Gujarat High Court
Arbitration and MediationCivil Procedure and Evidence

Section 37 courts cannot reappreciate arbitral merits absent patent illegality, perversity, or public-policy violation.

VYARA NAGARPALIKA vs JAGAJI CONSTRUCTION COMPANY

Gujarat High CourtJUDGMENT: September 09, 20263 MIN READSOURCE JUDGMENT
Section 37 courts cannot reappreciate arbitral merits absent patent illegality, perversity, or public-policy violation.. VYARA NAGARPALIKA vs JAGAJI CONSTRUCTION COMPANY. Gujarat High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

Jagaji Construction Company was engaged by Vyara Nagarpalika for works relating to the deepening and development of a lake, including excavation, pitching, foot-over bridges, an inlet gate and a spillway.

Source reference: no citation

Disputes arose regarding payment of extra items, completion of work, security deposit, delay and alleged abandonment of the contract.

Source reference: no citation

The arbitral tribunal, by a majority award dated 01.01.2010 as recorded in the judgment, awarded ₹43,65,190 towards claims, ₹49,79,330 as interest up to the date of the award, and ₹5,00,000 towards arbitration costs, with 18% post-award interest.

Source reference: para. 2; p. 14

The Municipality challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996, contending that it was unsupported by evidence, vague and perverse. The challenge was dismissed. The Municipality thereafter preferred the present appeal under Section 37 of the Act.

Source reference: paras. 2–3

The arbitral tribunal had conducted a site visit and recorded observations concerning the foot-over bridges, pitching, railing, inlet gate and non-execution of the spillway.

Source reference: paras. 6–9; pp. 3–6
02

Issues

Whether the appellant was denied a reasonable opportunity to cross-examine the claimant before the arbitral tribunal?

Source reference: para. 4

Whether the majority arbitral award was unsupported by evidence, perverse, vague or otherwise vitiated by patent illegality, violation of public policy or non-compliance with substantive law?

Source reference: paras. 3, 5, 13–15

Whether the High Court, exercising appellate jurisdiction under Section 37 of the Arbitration and Conciliation Act, 1996, could reappreciate the merits and evidence considered by the arbitral tribunal?

Source reference: para. 5

Whether the appellant was entitled to interference with the award or continuation of security furnished by the respondent for withdrawal of the deposited award amount?

Source reference: paras. 16–19
03

Law Applied

The Court applied Sections 34 and 37 of the Arbitration and Conciliation Act, 1996.

Source reference: no citation

A Section 37 court exercises limited appellate supervision over an order upholding or setting aside an arbitral award and cannot reassess the merits of the award or substitute its own view merely because another view is possible.

Source reference: para. 5

Interference is warranted only where the award discloses patent illegality, perversity, violation of public policy or a fundamental procedural failure.

Source reference: paras. 3, 13–15

A party cannot claim a right of cross-examination where the opposing party has not filed an affidavit or otherwise led oral evidence requiring cross-examination.

Source reference: para. 4

The tribunal also relied on the principle that, where time is not treated as essential or work remains incomplete, the employer must provide appropriate notice and an opportunity to complete the balance work before terminating the contract; the tribunal referred in this context to the Supreme Court decision reported in AIR 1997 SC 720.

Source reference: para. 11
04

Reasoning

The Court rejected the Municipality’s cross-examination objection because the claimant had not filed an affidavit of oral evidence; consequently, there was no oral testimony requiring cross-examination.

Source reference: para. 4

On the merits, the Court noted that the tribunal had considered the parties’ pleadings and evidence, verified the work through a site visit and provided findings on the certified measurements, outstanding payments, security deposit, delay and alleged abandonment.

Source reference: paras. 6–12

The tribunal found that the deepening work and substantial components of the project had been completed, that the spillway had not been constructed even by the date of the site inspection, and that the Municipality had not contemporaneously called upon the contractor to complete the alleged balance work or taken contractual action for abandonment.

Source reference: para. 9; pp. 5–6

These findings supported the conclusion that the termination was illegal and that the Municipality was responsible for the prolonged period and consequential overhead claim.

Source reference: paras. 7–12

Since the appellant’s objections substantially invited reconsideration of the evidence and merits, they fell outside the restricted scope of Section 37.

Source reference: paras. 5, 13–15

The Court found no patent illegality, perversity, violation of public policy or denial of procedural fairness in the award.

Source reference: paras. 5, 13–15
05

Holding

The High Court held that the Municipality failed to establish any ground for interference under Section 37 of the Arbitration and Conciliation Act, 1996.

The majority award was found to be reasoned, evidence-based and plausible, and the appeal was accordingly dismissed.

Source reference: para. 15

In view of the dismissal, the Court directed the Registrar General to return the original bank-guarantee documents furnished by the respondent for withdrawal of the amount deposited by the appellant, upon proper identification and acknowledgment.

Source reference: paras. 16–19
06

Acts & Sections Cited

3 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.

Arbitration and Conciliation Act, 19963

Gujarat High Court

Original Court PDF

VYARA NAGARPALIKAvsJAGAJI CONSTRUCTION COMPANY

Gujarat High Court · September 09, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment