Gujarat High Court
Employment and Labour LawCivil Procedure and Evidence

Restoration after an 18-year delay may be granted for procedural injustice, subject to substantial costs.

BHUPENDRABHAI R BHAGAT vs JYOTI POLYVINYL LTD.

Gujarat High CourtJUDGMENT: August 03, 20263 MIN READSOURCE JUDGMENT
Restoration after an 18-year delay may be granted for procedural injustice, subject to substantial costs.. BHUPENDRABHAI R BHAGAT vs JYOTI POLYVINYL LTD.. Gujarat High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioner-employee challenged the order dated 23 December 2019 passed by the Industrial Tribunal/Labour Court (3), Vadodara, in Misc. Application No. 32 of 2019 arising from Reference (LCV) No. 537 of 1997 and Recovery Application No. 307 of 2014.

Source reference: paras. 5–6; pp. 2–3

The employee’s termination reference had been partly allowed on 10 August 2001, with directions for reinstatement and payment of 50% back wages.

Source reference: paras. 5–6; pp. 2–3

The employer subsequently filed restoration applications in 2005 and 2015, both of which were dismissed for default on 21 February 2005 and 22 August 2015 respectively.

Source reference: paras. 6, 9; pp. 3, 6

In 2019, the employer filed a third restoration application seeking condonation of approximately 18 years’ delay.

Source reference: para. 5; p. 2

The Labour Court condoned the delay but imposed costs of only Rs. 27,000.

Source reference: para. 5; p. 2
02

Issues

Whether the Labour Court was justified in condoning the employer’s delay of approximately 18 years in seeking restoration of the reference proceedings, in the circumstances of the case.

Source reference: paras. 9–11; pp. 5–7

Whether the costs imposed by the Labour Court for condoning the delay were inadequate and liable to be enhanced.

Source reference: paras. 5, 11–12; pp. 2, 7–9

Whether appropriate directions should be issued for expeditious disposal of the restored reference proceedings.

Source reference: para. 12; p. 9
03

Law Applied

The Court applied Rule 26-A of the Industrial Disputes (Gujarat) Rules, 1966, governing applications for setting aside an ex parte award or restoration of proceedings.

Source reference: para. 10; p. 7

The governing principle is that a litigant seeking relief after substantial delay must establish “sufficient cause”; although the expression is not exhaustively defined, it must be assessed on the facts and circumstances of each case.

Source reference: para. 10; p. 7

Where proceedings are concluded without formally closing the relevant stages of cross-examination or evidence, and without giving the affected party proper notice, the resulting award may be treated as ex parte and restoration may be justified.

Source reference: paras. 9–12; pp. 5–9

Delay may nevertheless be balanced by imposing compensatory or deterrent costs, particularly where the opposing workman has been subjected to prolonged and repeated litigation.

Source reference: paras. 9–12; pp. 5–9
04

Reasoning

The High Court accepted that the employer had been negligent, having failed to prosecute its restoration applications filed in 2005 and 2015, and that the delay of 18 years was “huge”.

Source reference: paras. 9, 11; pp. 6–8

The record disclosed a procedural defect in the original adjudication: the Labour Court had neither closed the employee’s further cross-examination nor the employer’s evidence, and had not issued notice before deciding the reference.

Source reference: para. 11; p. 7

These circumstances constituted sufficient cause for restoration despite the delay.

Source reference: para. 11; p. 7

At the same time, the employee had been compelled to contest repeated restoration proceedings and was also facing separate litigation concerning a subsequent termination.

Source reference: paras. 11–12; pp. 8–9

The cost of Rs. 27,000 was therefore disproportionate to the prejudice caused and was considered too meagre.

Source reference: paras. 11–12; pp. 8–9

The Court balanced the employer’s right to an opportunity to contest the reference against the employee’s right to compensation for prolonged litigation by enhancing the costs to Rs. 1,00,000.

Source reference: paras. 11–12; pp. 8–9
05

Holding

The petition was partly allowed.

The High Court upheld the restoration of the reference but modified the order dated 23 December 2019 by increasing the costs payable by the employer from Rs. 27,000 to Rs. 1,00,000.

Source reference: para. 12; p. 9

The employer was directed to deposit the amount within four weeks, failing which the benefit of restoration would not operate.

Source reference: para. 12; p. 9

Upon deposit, the restored reference was to be completed by the Labour Court within two months, with both parties directed to cooperate and avoid unnecessary adjournments.

Source reference: para. 12; p. 9

The deposited amount was directed to be disbursed to the employee after following due process.

Source reference: para. 13; p. 10

The Labour Court was directed to decide the reference independently and without being influenced by the earlier award dated 10 August 2001.

Source reference: para. 13; p. 10
Gujarat High Court

Original Court PDF

BHUPENDRABHAI R BHAGATvsJYOTI POLYVINYL LTD.

Gujarat High Court · August 03, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment