Uttarakhand High CourtAdministrative and Public LawContract Law

Uttarakhand HC Upholds Contractor’s Road-Bid Rejection Over Insufficient Hill-Cutting Experience And 79-Year-Old Engineer For High-Altitude Work

BASANT BALLABH PUNETHAv.STATE OF UTTARAKHAND

Uttarakhand HC Upholds Contractor’s Road-Bid Rejection Over Insufficient Hill-Cutting Experience And 79-Year-Old Engineer For High-Altitude Work. BASANT BALLABH PUNETHA vs STATE OF UTTARAKHAND. Uttarakhand High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

Whether the decision to treat the petitioner’s experience certificate as insufficient under Clause 19 of the NIT was arbitrary or otherwise reviewable under Article 226.

The court held

The Court answered both issues against the petitioner, holding that the decision declaring his bid non-responsive did not warrant interference under Article 226.

It also directed

It dismissed the writ petition, vacated the interim order dated 30 June 2026, and made no order as to costs.

01Facts

The petitioner, a registered ‘A’ category PWD contractor, challenged the Technical Evaluation Committee’s decision dated 11 May 2026 declaring his bid non-responsive.

¶ 1–3

The rejection rested on two grounds: his experience certificate did not satisfy Clause 19 of the NIT, and the details of his proposed technical person were considered suspicious or non-verifiable.

¶ 1–3

The petitioner relied on hill-side cutting work he said he had executed as a sub-contractor and argued that the nominated Site Engineer’s affidavit confirmed his availability.

¶ 4–5

The NIT required experience in hill-side cutting worth at least one-third of the relevant BOQ value—₹32,04,262.67. The agency stated that the petitioner’s claimed work was worth only ₹12,23,800, while the proposed Site Engineer was 79 years old.

¶ 6–10

The petitioner sought judicial review under Article 226.

¶ 11–12

02Issues

i.Whether the decision to treat the petitioner’s experience certificate as insufficient under Clause 19 of the NIT was arbitrary or otherwise reviewable under Article 226.

¶ 6–9, 19

ii.Whether the rejection based on concerns about the proposed Site Engineer’s age and suitability for work in a high-altitude area warranted interference under Article 226.

¶ 10–12, 20

03Law Applied

Article 226 judicial review of tender decisions is limited: courts do not substitute their assessment for that of the tendering authority unless the decision-making process is mala fide, intended to favour someone, arbitrary, irrational, perverse, or contrary to the tender conditions.

¶ 12–14, 16

Central Coalfields Ltd. v. SLL-SML (Joint Venture Consortium), (2016) 8 SCC 622, and Afcons Infrastructure Ltd. v. Nagpur Metro Rail Corp., (2016) 16 SCC 818, require deference to the employer’s interpretation of tender documents absent mala fides or perversity.

¶ 13–14

Raunaq International Ltd. v. I.V.R. Construction Ltd., (1999) 1 SCC 492, and Air India Ltd. v. Cochin International Airport Ltd., (2000) 2 SCC 617, require the court to weigh public interest and avoid intervention absent a substantial public-interest justification or a vitiated decision-making process.

¶ 15–16

M/s N.G. Projects Ltd. v. Vinod Kumar Jain, (2022) 6 SCC 127, and Tata Motors Ltd. v. BEST, (2023) 19 SCC 1, reinforce restraint in tender matters, particularly where interference may delay infrastructure projects or impose public costs.

¶ 17–18

04Reasoning

The Court found a factual basis for the Committee’s assessment that the petitioner’s claimed hill-side cutting experience fell substantially below the ₹32,04,262.67 threshold: the agency’s communication placed the value at ₹12,23,800, and the Court accepted that assessment as supporting the finding of insufficient experience.

¶ 7–9, 19

It also held that the employer could consider the proposed Site Engineer’s age in light of the adverse climatic and high-altitude conditions of the project; the Court found no basis to characterize that assessment as an impermissible or arbitrary exercise of judgment.

¶ 10, 20

Applying the limited-review principles governing tender decisions, the Court found neither ground sufficiently arbitrary to justify intervention.

¶ 12–20

05Holding

The Court answered both issues against the petitioner, holding that the decision declaring his bid non-responsive did not warrant interference under Article 226.

¶ 19–21

It dismissed the writ petition, vacated the interim order dated 30 June 2026, and made no order as to costs.

¶ 21–22
Uttarakhand High Court

Original Court PDF

BASANT BALLABH PUNETHAvsSTATE OF UTTARAKHAND

Uttarakhand High Court · November 04, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment