The petitioner, appearing in a writ petition styled as a public interest litigation under Article 226 of the Constitution, sought a writ of mandamus directing Respondents 1 to 4 (the District Collector, Tahsildar, Assistant Director of Mines, and Assistant Engineer, WRO, PWD) to act against persons allegedly removing soil illegally from Periya Yeri in S.No. 77, Ulagankathan Village, Kallakurichi Taluk.
p. 2The petitioner contended that permission for soil removal had been granted in 2023, that the permitted period had expired, and that illegal quarrying was continuing, harming agriculturists and villagers.
¶ 2The learned Additional Government Pleader, relying on written instructions from the District Collector dated 17.11.2026, submitted that illegal quarrying was not occurring and that the lake was being maintained free of quarrying.
¶ 3The Collector's instructions disclosed that an application under Rule 7 of the Tamil Nadu Minor Mineral Concession Rules, 1959, seeking permission to remove ordinary earth for the construction of a new railway BG line (Porpadakurichi–Kallakurichi section), was pending and that no permission had been granted; receipt of the application did not amount to a grant.
¶ 4 · p. 4The Court recorded that no decision had yet been taken on the application.
¶ 502Issues
i.1. Whether illegal quarrying of soil from the Periya Yeri is presently taking place, so as to warrant a mandamus against the official respondents.
¶ 2, 3, 6ii.2. Whether the pending application under Rule 7 of the TNMMCR, 1959, for removal of ordinary earth for the railway project should be processed on its merits, with interim safeguards against illegal quarrying pending its decision.
¶ 4, 5, 603Law Applied
The Court's power was invoked under Article 226 of the Constitution, which permits a writ of mandamus to compel public authorities to perform statutory duties.
p. 2The judgment rests on Rule 7 of the Tamil Nadu Minor Mineral Concession Rules, 1959, which governs permission for the removal of minor minerals, including ordinary earth, and under which the pending application was filed.
¶ 4 · p. 4The Court's reasoning also reflects the principle that a mere receipt or pendency of a permit application does not constitute a grant of permission for extraction, as stated in the Collector's submission and adopted by the Court.
¶ 4 · p. 4 · ¶ 6No judicial precedent is cited in the judgment.
04Reasoning
The Court accepted the Collector's written statement that no illegal quarrying was then occurring and that the only pending matter was an application for the railway project.
¶ 6Because the factual basis for the mandamus (ongoing illegal quarrying) was contradicted by the official statement, the Court did not adjudicate the disputed allegations of illegal extraction, and no direction for enforcement action against any person was issued.
¶ 3, 6Instead, the Court directed the authorities to decide the pending Rule 7 application on its own merits, which addressed the petitioner's underlying concern regarding future extraction without prejudging the application.
¶ 6To protect the lake pending that decision, the Court directed that no illegal quarrying be carried out in the subject lake.
¶ 6The judgment does not expressly analyse Respondents 5 and 6, who were impleaded, nor does it engage with the petitioner's claim that the 2023 permission had lapsed.
05Holding
The Court held, in effect, that no present illegal quarrying was established on the record, and that the application under Rule 7 was pending without any grant of permission.
¶ 6The writ petition was disposed of with a direction to the authorities to process the Rule 7 application on its own merits, and with an interim direction that they ensure no illegal quarrying in the subject lake until a decision is taken. No costs were awarded.