Delhi High Court

Scope of Judicial Review Under Section 11 is Confined to Prima Facie Existence of Arbitration Agreement

M/S Awadh Engineers Pvt. Ltd. vs M/S Dalmia Cement (Bhart) Ltd

Delhi High CourtJUDGMENT: May 11, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Petitioner and Respondent entered into a Service Agreement dated 16.01.2023, which contained an arbitration clause (Clause 28) designating New Delhi as the seat

Source reference: p.1

Following disputes, the Petitioner invoked the arbitration clause via a Legal Notice dated 08.10.2025 under Section 21 of the Arbitration and Conciliation Act, 1996

Source reference: p.2

The Petitioner subsequently approached the High Court under Section 11 of the Act for the appointment of a Sole Arbitrator

Source reference: p.1

The Respondent expressed no objection to the referral of disputes to arbitration

Source reference: p.2
02

Issues

1. Whether the Court should appoint an arbitrator based on the prima facie existence of an arbitration agreement under Section 11 of the Act

Source reference: p.2, para 4

2. Whether the scope of judicial scrutiny under Section 11 is limited solely to examining the existence of the agreement rather than its validity or the merits of the dispute

Source reference: p.3, para 4
03

Law Applied

Section 11(6) of the Arbitration and Conciliation Act, 1996, regarding the appointment of arbitrators

Source reference: p.1

The Court relied heavily on the precedent set by the Supreme Court in SBI General Insurance Co. Ltd. v. Krish Spinning (2024), which streamlined judicial intervention by overruling previous standards set in Vidya Drolia

Source reference: p.2-4

The court also referenced the seven-judge bench decision in Interplay Between Arbitration Agreements under Arbitration Act, 1996 & Stamp Act, 1899, In re, which established that the referral court's role is confined to a prima facie examination of the existence of the arbitration agreement

Source reference: p.3-4
04

Reasoning

The Court noted that the legal position regarding Section 11 is now res integra, focusing on "minimal judicial interference"

Source reference: p.2, 4

It reasoned that under Section 11(6-A), the court’s role is facilitative and limited to weeding out non-existent agreements without embarking on "laborious enquiry" into issues like "accord and satisfaction"

Source reference: p.3-4

The Court applied these principles to the present facts, noting that Clause 28 of the Agreement explicitly provided for arbitration. Since a Section 21 notice was served and the Respondent consented to the referral, the Court found its duty was merely to give effect to the parties' mutual intention to arbitrate

Source reference: p.5-6

The Court emphasized that all contested factual and legal issues remain within the exclusive jurisdiction of the Arbitral Tribunal under the principle of competence-competence

Source reference: p.4-5
05

Holding

The Court allowed the petition, holding that the existence of the arbitration agreement was prima facie established

The Court appointed Ms. Nandita Rao, Senior Advocate, as the Sole Arbitrator to adjudicate the disputes valued at approximately Rs. 40 Lakhs. The arbitrator was directed to charge fees as per the Fourth Schedule and file disclosures under Section 12(2). All rights and contentions of the parties were kept open for the tribunal's adjudication

Source reference: p.6
Delhi High Court

Original Court PDF

M/S Awadh Engineers Pvt. Ltd.vsM/S Dalmia Cement (Bhart) Ltd

Delhi High Court · May 11, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment