Calcutta High CourtProperty and Real Estate LawCivil Procedure and Evidence

Voluntary reconstruction of a demolished wall amounted to acquiescence in responsibility for its demolition.

THE BISWA BHARATI CONSTRUCTIONv.STATE OF WEST BENGAL AND ORS.

Voluntary reconstruction of a demolished wall amounted to acquiescence in responsibility for its demolition.. THE BISWA BHARATI CONSTRUCTION vs STATE OF WEST BENGAL AND ORS.. Calcutta High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the appellant’s failure to receive prior notice of the field enquiry or a copy of its report invalidated the authority’s decision, despite the appellant not raising those objections before the authority.

The court held

The appeal was dismissed on contest, and the Single Judge’s order was affirmed.

It also directed

The appellant was directed to pay Rs. 10 lakh to the private respondents by the end of October 2026.

After payment, the appellant may pursue recovery through due process from any authority that received the compensation, subject to that authority’s defences.

CAN 1 of 2025 was disposed of, with no order as to costs.

01Facts

Private respondents alleged that the appellant demolished their boundary wall while constructing a road.

In an earlier writ proceeding, the Court directed a field enquiry and provided that, if the authority found the demolition to be unauthorised, the appellant would be directed to pay Rs. 10 lakh in compensation.

Following an enquiry and hearing, the authority found against the appellant, directed it to rebuild the wall and pay compensation.

The appellant challenged that decision, alleging it had received neither prior notice of the enquiry nor a copy of the enquiry report.

The Single Judge rejected the challenge.

In the appeal, the appellant argued that it rebuilt the wall under threat of contempt; the Division Bench examined the relevant contempt orders and found no such threat or specific direction.

¶ 2–9, 14–24

The Court also noted that the Rs. 10 lakh amount had been specified in an earlier order that the appellant had not challenged.

¶ 25–28

02Issues

i.1. Whether the appellant’s failure to receive prior notice of the field enquiry or a copy of its report invalidated the authority’s decision, despite the appellant not raising those objections before the authority.

¶ 7–9, 30–33

ii.2. Whether the appellant’s reconstruction of the wall was compelled by a threat of contempt or amounted to acquiescence in its responsibility for the demolition.

¶ 14–24

iii.3. Whether the appellant could challenge the Rs. 10 lakh compensation amount fixed in an earlier, unchallenged order.

¶ 25–28

03Law Applied

The Court applied the principles of natural justice, including the opportunity to receive notice and respond to material relied upon by a decision-maker.

¶ 25–33

It also applied the procedural principle that an objection not raised before the competent authority, particularly where no contemporaneous protest is shown, may not be raised for the first time in a later writ challenge.

¶ 25–33

The Court treated voluntary conduct as capable of amounting to acquiescence and applied the finality of an unchallenged judicial direction fixing compensation, which could not be reopened in the subsequent proceedings.

¶ 25–33

04Reasoning

The Court found that the contempt orders did not compel the appellant to rebuild the wall: the first left reconstruction to the appellant’s discretion, and the second recorded counsel’s submission that reconstruction had begun but contained no specific judicial direction requiring it.

¶ 16–24

The Court therefore rejected the claim that rebuilding occurred under threat of contempt and treated it as acquiescence in the appellant’s responsibility for the demolition.

¶ 16–24

The compensation amount had been expressly fixed at Rs. 10 lakh in the earlier order and was not challenged; the appellant could not reopen that determination.

¶ 25–28

Accordingly, the notice and report-service objections no longer affected the outcome; in any event, the appellant had raised neither objection before the authority and had made no contemporaneous communication about non-service.

¶ 29–33

05Holding

The appeal was dismissed on contest, and the Single Judge’s order was affirmed.

¶ 34–37

The appellant was directed to pay Rs. 10 lakh to the private respondents by the end of October 2026.

¶ 34–37

After payment, the appellant may pursue recovery through due process from any authority that received the compensation, subject to that authority’s defences.

¶ 34–37

CAN 1 of 2025 was disposed of, with no order as to costs.

¶ 36, 38
Calcutta High Court

Original Court PDF

THE BISWA BHARATI CONSTRUCTIONvsSTATE OF WEST BENGAL AND ORS.

Calcutta High Court · October 09, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment