Facts
The Petitioner filed a petition under Section 11(6) of the Arbitration and Conciliation Act, 1996, seeking appointment of a sole arbitrator for disputes arising out of a contract dated 21 November 2017 concerning consultancy services for feasibility studies and Detailed Project Reports relating to road stretches in Bihar.
Source reference: p.1Clauses 9.2 of the GCC and SCC contained the arbitration agreement.
Source reference: p.1The Petitioner invoked the arbitration clause by notice dated 26 December 2024 under Section 21 of the Act.
Source reference: p.2The Respondents did not dispute the existence of a valid arbitration agreement or the maintainability of the petition.
Source reference: p.2During the proceedings, the Respondents expressed willingness to explore an amicable settlement.
Source reference: p.3Issues
1. Whether a sole arbitrator should be appointed under Section 11(6) of the Arbitration and Conciliation Act, 1996, for adjudication of the disputes arising from the contract dated 21 November 2017.
Source reference: pp.1–22. Whether the parties should be granted time to explore an amicable settlement before the arbitrator enters upon the reference.
Source reference: p.3Law Applied
The Court applied Section 11(6) of the Arbitration and Conciliation Act, 1996, under which the Court may appoint an arbitrator where the agreed appointment procedure has failed or requires judicial intervention.
Source reference: p.2At the Section 11 stage, the Court’s enquiry is confined to examining the prima facie existence of a valid arbitration agreement.
Source reference: p.2Section 21 governs commencement of arbitral proceedings through a request for reference to arbitration, while Section 12(2) requires the appointed arbitrator to furnish the prescribed disclosure before proceeding with the arbitration.
Source reference: pp.2–3The arbitration agreement contained in Clauses 9.2 of the GCC and SCC governed the parties’ disputes.
Source reference: p.1Reasoning
The Court found that the contract contained a prima facie valid arbitration agreement and that the Petitioner had duly invoked it by notice dated 26 December 2024.
Source reference: pp.1–2Since the Respondents raised no objection regarding the existence of the arbitration clause or the maintainability of the petition, there was no impediment to appointing a sole arbitrator under Section 11(6).
Source reference: p.2The Court nevertheless permitted the parties to pursue settlement negotiations for three weeks, directing that the arbitrator enter upon the reference only after four weeks from the date of the order.
Source reference: p.3It preserved the parties’ right to raise objections concerning arbitrability and jurisdiction before the arbitrator.
Source reference: p.3Holding
The petition was allowed and Mr. Amit George, Advocate, was appointed as the sole arbitrator to adjudicate the disputes, subject to furnishing the disclosure required under Section 12(2) within four weeks of entering upon the reference.
The arbitration was directed to be conducted under the rules and aegis of the Delhi International Arbitration Centre, with fees payable according to the DIAC Schedule of Fees.
Source reference: p.3The parties were granted three weeks to explore an amicable settlement, and the arbitrator was directed to enter upon the reference after four weeks from the order dated 14 September 2026.
Source reference: p.3The petition and all pending applications were disposed of accordingly.
Source reference: p.4Acts & Sections Cited
3 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.
Arbitration and Conciliation Act, 19963
Original Court PDF
Technocrats Advisory Services Private LimitedvsMinistry Of Road Transport And Highways & Anr.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
