Facts
The petitioner sought revision of Clause 9 of its Energy Wheeling Agreement dated 2 May 2026, contending that it was inconsistent with Clause 5.5.8 of the Tamil Nadu Electricity Regulatory Commission’s Solar Tariff Order No. 9 of 2020.
Source reference: p. 1–3It also sought payment for unutilised surplus solar energy at 75% of the competitively discovered tariff, stated to be ₹3.04 per unit.
Source reference: p. 1–3The parties informed the Court that the issue was covered by earlier writ orders directing revision of inconsistent agreement clauses and settlement of amounts due under the tariff order.
Source reference: p. 3–7The respondents stated that an appeal against the Commission’s order was pending before APTEL.
Source reference: p. 7Issues
Whether respondents 2 to 4 should be directed to revise the relevant clause of the petitioner’s Energy Wheeling Agreement to incorporate Clause 5.5.8 of Solar Tariff Order No. 9 of 2020.
Source reference: p. 1–3, 7–8Whether amounts payable for surplus solar energy should be settled in accordance with the tariff order, notwithstanding the pending APTEL appeal.
Source reference: p. 1–2, 7–8Law Applied
Clause 5.5.8 of Solar Tariff Order No. 9 of 2020, read with the Tamil Nadu Electricity Regulatory Commission’s order in M.P. No. 47 of 2021 dated 11 May 2023, provides that a generator is entitled to payment for energy supplied over and above the sanctioned limit at 75% of the tariff fixed by the Commission or, where no tariff is fixed, 75% of the tariff discovered through competitive bidding.
Source reference: p. 4–5The Commission also recognised that claims may be denied in specified cases involving injection contrary to SLDC directions or risk to grid security, subject to notice and a fair hearing.
Source reference: p. 4–5The Court applied its earlier orders in W.P. Nos. 14115 of 2025, 31457 of 2025 and 49777 of 2025, which directed amendment of inconsistent wheeling-agreement clauses.
Source reference: p. 3–7Reasoning
The Court treated the dispute as covered by its earlier decisions directing that wheeling agreements be brought into conformity with Clause 5.5.8.
Source reference: p. 7–8It therefore directed amendment of the petitioner’s agreement and settlement of any amount payable under the tariff order.
Source reference: p. 7–8Although the respondents relied on the pending APTEL appeal, the Court held that compliance need not await its outcome; the authorities could proceed in accordance with law after APTEL decided the matter.
Source reference: p. 7–8Holding
The writ petition was disposed of with a direction to respondents 2 to 4 to revise the relevant agreement clause by incorporating Clause 5.5.8 within six weeks from uploading of the web copy.
Any amount payable was to be settled within eight weeks thereafter.
Source reference: p. 7–8Compliance was not to be deferred pending the APTEL appeal, though the authorities could act in accordance with law following its decision.
Source reference: p. 7–8No costs were ordered.
Source reference: p. 7–8Original Court PDF
Citrine Green Power Pvt Ltd.,vsTAMIL NADU ELECTRICITY REGULATORY COMMISSION
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
