01Facts
The petitioner worked as a Class-IV employee in a school run by the respondents from 1990. Her services were terminated with effect from 01.09.2003 without following the procedure under the Industrial Disputes Act, 1947
¶ 2.1She raised a dispute before the Conciliation Officer, which was referred to the Labour Court, Bhavnagar, as Reference (LCB) No. 15 of 2012. A parallel petitioner's claim was referred as Reference (LCB) No. 18 of 2012
¶ 3.1The Labour Court's award dated 10.03.2023 granted a lump-sum payment of Rs. 30,000 in each reference
¶ 2.1, 3.1The petitioner restricted her prayer to enhancement of compensation and did not press for reinstatement with back wages
¶ 4The matter was taken up for final disposal by consent
¶ 5The petitioners relied on State of U.P. v. Krishna Murari Sharma (2025 INSC 1500) and on a Division Bench decision of this Court in Bhikhabhai Fatabhai Solanki v. Executive Engineer, Narmada Project Canal System (LPA No. 908 of 2023, dated 09.05.2024), and sought Rs. 3,00,000 per petitioner
¶ 7, 7.1The respondents opposed enhancement relying on Prabhakar v. Joint Director, Sericulture Department (AIR 2016 SC 2984), arguing an approximately eight-year delay rendered the claim stale
¶ 8The respondents' counsel fairly stated they had no objection to maintaining Rs. 30,000
¶ 902Issues
i.1. Whether the lump-sum compensation of Rs. 30,000 awarded by the Labour Court requires enhancement in the facts and circumstances of the case.
¶ 9ii.2. Whether the delay of about eight years in raising the claim renders the dispute stale, such that the reference and the relief granted should be set aside in light of Prabhakar.
¶ 8, 10iii.3. Whether the Court can examine the legality of the unchallenged finding of breach of Section 25F of the Industrial Disputes Act, 1947, in petitions seeking only enhancement of compensation.
¶ 1003Law Applied
The Court relied on Section 25F of the Industrial Disputes Act, 1947, the breach of which was found by the Labour Court and was not challenged by the respondents
¶ 9, 10Under the settled practice reflected in the judgment, where reinstatement is inappropriate, a Labour Court may mould relief into lump-sum compensation
¶ 10The Court applied Prabhakar v. Joint Director, Sericulture Department (AIR 2016 SC 2984), which holds that the appropriate Government should consider whether a live dispute exists before referring a stale claim, but held it inapplicable where neither the reference, the award, nor the Section 25F finding was challenged
¶ 8, 10It further relied on State of U.P. v. Krishna Murari Sharma (2025 INSC 1500), which sustained lump-sum compensation despite a 15-year delay in seeking reinstatement
¶ 7It further relied on Bhikhabhai Fatabhai Solanki (LPA No. 908 of 2023, DB, 09.05.2024), particularly para. 10 thereof, which proposes a method for quantifying lump-sum compensation for long-serving employees
¶ 7, 7.1, 10The Court did not expressly reproduce the calculation method from Bhikhabhai, and the petitioners' categorisation under its "first category" was pleaded but not expressly adopted in the reasoning
Provisions in the judgment · 1
Industrial Disputes Act, 1947 Section 25F
04Reasoning
The Court first disposed of the respondents' delay argument. Because the reference itself, the award, and the Section 25F breach finding were not challenged, the Court held that it could not reopen the legality of the breach finding in petitions seeking only enhancement
¶ 10This disposed of the Prabhakar contention, as that decision was held inapplicable where the reference and award stood unchallenged
¶ 10The Court therefore held that the Labour Court was correct in moulding relief into lump-sum compensation instead of reinstatement
¶ 10On quantum, the Court found the Rs. 30,000 award inadequate in light of the two authorities cited by the petitioners, namely Krishna Murari Sharma and Bhikhabhai Fatabhai Solanki, and enhanced it to Rs. 3,00,000 per petitioner
¶ 10The reasoning on quantum is brief, and the judgment does not explicitly work through the Bhikhabhai formula
05Holding
The Court held that the unchallenged finding of breach of Section 25F cannot be reopened in enhancement proceedings
¶ 10The Court held that Prabhakar does not bar relief where the reference and award are unchallenged
¶ 10The Court held that the Labour Court rightly awarded lump-sum compensation instead of reinstatement
¶ 10The petitions were partly allowed, and the compensation was enhanced from Rs. 30,000 to Rs. 3,00,000 for each petitioner
¶ 10, 11The respondents must pay Rs. 3,00,000 to each petitioner within eight weeks of receipt of the order, failing which interest at 6% per annum will run from the expiry of that period
¶ 11The Rule is made absolute to that extent, and direct service is permitted
¶ 12The prayer for reinstatement was not pressed