Facts
The petitioners purchased the residential property at A-51, Spring Meadows, South Bopal, Ahmedabad, by registered sale deed dated 30 December 2024.
Source reference: p.3On 4 June 2025, the Ahmedabad Municipal Corporation issued a notice under Section 260(1)(a) of the Gujarat Provincial Municipal Corporations Act, 1949 (GPMC Act), alleging unauthorised construction and requiring a response by 9 June 2025.
Source reference: p.3The petitioners state that they replied by registered post on 5 June, but the Corporation passed an order under Section 260(2) on 10 June without giving them a personal hearing.
Source reference: p.3–4The petitioners applied for regularisation under the Gujarat Regularization of Unauthorised Development Act, 2022 (GRUDA) on 5 November 2025 and filed this petition the following day, challenging the notice, order, and a communication seeking disconnection of electricity.
Source reference: p.4, 6At the hearing, they sought a direction for determination of their GRUDA application; the Corporation contended that the construction post-dated the statutory cut-off and was ineligible for regularisation.
Source reference: p.5–6Issues
1. Whether the Court should direct the respondent authority to decide the petitioners’ pending GRUDA application.
Source reference: p.5–62. Whether the Court should determine the GRUDA application’s maintainability or the validity of the impugned proceedings under Sections 260(1) and 260(2) of the GPMC Act.
Source reference: p.6–7Law Applied
Section 260 of the GPMC Act empowers the municipal authority to take action in respect of unauthorised construction; the Court noted that the pending GRUDA application did not preclude action under that provision.
Source reference: p.6The GRUDA provides a statutory process for considering applications to regularise unauthorised development.
Source reference: p.6–7The Court directed that the application be decided in accordance with law, but expressed no view on its maintainability or on whether the construction fell before or after the applicable cut-off date.
Source reference: p.6–7No precedent was relied upon.
Source reference: no citationReasoning
The petitioners’ counsel accepted that their principal grievance could be addressed by a decision on the pending GRUDA application.
Source reference: p.5Although the Corporation disputed the application’s eligibility on the ground that the construction was subsequent to the cut-off date, the Court considered it appropriate, in the circumstances, to require the authority to determine the application rather than decide that disputed question itself.
Source reference: p.6–7The Court left both the application’s maintainability and the challenge to the Section 260 notice and order open, and clarified that the GRUDA application did not bar the Corporation from acting under Section 260.
Source reference: p.6–7Holding
The petition was disposed of with a direction to the respondent authority to decide the petitioners’ GRUDA application in accordance with law, preferably within two weeks.
The Court made no determination on the application’s maintainability, the cut-off-date issue, or the validity of the notice and order under Sections 260(1) and 260(2) of the GPMC Act.
Source reference: p.6–7Rule was made absolute to that limited extent.
Source reference: p.7Acts & Sections Cited
1 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.
Gujarat Provincial Municipal Corporations Act, 19491
Original Court PDF
VIRENDRA MANILAL MAHEMDAVADI (MALI)vsSTATE OF GUJARAT
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in