01Facts
The four petitioners purchased three plots, each admeasuring 0.29.5 Ares (0.73 cents), in Survey No. 314/9 (T.S. No. 14/9A) at Sorathur Road, Thuraiyur, under registered documents dated 09.06.2025 and 01.04.2026.
p. 2 · ¶ 2The land forms part of Detailed Development Plan-4 (DDP-4) of the Thuraiyur Local Planning Area, approved by the Second Respondent under Roc. No. 15298/03/DP-3 dated 29.11.2003.
p. 2 · ¶ 2The petitioners have been in peaceful possession and enjoyment of the property.
p. 3 · ¶ 3The petitioners contend that the land was earmarked in 2003, has not been acquired in the roughly 13 years since, and that the reservation has therefore lapsed under Section 38 of the Tamil Nadu Town and Country Planning Act, 1971.
p. 3 · ¶ 3The petitioners sought a writ of declaration to that effect under Article 226.
p. 1The Special Government Pleader appeared for the respondents.
p. 1The Court permitted a single writ petition to be filed for the four petitioners' plots under W.M.P.(MD) No. 24933 of 2026.
p. 2 · ¶ 1The Court heard both sides and perused the record.
p. 4 · ¶ 4The petition was supported by the Court's earlier decision in W.P.(MD) No. 20277 of 2024 dated 23.09.2024.
pp. 4–6 · ¶ 502Issues
i.1. Whether the reservation of the petitioners' land in DDP-4 of the Thuraiyur Local Planning Area stands released under Section 38 of the TNTCP Act, 1971, where the land was not acquired within three years of the relevant notice and no extension notification has been issued.
pp. 4–6 · ¶ 5 · pp. 6–7 · ¶ 6ii.2. Whether the petitioners are entitled to a direction to the respondents to release the land from the reservation.
p. 7 · ¶ 603Law Applied
The Court relied principally on Sections 37 and 38 of the TNTCP Act, 1971, as extracted in W.P.(MD) No. 20277 of 2024.
pp. 4–6 · ¶ 5Section 37(1) empowers the planning authority, after publication of a notice under Section 26 or 27 of a regional, master, detailed development, or new town plan, to acquire land reserved in such plan, either by agreement or through the Land Acquisition Act, 1894.
p. 4 · ¶ 5Section 37(2) requires a government declaration within three years of such notice, and Section 37(3) governs the acquisition process.
pp. 4–5 · ¶ 5Section 38 provides that if, within three years of the Section 26/27 notice, no declaration under Section 37(2) is published, or the land is not acquired by agreement, the land is "deemed to be released" from its reservation, allotment, or designation.
pp. 5–6 · ¶ 5The proviso to Section 38 permits the Government to extend the period by notification.
p. 6 · ¶ 5The Court relied on the precedent in W.P.(MD) No. 20277 of 2024, which construed these provisions as operating automatically upon expiry of the three-year period absent an extension notification.
p. 6 · ¶ 5Provisions in the judgment · 6
Tamil Nadu Town and Country Planning Act, 1971 Section 38Section 37Section 36Section 26Section 27
Land Acquisition Act, 1894 Section 6
04Reasoning
The Court treated the question as settled by its earlier decision in W.P.(MD) No. 20277 of 2024 and found that decision applicable to the present facts.
p. 6 · ¶ 6The Court observed that the land had not been acquired within the mandatory period under Sections 37 and 38.
pp. 6–7 · ¶ 6The Court further noted that no extension notification under the proviso to Section 38 had been issued.
p. 6 · ¶ 5On that basis, the Court held that the land is deemed released from reservation by operation of law.
pp. 6–7 · ¶ 6The order does not record the date of the Section 26/27 notice for DDP-4, nor does it state whether any Section 37(2) declaration or any extension notification exists. The release is therefore expressed as conditional: the respondents are directed to release the land "if no such notification is issued."
p. 7 · ¶ 6The reasoning rests on the absence of acquisition and the absence of an extension notification within the statutory period, and the 2003 approval date is relevant only as context.
pp. 6–7 · ¶ 605Holding
The Court answered the first issue in the petitioners' favour: non-acquisition within the three-year period under Section 38, with no extension notification, results in the land being deemed released from reservation.
pp. 6–7 · ¶ 6The writ petition is disposed of with a direction that the respondents release the petitioners' land from the reservation if no extension notification under Section 38 has been issued. No costs were awarded. The Court relied throughout on its earlier decision in W.P.(MD) No. 20277 of 2024.
p. 7 · ¶ 6 · p. 7 · ¶ 7 · pp. 4–6 · ¶ 5Original Court PDF