) of the Real Estate (Regulation and Development) Act, 2016 (“RERA Act”).
pp. 1–302Issues
i.1. Whether the project stood deemed registered under Section 5(2) because RERA did not grant or reject the application within 30 days of its receipt, despite the Authority’s assertion that the application was incomplete.
pp. 16–19, 36–40ii.2. Whether RERA could require the three disputed co-operative-society and sale-deed documents as conditions for registration under Section 4 of the RERA Act and Rule 3 of the Bihar RERA Rules, 2017.
pp. 21–26, 34–3503Law Applied
Section 4(2) of the RERA Act specifies the documents and information a promoter must provide with a registration application; further documents may be required only as prescribed by rules or regulations.
pp. 30–35Under Section 5(1), the Authority must grant or reject an application within 30 days of receipt, and Section 5(2) provides that the project is deemed registered if it does neither within that period.
pp. 36–37The Court applied the principle that statutory language must be given effect without adding requirements or rendering another provision redundant, relying on Hardeep Singh v. State of Punjab, M/s Newtech Promoters and Developers Pvt. Ltd. v. State of U.P., and Union of India v. Deoki Nandan Aggarwal.
pp. 18–21, 38–39It also relied on Uttar Pradesh Real Estate Regulatory Authority v. Larsen & Toubro Limited, which held that the Authority must choose between grant and rejection within the statutory period and cannot keep an application pending on grounds of alleged deficiencies.
pp. 20–21, 37The Court further cited Bhavnagar University v. Palitana Sugar Mill (P) Ltd. and Sharif-Ud-Din v. Abdul Gani Lone for the mandatory character of a time limit accompanied by a specified consequence for non-compliance.
pp. 20–2204Reasoning
The Court found that the three disputed documents were not specified in Section 4(2), Rule 3 of the Bihar RERA Rules, 2017, or any identified regulation; RERA therefore could not treat their absence as making the application incomplete.
p. 35The application and accompanying materials addressed the statutory requirements, and RERA did not identify any required Section 4(2) document that remained missing.
p. 35Since Section 5 runs from receipt of the application and contains no provision suspending or restarting the 30-day period when queries are raised, the Authority’s later queries did not stop time from running.
p. 37Applying the date stated in its findings, the Court held that the period expired on 19 July 2025, well before the December notice and subsequent rejection.
p. 40The petitioner’s later request for time to provide the disputed documents could not waive or undo the deemed-registration consequence that had already arisen by operation of law.
p. 41The Court also held that the cited municipal decisions did not enlarge RERA’s powers under the Act.
p. 3505Holding
The Court held that “Chhabilchandra Enclave” stood deemed registered under Section 5(2) of the RERA Act when RERA failed to grant or reject the application within 30 days.
pp. 40–42It allowed the writ petition, quashed the notice dated 18 December 2025, the order dated 8 January 2026, and Form D dated 16 February 2026, and directed RERA to provide the petitioner with a registration number, login ID, and password upon production or receipt of the order.
p. 42Original Court PDF
Aditya Niwas Developers and ColonizersvsThe State of Bihar
Click to open original judgment