Facts
The Kulgaon Badlapur Municipal Council issued a tender for appointment of a Project Management Consultant to prepare a Detailed Project Report for construction of 3,000 tenements under the JNNURM-BSUP/PMAY scheme.
Source reference: no citationM/s. Sparsh Pratishthan was selected as the lowest bidder, and the parties executed an agreement dated 6 September 2016.
Source reference: p. 2 / para. 4Disputes arose when the Municipal Council allegedly failed to release payments despite the Respondent having performed its contractual obligations.
Source reference: no citationThe Respondent invoked arbitration.
Source reference: no citationBy an award dated 15 February 2024, the Sole Arbitrator partly allowed the Respondent’s claim, rejected the Appellant’s counterclaim and set-off, and directed payment of ₹6,72,96,000 with interest at 12% per annum, along with ₹6,50,000 towards arbitration costs.
Source reference: p. 2 / para. 4The Municipal Council’s application under Section 34 of the Arbitration and Conciliation Act, 1996 was dismissed by the District Judge-2, Kalyan, on 29 June 2026.
Source reference: p. 2 / para. 5The Municipal Council consequently preferred the present appeal under Section 37.
Source reference: p. 2 / para. 6Issues
Whether the arbitral award was liable to be set aside on the ground that the Respondent had not completed its contractual obligations and was therefore not entitled to the entire awarded amount.
Source reference: p. 3 / para. 7Whether the subsequent agreement dated 5 November 2021 superseded or altered the parties’ obligations under the agreement dated 6 September 2016, and whether the Respondent’s alleged non-compliance with the subsequent agreement invalidated the award.
Source reference: p. 3 / para. 7Whether the High Court, exercising appellate jurisdiction under Section 37, could re-appreciate the evidence or adopt a different interpretation of the contractual documents.
Source reference: p. 5 / paras. 10–11Law Applied
The Court applied Sections 34 and 37 of the Arbitration and Conciliation Act, 1996, which impose narrow limits on judicial interference with arbitral awards.
Source reference: p. 5 / para. 11A court exercising jurisdiction under Section 37 does not sit as an ordinary appellate court on the merits of the award; it examines whether the Section 34 court acted within the statutory limits.
Source reference: p. 5 / para. 11Interference is warranted only where the Section 34 court exceeded its jurisdiction, failed to exercise jurisdiction lawfully, or where the award is palpably perverse or unreasonable.
Source reference: p. 5 / para. 11Relying on M.P. Road Development Corporation Ltd. v. Jabalpur Corridor (P) Ltd., 2026 SCC OnLine SC 1001, the Court reiterated that the arbitral tribunal is ordinarily the final authority on appreciation of evidence and that concurrent findings under Sections 34 and 37 deserve substantial deference.
Source reference: p. 5 / para. 11Reasoning
The Court found that the Respondent had performed its obligations under the agreement dated 6 September 2016 and that arbitration was invoked only after the Municipal Council failed to release the Respondent’s legitimate dues.
Source reference: p. 5 / para. 9The Arbitrator had specifically recorded that the agreement dated 5 November 2021 was never acted upon, defeating the Appellant’s contention that it superseded the earlier agreement or governed the Respondent’s entitlement.
Source reference: p. 5 / para. 9The Appellant’s remaining objections sought reconsideration of the evidence and contractual interpretation already undertaken by the Arbitrator and the Section 34 court.
Source reference: p. 5 / paras. 10–12Such re-appreciation was impermissible under the limited scope of Section 37, particularly in the absence of any legal error, perversity, or jurisdictional failure.
Source reference: p. 5 / paras. 10–12Holding
The High Court held that neither the arbitral award dated 15 February 2024 nor the judgment dated 29 June 2026 disclosed any error of law or fact warranting interference under Section 37.
The appeal was dismissed as devoid of merit, thereby confirming the award directing the Municipal Council to pay ₹6,72,96,000 with 12% per annum interest and ₹6,50,000 towards arbitration costs.
Source reference: p. 2 / para. 4; p. 6 / para. 13The accompanying Interim Application was disposed of as infructuous.
Source reference: p. 6 / para. 14Acts & Sections Cited
2 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.
Arbitration and Conciliation Act, 19962
Original Court PDF
Kulgaon Badlapur Municipal Corporation Through Its Chief OfficervsM/S Sparsh Pratisthan Through Its President Kedar Dawalbhkta
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
