01Facts
The petitioners are assignees of land under assignment orders covering Survey Nos. 244/20, 244/15, 244/22, 244/18 and 244/23
¶ 5 · p. 4They challenged a final notice dated 30.10.2026 issued by the Assistant Divisional Engineer (Highways) for removal of encroachments
¶ 1 · p. 2This is the second round of litigation. In earlier W.P. No. 14772 of 2022, a Division Bench order dated 14.06.2022 directed the authorities to survey the highway property and then proceed with removal of encroachments
¶ 2 · pp. 2–3The survey identified encroachments on highway property. A show cause notice dated 01.10.2026 was issued, the petitioners submitted explanations, and the final notice followed on 30.10.2026
¶ 2 · p. 3The petitioners contended that the authorities were attempting to remove them from their assigned land
¶ 3 · p. 3The learned Additional Government Pleader submitted that the assigned land is not connected with the highway property where encroachments were found, and that removal would be confined to Survey No. 244/1
¶ 4 · p. 3The petitioners sought a writ of certiorarified mandamus quashing the final notice and directing acquisition of the land in accordance with law
cause title · p. 102Issues
i.1. Whether the final notice dated 30.10.2026 is liable to be quashed where the petitioners' assigned lands (Survey Nos. 244/15, 244/18, 244/20, 244/22, 244/23) are not shown to be the encroached land (Survey No. 244/1).
¶ 4–5 · pp. 3–4ii.2. Whether the petitioners have established any right to resist removal of encroachments from highway property following survey, show cause notice and final notice.
¶ 7 · p. 403Law Applied
The Court relied on the Highways Act, under which the authorities are bound to protect highway property and remove encroachments; the order does not specify the particular provision.
¶ 6 · p. 4The Court treated encroachments on highway property as impermissible in all circumstances, since they endanger road users and obstruct free flow of traffic.
¶ 6 · p. 4The Court applied the procedural sequence of survey, show cause notice, opportunity of explanation, and final notice as the framework the authorities had followed.
¶ 2, 7 · pp. 3–4Under Article 226 of the Constitution, the Court examined whether the impugned notice was legally sustainable on the facts, and whether the assignees had established a countervailing right.
¶ 7 · p. 4No precedent is cited in the order.
04Reasoning
The Court compared the assignment orders with the impugned notice. It found that the assignments covered Survey Nos. 244/15, 244/18, 244/20, 244/22 and 244/23, whereas the encroachments were identified in Survey No. 244/1.
¶ 5 · p. 4Accepting the Additional Government Pleader's position that removal would be confined to Survey No. 244/1, the Court held that the notice did not affect the petitioners' assigned land, and that its issuance for road expansion was not infirm.
¶ 5 · p. 4On the question of rights, the Court held that the statutory process had been followed, that the petitioners had been heard, and that they had not established any right to interfere with the final notice.
¶ 7 · p. 405Holding
The Court held that the final notice dated 30.10.2026 required no interference, as the encroachments identified lie in Survey No. 244/1, which is not the land assigned to the petitioners, and the procedure had been duly followed.
¶ 5, 7 · p. 4The authorities were directed to remove the encroachments identified in the highway property.
¶ 7 · p. 4The writ petitions were dismissed without costs, and the connected miscellaneous petitions were closed.
¶ 8 · p. 5Original Court PDF
D.RADHAKRISHNANvsTHE ASSISTANT DIVISIONAL ENGINEER (HIGHWAYS) (C AN
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
