Supreme Court
Arbitration and MediationContract Law

SC: Express contract bar on interest for delayed payments excludes pre-reference interest in arbitration

North Eastern Electric Power Corporation Limited (Neepco) vs Astra Construction Private Limited

Supreme CourtJUDGMENT: September 22, 20263 MIN READSOURCE JUDGMENT
SC: Express contract bar on interest for delayed payments excludes pre-reference interest in arbitration. North Eastern Electric Power Corporation Limited (Neepco) vs Astra Construction Private Limited. Supreme Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

NEEPCO invited tenders for civil works relating to a Gas Turbine Power Project in Tripura; Astra Construction’s tender was accepted and the parties executed a contract containing Clause 54 of the General Conditions of Contract (GCC).

Source reference: para. 3

Disputes arose regarding delay in execution, which the Arbitral Tribunal attributed to NEEPCO. By award dated 05.06.2015, the Tribunal awarded Astra approximately Rs. 3.30 crores, together with pre-reference interest at 12% per annum and pendente lite and future interest at 9% per annum.

Source reference: para. 4

The Commercial Court set aside the award of pre-reference and pendente lite interest, holding that Clause 54 barred interest under Section 31(7) of the Arbitration and Conciliation Act, 1996.

Source reference: para. 5

The Meghalaya High Court reversed that decision, relying on State of U.P. v. Harish Chandra & Co., and restored the interest award.

Source reference: para. 6

NEEPCO appealed to the Supreme Court, principally challenging the restoration of pre-reference interest.

Source reference: para. 7
02

Issues

Whether Clause 54 of the GCC barred the grant of pre-reference interest under Section 31(7)(a) of the Arbitration and Conciliation Act, 1996.

Source reference: paras. 16–21

Whether Clause 54 was materially similar to the clause construed in State of U.P. v. Harish Chandra & Co., or instead to the clauses considered in Sayeed Ahmed & Co. v. State of U.P. and Jaiprakash Associates Ltd. v. THDC-II.

Source reference: paras. 17–20

Whether NEEPCO had waived its right to rely on Clause 54 by failing to raise the objection before the Arbitral Tribunal.

Source reference: para. 22
03

Law Applied

The Court applied Section 31(7)(a) of the Arbitration and Conciliation Act, 1996, under which an arbitral tribunal may award interest for the period between the accrual of the cause of action and the award date “unless otherwise agreed by the parties”.

Source reference: para. 13

Under the 1996 Act, party autonomy permits an express contractual prohibition on interest to exclude the tribunal’s power to grant pre-reference and pendente lite interest, even if the clause does not expressly refer to arbitral jurisdiction.

Source reference: para. 14

Pre-reference interest is governed by substantive law and must derive from an agreement, statute, or recognised mercantile usage; it cannot be founded solely on Section 31(7)(a).

Source reference: para. 14

The Court distinguished Harish Chandra, where the clause was confined to money withheld because of disputes, from Sayeed Ahmed and Jaiprakash Associates (THDC-II), where clauses separately barred interest arising from delay in making payments and therefore operated as complete bars to interest.

Source reference: paras. 17–20

The Court also held that waiver was unavailable because NEEPCO had specifically raised Clause 54 in its Statement of Defence before the Tribunal.

Source reference: para. 22
04

Reasoning

Clause 54 provided that no claim for interest or damages would be entertained in respect of money lying with NEEPCO due to a dispute, or in respect of “any delay” by the Engineer-in-Charge in making periodical or final payments, “or in any other respect whatsoever”.

Source reference: para. 16

The Court held that the reference to delay in making payments was an independent and additional bar, rather than merely a description of disputes concerning withheld money.

Source reference: paras. 18–19

Accordingly, unlike the clause in Harish Chandra, Clause 54 expressly covered interest arising from delayed payment, whether or not the delay was connected with a dispute.

Source reference: para. 20

Its wording therefore aligned with the clauses upheld in Sayeed Ahmed and THDC-II, and excluded the Tribunal’s authority to award pre-reference interest under Section 31(7)(a).

Source reference: para. 20

The record further established that NEEPCO had pleaded the contractual bar before the Tribunal, defeating Astra’s waiver argument.

Source reference: para. 22
05

Holding

The Supreme Court held that Clause 54 barred the award of pre-reference interest and that the Arbitral Tribunal exceeded the limits of its jurisdiction under Section 31(7)(a) by granting such interest.

The High Court erred in treating Clause 54 as equivalent to the narrower clause in Harish Chandra.

Source reference: para. 23

The appeal was allowed to the extent that the High Court’s restoration of pre-reference interest was set aside; there was no order as to costs.

Source reference: paras. 23–24
06

Acts & Sections Cited

5 provisions across 2 statutes referred to in this judgment. Each provision opens on LawLens.

Arbitration and Conciliation Act, 19963

Interest Act, 19782

Supreme Court

Original Court PDF

North Eastern Electric Power Corporation Limited (Neepco)vsAstra Construction Private Limited

Supreme Court · September 22, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment