Facts
The appellants owned land in the Revenue Estate of Village Bakkarwala, Delhi, acquired pursuant to the same Section 4 notification dated 17 June 2005, Section 6 notification dated 31 May 2006, and Award No. 1/DC(W)/2006-07.
Source reference: p.3, paras 2–3The Land Acquisition Collector initially determined compensation at ₹15,70,000 per acre.
Source reference: p.3, paras 2–3In a reference filed by another landowner, Kailashwati v. Union of India, the compensation was enhanced to ₹20,35,255 per acre by judgment dated 26 April 2010.
Source reference: p.3, para 4The appellants consequently sought re-determination under Section 28A of the Land Acquisition Act, 1894, which the Collector allowed on 29 May 2013 on the basis of Kailashwati.
Source reference: p.4, para 8Subsequently, in Jamna v. Union of India, decided by the High Court on 8 July 2011, compensation for land acquired under the same notification and award was further enhanced to ₹23,93,227.20 per acre.
Source reference: p.4, paras 6–9; p.7, para 20The appellants sought the benefit of this subsequent enhancement through references under Section 28A(3).
Source reference: p.5, paras 10–12The Additional District Judge dismissed their claims, holding that the appellants had already obtained re-determination under Section 28A and could not seek a second re-determination based on a later appellate judgment.
Source reference: p.5, paras 10–12Issues
Whether a landowner whose compensation has already been re-determined under Section 28A of the Land Acquisition Act on the basis of a Reference Court award can seek further re-determination on the basis of a subsequent enhancement granted by the High Court in respect of land acquired under the same notification and award?
Source reference: p.6, paras 14–16; p.9, paras 21–23Whether the appellants were entitled to the enhanced compensation awarded in Jamna, notwithstanding their earlier receipt of compensation under Section 28A based on Kailashwati?
Source reference: p.7, para 20; p.10, paras 24–26Law Applied
Section 28A of the Land Acquisition Act, 1894 permits re-determination of compensation for similarly situated landowners whose lands were acquired under the same notification, on the basis of an award enhancing compensation in a reference proceeding.
Source reference: no citationSection 28A(3) provides a mechanism for seeking a reference where the Collector’s re-determination is disputed.
Source reference: no citationThe Court relied on Andanayya v. Deputy Chief Engineer, 2026 SCC OnLine SC 482, which held that a second application under Section 28A is maintainable where a subsequent appellate judgment further enhances compensation; an earlier re-determination and receipt of compensation do not bar such further relief.
Source reference: p.9, paras 21–23The doctrine of merger applies, and the benefit of enhancement granted by the High Court or Supreme Court must extend to similarly situated landowners.
Source reference: p.9, paras 21–23The Court distinguished Girimallappa v. Special Land Acquisition Officer, (2012) 11 SCC 548, because the present question concerned further enhancement after an earlier Section 28A application had already been allowed, not the appellants’ initial eligibility under Section 28A.
Source reference: p.9, paras 21–23The statutory objective is to secure parity and equality among similarly situated landowners; estoppel, waiver, or acquiescence cannot defeat the statutory entitlement.
Source reference: p.10, para 23Reasoning
The appellants’ lands were covered by the same acquisition notification and award as the lands considered in Kailashwati and Jamna.
Source reference: p.9, para 21Their initial Section 28A applications had already been allowed, and those orders had not been challenged by the respondents.
Source reference: p.9, para 21; p.10, para 25Therefore, the Additional District Judge erred in treating the earlier re-determination as a bar to claiming the later appellate enhancement.
Source reference: no citationApplying Andanayya, the Court held that the subsequent enhancement in Jamna represented the final determination of compensation for similarly situated landowners and had to be extended to the appellants.
Source reference: no citationThe reasoning that Section 28A primarily benefits poor or inarticulate landowners could not defeat the appellants’ entitlement, particularly because their eligibility under Section 28A had already been accepted and had attained finality.
Source reference: p.9, para 21; p.10, paras 23–25Holding
The High Court allowed all three appeals.
It held that the appellants were entitled to the further enhanced compensation awarded in Jamna v. Union of India, namely ₹23,93,227.20 per acre, notwithstanding the earlier re-determination under Section 28A based on Kailashwati.
Source reference: p.10, paras 24–27The impugned orders of the Additional District Judge were consequently set aside to that extent, with consequential reliefs granted.
Source reference: p.11, para 27Pending applications were also disposed of.
Source reference: p.11, para 27Acts & Sections Cited
6 provisions across 1 statute referred to in this judgment. Linked provisions open on LawLens.
Land Acquisition Act, 18946
Original Court PDF
Sky High Agro Expo Pvt LtdvsUnion Of India & Anr
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
