01Facts
The Appellant-University had entered into an agreement with the Respondent for renovation and repair works at its Lodhi Road Campus.
Disputes arose, and an arbitral award was rendered on 2 September 2024.
The Respondent subsequently filed a request under Section 33 of the Arbitration and Conciliation Act, 1996 (“A&C Act”) seeking correction of an alleged typographical error and consideration of additional items.
pp. 2–3 · ¶ 4–7That request was disposed of by the Sole Arbitrator on 19 October 2024.
pp. 2–3 · ¶ 4–7The University thereafter filed objections under Section 34 of the A&C Act.
The electronic filing record showed that the case entry was initiated on 3 January 2025, while the e-file was finally submitted on 19 February 2025.
pp. 6–7 · ¶ 19–23The Commercial Court treated 19 February 2025 as the date of filing and dismissed the Section 34 petition as barred by limitation under Section 34(3).
p. 3 · ¶ 8The University challenged that order in the present appeal.
p. 1 · ¶ 102Issues
i.1. Whether the limitation period under Section 34(3) of the A&C Act was required to be computed from the date of the original arbitral award, 2 September 2024, or from the date on which the Section 33 request was disposed of, 19 October 2024?
pp. 4–6 · ¶ 12–18ii.2. Whether the Section 34 objections were instituted on 3 January 2025, when the electronic case entry was initiated, or on 19 February 2025, when the e-file was finally submitted?
pp. 6–8 · ¶ 19–24iii.3. Whether the objections were liable to be rejected on the additional grounds that the order disposing of the Section 33 request was not filed or that the objections were unsigned?
pp. 3, 8–9 · ¶ 10, 27–2803Law Applied
Section 34(3) of the A&C Act prescribes three months for filing an application to set aside an arbitral award; where a request under Section 33 has been made, limitation runs from the date on which that request is disposed of.
p. 4 · ¶ 13The proviso permits the Court to entertain the application for a further period of thirty days upon sufficient cause being shown, but not thereafter.
p. 4 · ¶ 13In Ved Prakash Mithal and Sons v. Union of India, 2018 SCC OnLine SC 3181, the Supreme Court held that disposal of a Section 33 request—whether by allowing or dismissing it—determines the commencement of limitation under Section 34(3).
pp. 4–5 · ¶ 14This principle was reaffirmed in National Highway Authority of India v. T. Younis, 2026 SCC OnLine SC 1060.
p. 5 · ¶ 15The Court also noted P. Radha Bai v. P. Ashok Kumar, (2019) 13 SCC 445, which holds that the thirty-day extension under the proviso is subject to an absolute outer limit and cannot be extended thereafter.
p. 7 · ¶ 25Provisions in the judgment · 2 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 33Section 34
04Reasoning
The Court held that the Section 33 request was formally invoked and disposed of on 19 October 2024.
pp. 5–6 · ¶ 16–18Applying Section 34(3) and the principles in Ved Prakash Mithal and T. Younis, limitation therefore commenced from 19 October 2024, rather than from the date of the original award, 2 September 2024.
pp. 5–6 · ¶ 16–18The Court then examined the electronic filing record and found that it separately recorded initiation of the Section 34 case on 3 January 2025 and final submission of the e-file on 19 February 2025.
p. 6 · ¶ 19–21Since the earlier date fell within the three-month period, the Court treated 3 January 2025 as the date of institution.
pp. 6–8 · ¶ 22–24, 29–30It rejected the Commercial Court’s failure to consider that entry and held that the later date of final submission could not, in the circumstances, determine limitation.
pp. 6–8 · ¶ 22–24, 29–30The objections concerning non-filing of the Section 33 disposal order and the alleged lack of signature could not sustain the dismissal: the former was inconsistent with the statutory starting point under Section 34(3), while the latter was not the basis of the Commercial Court’s order.
pp. 8–9 · ¶ 27–2805Holding
The High Court allowed the appeal and set aside the Commercial Court’s order dated 7 January 2026.
pp. 9–10 · ¶ 29–35It held that the Section 34 objections were instituted on 3 January 2025 and were therefore within the prescribed limitation period computed from 19 October 2024.
pp. 9–10 · ¶ 29–35O.M.P. (COMM.) No. 11/2025 was restored to its original number for adjudication on merits, with the parties directed to appear before the Commercial Court on 17 September 2026.
p. 10 · ¶ 31–35The High Court expressly left all merits-related contentions open and expressed no opinion on them.
p. 10 · ¶ 31–35Original Court PDF
Dr B R Ambedkar University DelhivsSwastik Constructions Company
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
