Facts
The petitioners were tenants in structures acquired by the Dedicated Freight Corridor Corporation of India Ltd. (DFCCIL) for the Dedicated Freight Corridor Project at Alibag, District Raigad.
Source reference: para. 2The Deputy Commissioner (Rehabilitation), Konkan Division, allowed the petitioners’ appeals on 16 June 2022 and held them eligible for rehabilitation compensation; DFCCIL’s review applications were rejected.
Source reference: paras. 5–7Thereafter, the competent authority passed a reasoned order dated 6 November 2025 determining compensation of Rs. 14,17,000 for each petitioner.
Source reference: para. 8DFCCIL and the competent authority initially directed the concerned bank to transfer Rs. 10,00,000 to each petitioner, but DFCCIL subsequently objected that the petitioners, being tenants, were entitled only to three months’ notice and Rs. 10,000 as shifting allowance under its 2015 Entitlement Matrix.
Source reference: paras. 9–10Despite the competent authority’s clarification that the petitioners’ eligibility and entitlement had been approved under the applicable statutory framework, DFCCIL did not disburse the compensation, leading to the writ petitions.
Source reference: para. 11Issues
Whether tenants of acquired structures fall within the definition of “affected family” and are entitled to rehabilitation and resettlement compensation under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013?
Source reference: paras. 18–20Whether DFCCIL could rely on its 2015 Entitlement Matrix, based on its 2012 Rehabilitation and Resettlement Plan, to deny compensation determined under the Act of 2013?
Source reference: paras. 12–16, 22–23Whether the Government Resolution dated 22 May 2018 justified restricting the petitioners’ compensation to the amount payable to the owners of the structures?
Source reference: paras. 17, 24Whether the petitioners were entitled to statutory interest for delayed payment of the compensation?
Source reference: paras. 26–29Law Applied
The Court applied Section 3(c)(ii) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, which expressly includes tenants, including tenants under any form of tenancy, within the definition of an “affected family” where their primary source of livelihood is affected by acquisition.
Source reference: para. 18Under Section 31, the Collector must pass a Rehabilitation and Resettlement Award for each affected family in accordance with the entitlements in the Second Schedule.
Source reference: para. 18The Second Schedule provides rehabilitation and resettlement entitlements in addition to the compensation under the First Schedule.
Source reference: para. 19Administrative instructions or an internal entitlement matrix cannot override statutory rights under the Act of 2013.
Source reference: para. 23Further, Section 108 recognises the affected family’s right to opt for better compensation and rehabilitation benefits where more beneficial relief is available.
Source reference: para. 24Under Section 80, delayed payment attracts interest at 9% per annum for the first year from the date of possession and 15% per annum thereafter.
Source reference: para. 27Reasoning
The Court held that the petitioners undisputedly occupied the acquired structures as tenants and therefore fell within Section 3(c)(ii) of the 2013 Act.
Source reference: para. 20Their eligibility had already been conclusively determined by the appellate authority, and DFCCIL’s review applications had failed.
Source reference: para. 21The competent authority subsequently applied the statutory scheme and quantified the compensation at Rs. 14,17,000 per petitioner.
Source reference: no citationDFCCIL’s reliance on its 2015 Entitlement Matrix and the 2012 Rehabilitation and Resettlement Plan was rejected because those internal or administrative arrangements could not prevail over the statutory entitlements under the Act of 2013.
Source reference: paras. 22–23The Court also held that the State Government’s 2018 Resolution could not be used to deny the higher compensation available under the Act, particularly because the Resolution itself recognised that the higher statutory relief would prevail.
Source reference: para. 24Given DFCCIL’s belated and inconsistent objection—after it had jointly instructed the bank to disburse a substantial portion of the compensation—the Court found the delay unjustified and awarded statutory interest under Section 80.
Source reference: paras. 28–29Holding
The writ petitions were allowed.
The Court directed that each petitioner be paid Rs. 14,17,000, together with interest under Section 80 of the 2013 Act—9% per annum for the first year from the date of possession and 15% per annum thereafter.
Source reference: paras. 30–31Since the principal amounts had already been deposited by DFCCIL, they were ordered to be disbursed within two weeks.
Source reference: para. 32The competent authority was directed to calculate the interest within four weeks, communicate the calculation to DFCCIL within one further week, and DFCCIL was directed to deposit the interest amount within two weeks thereafter; the competent authority was then to disburse the interest to the petitioners within one week.
Source reference: paras. 32–34Rule was made absolute in those terms.
Source reference: para. 35Acts & Sections Cited
6 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.
Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 20136
Original Court PDF
Heena Suhas NiromkarvsThe Chief General Manager Dedicated Fright Corridor Corporation And Ors
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
