Bombay High Court
Arbitration and MediationProperty and Real Estate Law

RERA disputes between homebuyers and builders are non-arbitrable, Bombay High Court reiterates

Laxman Mura Vaid vs Shree Siddivinayak Infrastructure And Realty A Partnership Firm

Bombay High CourtJUDGMENT: September 21, 20264 MIN READSOURCE JUDGMENT
RERA disputes between homebuyers and builders are non-arbitrable, Bombay High Court reiterates. Laxman Mura Vaid vs Shree Siddivinayak Infrastructure And Realty A Partnership Firm. Bombay High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Applicants booked Flat No. 3903 in the Respondent-promoter’s project, “Ruparel Skygreens,” under a 5:90:5 subvention scheme involving DHFL.

Source reference: paras. 2–3

A Tripartite Agreement was executed in 2017, followed by a registered Agreement for Sale dated 11 March 2022.

Source reference: paras. 2–3

The Applicants alleged that the Respondent failed to pay the pre-interest EMI to DHFL, compelling them to pay Rs. 12,99,557/- towards interest.

Source reference: paras. 3–6

They also alleged that possession, expected by December 2022, was not delivered.

Source reference: paras. 3–6

The Respondent issued a Termination Notice dated 3 January 2026.

Source reference: para. 4

Relying on Clause 86 of the Agreement for Sale, which contained an arbitration clause, the Applicants invoked arbitration and filed an application under Section 11(6) of the Arbitration and Conciliation Act, 1996.

Source reference: paras. 4, 7

They also filed a petition under Section 9 seeking interim relief.

Source reference: paras. 4, 7
02

Issues

Whether the existence of Clause 86 of the Agreement for Sale required the Court to appoint an arbitrator under Section 11 of the Arbitration and Conciliation Act, 1996?

Source reference: paras. 11–14

Whether disputes concerning possession, payment of consideration, subvention obligations, interest and termination between an individual allottee and a promoter in a RERA-covered project are arbitrable?

Source reference: paras. 13–24, 32–44

Whether the Applicants’ Section 9 petition for interim measures could be entertained when the underlying disputes were held to be non-arbitrable?

Source reference: paras. 46–48
03

Law Applied

The Court applied Sections 11(6), 16 and 9 of the Arbitration and Conciliation Act, 1996, holding that although the Section 11 enquiry is ordinarily limited and principally concerns the existence and validity of an arbitration agreement, the Court may undertake a prima facie examination of whether the subject matter is non-arbitrable.

Source reference: paras. 11–12, 36–38

Following Rashmi Realty Builders Pvt. Ltd. v. Rahul Rajendrakumar Pagariya, the Court held that disputes between an individual allottee and a promoter covered by RERA are, by necessary implication, non-arbitrable because RERA creates a statutory and public regulatory framework whose operation may affect the project, other allottees and the association of allottees.

Source reference: paras. 15–23

Sections 79, 88 and 89 of RERA were read together to preserve the statutory mechanism and its overriding effect in case of inconsistency.

Source reference: para. 39

The Court distinguished the contrary approach in Priyanka Tak Sood v. Sunworld Residency Pvt. Ltd., which treated certain individual refund claims as arbitrable, and held that judicial discipline required following the applicable Bombay High Court decision in Rashmi Realty.

Source reference: paras. 25–30, 41–42

It relied on Interplay between Arbitration Agreements under the Arbitration and Conciliation Act, 1996 and the Indian Stamp Act, 1899 and Motilal Oswal Financial Services Ltd. v. Santosh Cordeiro for the limited nature of Section 11 scrutiny, and on Arif Azim Company Ltd. v. Aptech Ltd. for the proposition that a court may refuse reference where the dispute is non-arbitrable.

Source reference: paras. 8, 11–12, 36
04

Reasoning

The Court accepted that Clause 86 constituted a valid arbitration agreement and that the Applicants had raised a genuine dispute, rather than a sham claim.

Source reference: para. 43

However, it distinguished the existence of an arbitration agreement from the arbitrability of the particular dispute.

Source reference: paras. 11–14

The Applicants’ claims were not merely ordinary contractual claims for money; they concerned delayed possession, payment of consideration, the promoter’s alleged subvention obligations, interest, reconciliation of accounts and termination of the allotment.

Source reference: paras. 13, 32–34

These matters arose directly from the statutory relationship between a promoter and an allottee in respect of a registered real estate project and corresponded to rights and obligations regulated by RERA, including the consequences of delayed possession under Section 18.

Source reference: paras. 13, 32–34

The Applicants’ alleged payment to DHFL and asserted readiness to pay the balance did not alter the legal character of the dispute or take it outside RERA.

Source reference: paras. 33–34

In light of Rashmi Realty, the Court held that the private arbitration clause could not override the statutory exclusion of arbitral adjudication.

Source reference: paras. 35–40

The principle of kompetenz-kompetenz under Section 16 did not require reference where the Court found, on a prima facie basis, that the dispute was legally non-arbitrable.

Source reference: paras. 35–40
05

Holding

The Court held that Clause 86 contained an arbitration agreement, but the disputes raised by the Applicants were disputes between an individual allottee and a promoter concerning a RERA-covered real estate project and were therefore non-arbitrable.

The Section 11 application was dismissed and no arbitrator was appointed.

Source reference: paras. 46–47

Since the underlying dispute was non-arbitrable, the Section 9 Arbitration Petition was also dismissed.

Source reference: para. 48

The Applicants were nevertheless granted liberty to pursue any appropriate remedy available in law, with all merits of the parties’ claims and defences left open for determination by the competent forum.

Source reference: para. 49
06

Acts & Sections Cited

16 provisions across 2 statutes referred to in this judgment. Each provision opens on LawLens.

Arbitration and Conciliation Act, 19963

Real Estate (Regulation and Development) Act, 2016.13 provisions
Bombay High Court

Original Court PDF

Laxman Mura VaidvsShree Siddivinayak Infrastructure And Realty A Partnership Firm

Bombay High Court · September 21, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment