Facts
The Government of Uttar Pradesh initiated acquisition of 1,857.8871 hectares of land across fourteen villages for Stage-2, Phase-2 and Phase-3 of the Noida International Airport project at Jewar
Source reference: para 3.1, 3.5The project is implemented via a Public-Private Partnership (PPP) model involving Noida International Airport Limited (NIAL) and Zurich Airport International AG
Source reference: para 3.2A Social Impact Assessment (SIA) was conducted and approved by an Expert Group and the State Government
Source reference: para 3.6–3.9Consent from 73.02% of affected families was recorded
Source reference: para 3.10Preliminary notifications under Section 11 were issued on 11.04.2025, and a Section 19 declaration was made on 24.10.2025
Source reference: para 3.13, 3.19Petitioners challenged the notifications primarily regarding the displacement of village abadi (residential) land, alleging lack of requisite consent, procedural irregularities, and violation of food security norms
Source reference: para 4, 4.2Issues
1. Whether the mandatory 70% consent threshold for PPP projects under Section 2(2) was satisfied.
Source reference: para 6.42. Whether the acquisition of irrigated multi-cropped land violated the food security safeguards under Section 10.
Source reference: para 6.103. Whether the conduct of parallel proceedings under Sections 15 and 16 vitiated the acquisition process.
Source reference: para 6.74. Whether the declaration under Section 19(2) identifying a "resettlement area" constituted an illegal expansion of the acquisition without a Section 11 notification.
Source reference: para 6.9Law Applied
The court applied the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 ("Act, 2013") and the U.P. Rules, 2016.
Source reference: no citationSection 2(2) mandates 70% consent from "affected families" (defined broadly in Section 3(c)) for PPP projects
Source reference: para 6.2.1Section 10 restricts the acquisition of multi-cropped land to a notified limit (5% for the district) to safeguard food security
Source reference: para 6.10Section 15 provides the right to object, while Section 16 mandates the R&R scheme
Source reference: para 6.6, 6.7The court relied on Kichhu Ram v. State of U.P. [2019 SCC OnLine All 5071] regarding consent computation
Source reference: para 6.4.3The court relied on Ramniklal N. Bhutta v. State of Maharashtra [AIR 1997 SC 1236] regarding the balancing of private vs. public interest in infrastructure
Source reference: para 6.21.1Reasoning
The Court found that the consent of 73.02% of "affected families" met the statutory 70% requirement; it clarified that the unit of measurement is the "family" across the project, not village-wise landholdings
Source reference: para 6.4.1, 6.4.2Regarding food security, the court noted that the total acquisition remained within the 5% net sown area limit for the district, and petitioners failed to provide documentary evidence (e.g., Khasras) to prove the land was irrigated multi-crop
Source reference: para 6.10.2, 6.10.3The Court rejected the argument against parallel proceedings, ruling that Sections 15 and 16 are designed to operate concurrently to meet the 12-month mandatory timeline in Section 19
Source reference: para 6.7.2Furthermore, the land identified in Schedule-B of the Section 19 declaration was held to be a mandatory identification of a "resettlement area" under Section 19(2), not a new acquisition for the project itself
Source reference: para 6.9.1The court also distinguished Kolkata Municipal Corporation v. Bimal Kumar Shah [2024 5 SCR 831], noting that unlike the vacuum in that case, the Act, 2013 provides a comprehensive procedural code that was meticulously followed here
Source reference: para 6.16.1Holding
The Court dismissed the challenge to the acquisition, holding that all statutory and constitutional requirements (including Article 300-A) were satisfied
It directed that possession of abadi land shall only be taken after the passing of R&R awards and the actual handing over of developed relocation plots to displaced families, as per the State's undertaking
Source reference: para 8.1(a)Petitioners were granted liberty to pursue compensation disputes before the Reference Authority under Section 64
Source reference: para 8.1(b)All three writ petitions were disposed of accordingly
Source reference: para 8.1Original Court PDF
Vijay Pal Singh And 12 OthersvsState Of U.P. And 6 Others
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in