01Facts
The petitioner, a private company acting through its Director, entered into Agreement No. 03/SBD 2024-25 with the Executive Engineer, LAEO, Works Division-02, Benipur, Darbhanga, on 04.09.2024 for construction of a Panchayat Sarkar Building at Budh Way Inayatpur Panchayat, Ghanshyampur Block.
¶ 2, 3The work was to be completed by 03.11.2025.
¶ 4The petitioner contends that severe waterlogging at the site prevented completion, and that work was halted under Memo No. 433 dated 09.05.2025 issued by the Circle Officer, Ghanshyampur.
¶ 4The Executive Engineer sought clarification from the Circle Officer vide Letter No. 864 dated 17.05.2025.
¶ 5No decision on resumption had been taken for over two years.
¶ 5The petitioner's representation seeking either resumption of work or cancellation of the agreement with refund of security deposit and earnest money remained undecided, prompting the writ petition.
¶ 5The State sought a short adjournment to place the factual position on record.
¶ 602Issues
i.1. Whether the petitioner is entitled to a writ directing the Executive Engineer to resume the construction work under the Agreement dated 04.09.2024, or alternatively to refund the security deposit and earnest money.
¶ 2, 5ii.2. Whether, in the absence of any decision on the petitioner's representation over two years, the Court should direct the authority to decide the representation within a fixed time frame.
¶ 5, 7, 803Law Applied
The judgment cites no statute, rule, or precedent. The Court's reasoning rests on its discretion in writ jurisdiction to dispose of a petition with liberty to seek administrative relief where the claim is best examined by the executive authority in the first instance.
¶ 7The implicit principle that a pending representation must be decided by a reasoned order within a reasonable, specified time.
¶ 8No specific statutory provision governing contract termination, refund of earnest money or security deposit, or resumption of contractual work is referred to.
04Reasoning
The Court did not examine whether the waterlogging justified suspension, whether the contract should be resumed or terminated, or whether refund was due.
The petitioner's core grievance was administrative inaction: the Executive Engineer had sought clarification in May 2025 but had taken no decision for over two years, and the representation remained unanswered.
¶ 5Having regard to the nature of the claim, which turns on contractual and factual questions (site conditions, the status of the halt order, and the rights under the agreement) best determined by the executive authority, the Court chose not to decide the merits.
¶ 7The Court granted liberty to file a fresh representation within two weeks, and fixed a further eight-week period for a reasoned order.
¶ 7, 8The Court's approach avoids substituting its own findings on disputed contractual facts while ensuring that the petitioner's claim receives a determination.
05Holding
The Court did not answer the substantive questions whether resumption or refund was warranted.
¶ 7The writ petition was disposed of with liberty to the petitioner to file a fresh representation before the Executive Engineer, LAEO, Works Division-02, Benipur, Darbhanga, preferably within two weeks. Upon filing, the Executive Engineer must pass an appropriate order in accordance with law within eight weeks. The writ petition stands disposed of.
¶ 7, 8, 9Original Court PDF