Facts
The petitioner, a partnership firm, claimed outstanding hire charges from the respondents in respect of a Mahindra XUV-300 bearing Registration No. CG-31-A-7893, including amounts allegedly payable for January–March 2025 and for the period from 5 April 2025 to 21 June 2025.
Source reference: para. 1It sought a writ of mandamus for release of the alleged dues, interest, consideration of its representation, verification and settlement of its bills by an officer other than Respondent No. 6, and costs. The petitioner also filed an application for interim relief.
Source reference: para. 1During hearing, it was submitted that Clause 5 of the agreement contained an arbitration clause and that the dispute arising from the agreement was amenable to arbitration. The petitioner therefore sought permission to withdraw the writ petition to avail the remedy under the Arbitration and Conciliation Act, 1996.
Source reference: para. 2Issues
Whether the writ petition seeking payment and settlement of contractual hire charges should be entertained when the agreement contains an arbitration clause covering disputes arising from the agreement?
Source reference: para. 2Whether the petitioner could withdraw the writ petition and pursue remedies, including interim relief, under the Arbitration and Conciliation Act, 1996?
Source reference: paras. 2–3Law Applied
The Court applied the principle that disputes arising out of a contractual agreement containing an arbitration clause should ordinarily be pursued through the agreed arbitral mechanism rather than by invoking writ jurisdiction for adjudication of contractual claims.
Source reference: paras. 2–3The Court relied upon Clause 5 of the agreement, which provided for arbitration of disputes arising from the agreement, and permitted the petitioner to pursue remedies under the Arbitration and Conciliation Act, 1996, including appropriate interim relief under that statute.
Source reference: paras. 2–3Reasoning
The petitioner’s claims concerned alleged unpaid hire charges, computation of contractual dues, interest, and verification of bills—matters arising directly from the agreement.
Source reference: para. 1Since Clause 5 stipulated arbitration for disputes arising from the agreement, the Court treated arbitration as the appropriate remedial forum rather than adjudicating the contractual monetary claims in writ proceedings.
Source reference: para. 2At the petitioner’s request, the Court therefore allowed withdrawal of the writ petition while preserving the petitioner’s liberty to invoke the Arbitration and Conciliation Act, 1996 and to seek interim relief under that Act.
Source reference: paras. 2–3Holding
The writ petition was disposed of as withdrawn.
The petitioner was granted liberty, if so advised, to pursue the available remedy under the Arbitration and Conciliation Act, 1996 and to seek interim relief under that Act.
Source reference: para. 3No adjudication was made on the petitioner’s entitlement to the claimed hire charges, interest, or other reliefs.
Source reference: no citationOriginal Court PDF
M/S. PRAMOD KUMAR AGRAWALvsCHHATTISGARH STATE POWER DISTRIBUTION COMPANY LIMITED
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
