Facts
Respondent No. 2, M/s. Modern Construction Co. Ltd., developed Plot Nos. 2 and 3 by constructing ten buildings.
Source reference: p.2The flat purchasers formed Respondent No. 3, E.M.C.C. Co-operative Housing Society, which obtained conveyance of Plot Nos. 2 and 3 on 31 March 1971.
Source reference: p.2Under a Package Deal Agreement dated 25 September 1970, Respondent No. 3 agreed to acquire rights in Plot No. 1, while granting Respondent No. 2 development rights to construct a building and sell flats thereon.
Source reference: pp.5–6A common layout plan for Plot Nos. 1, 2 and 3 was sanctioned on 14 December 1971.
Source reference: pp.12–13The flat purchasers of the building on Plot No. 1 subsequently formed and registered the Petitioner-Society on 4 December 2008, without challenge by Respondent No. 3.
Source reference: p.7The Petitioner applied for deemed conveyance under Section 11 of the Maharashtra Ownership Flats Act, 1963 (“MOFA”) on 3 July 2024.
Source reference: p.2The Competent Authority rejected the application on 6 March 2025, principally citing deficiencies in the documents, uncertainty regarding the land area, the alleged ownership of Respondent No. 3 over the layout, and possible FSI-related complications.
Source reference: pp.2, 7–9The Petitioner challenged that order under Article 226 of the Constitution.
Source reference: no citationIssues
Whether the Petitioner-Society, despite the Package Deal Agreement and the alleged right of Respondent No. 3 to acquire Plot No. 1, was entitled to seek independent deemed conveyance of its building and a proportionate share in the layout land?
Source reference: pp.9–13, 19–20 / paras. 16–20, 31–32Whether the registration of the Petitioner-Society and Respondent No. 3’s subsequent conduct prevented Respondent No. 3 from collaterally disputing the Petitioner’s entitlement to conveyance proceedings?
Source reference: pp.10–12 / paras. 17–19Whether conveyance could be confined to Plot No. 1 measuring 1,219 sq. metres, or whether the Petitioner was entitled to a proportionate share in the entire common layout based on the common sanctioned plan and utilisation of FSI?
Source reference: pp.13–19 / paras. 21–30Whether the Competent Authority was justified in rejecting the application for deemed conveyance on the stated procedural, documentary, ownership and FSI-related grounds?
Source reference: pp.7–9, 19–21 / paras. 14–15, 32–34Law Applied
The Court applied Section 11 of the MOFA, under which a promoter is required to convey his right, title and interest in the land and building to the flat purchasers’ co-operative society, and the Competent Authority may issue a certificate of deemed conveyance where the promoter fails to do so.
Source reference: pp.19–21 / paras. 31–33The Court relied on the principle that once a separate co-operative housing society is validly formed and registered for a particular building, its right to seek conveyance of the building and the land necessary for its enjoyment cannot ordinarily be defeated by a collateral ownership objection; any challenge to the registration had to be pursued through the remedies under Sections 152 or 21A of the Maharashtra Co-operative Societies Act, 1960.
Source reference: pp.10–12 / paras. 17–19The Court also applied the Government Resolution dated 22 June 2018, which permits proportionate division of layout land where buildings are developed under a common sanctioned plan and utilise the FSI of the larger layout.
Source reference: pp.12–15 / paras. 21–26The Court considered the principles discussed in Veer Tower Co-operative Housing Society Ltd. v. District Deputy Registrar, Upvan Co-operative Housing Society Ltd. v. M/s. Upvan Developers, M/s. Blue Heavens Co-operative Housing Society Ltd. v. M/s. Punit Construction Company Pvt. Ltd., and Deep Sadan Co-operative Housing Society Ltd. v. State of Maharashtra, but held that the present case involved peculiar facts and therefore did not require an extended discussion of those authorities.
Source reference: pp.3–5, 19 / paras. 3, 5, 31Reasoning
The Court held that Respondent No. 3’s Package Deal Agreement with the developer did not defeat the Petitioner’s right to seek conveyance.
Source reference: pp.10–12 / paras. 17–19Although the agreement contemplated that purchasers in the Plot No. 1 building would become members of Respondent No. 3, Respondent No. 3 did not challenge the Petitioner-Society’s registration in 2008 and later invited it to participate in a joint redevelopment process, thereby acknowledging its separate and valid existence.
Source reference: pp.10–12 / paras. 17–19The Court reasoned that Respondent No. 3 could not accept the Petitioner as a separate society for management and redevelopment purposes while denying it the corresponding right to acquire the building and the land required for its sustenance.
Source reference: pp.11–13 / paras. 18–20Since all three plots were subjected to a common sanctioned layout plan, the individuality of Plot No. 1 was lost for FSI and development purposes.
Source reference: pp.13–18 / paras. 21–30The Petitioner’s building had a sanctioned BUA of 2,174.56 sq. metres, which could not have been achieved solely through Plot No. 1’s area of 1,219 sq. metres and therefore reflected utilisation of the common layout’s FSI.
Source reference: pp.13–18 / paras. 21–30Applying the architect’s proportionate calculation, the Court accepted the Petitioner’s entitlement to 1,970.45 sq. metres of main layout land, together with FSI advantages attributable to the 44-foot road and S.V. Road, measuring 123.59 sq. metres and 45.10 sq. metres respectively.
Source reference: pp.14–15, 20 / paras. 22–26, 32The Competent Authority had therefore erred in treating Respondent No. 3’s asserted ownership of the larger layout as an absolute bar to deemed conveyance.
Source reference: pp.8–9, 19–20 / paras. 14–16, 32Holding
The Court allowed the Petition and set aside the Competent Authority’s order dated 6 March 2025 rejecting Application No. 159 of 2024.
It held that the Petitioner-Society was entitled to deemed conveyance of 1,970.45 sq. metres of layout land, along with FSI advantages of 123.59 sq. metres in respect of the 44-foot road and 45.10 sq. metres in respect of the S.V. Road.
Source reference: p.20 / para. 33(ii)The matter was remanded to the Competent Authority for issuance of the deemed conveyance certificate, preferably within four months; the parties were directed to appear before that authority on 30 September 2026.
Source reference: p.20 / paras. 33(iii)–(iv)There was no order as to costs.
Source reference: p.21 / para. 34Acts & Sections Cited
2 provisions across 2 statutes referred to in this judgment. Each provision opens on LawLens.
Maharashtra Ownership Flats (Regulation of the promotion of construction, sale, management and transfer) Act, 19631
Maharashtra Co-operative Societies Act, 19601
Original Court PDF
Beau Monde Plot No. 1 Co-Operative Housing Society Thr Rep Rajesh PatelvsDistrict Deputy Registrar And Ors
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
