01Facts
NOIDA allotted the petitioner a commercial plot on 27 July 2007 and executed a lease deed on 4 January 2008.
¶ 3–6, 21A status quo order was operating over land in Sectors 42 and 43 in litigation involving a third-party society; the petitioner was never given physical possession of the plot.
¶ 3–6, 21After the petitioner defaulted on instalments, NOIDA cancelled the allotment in 2013 and later demanded restoration charges.
¶ 12, 23–24In revision under Section 41(3) of the U.P. Urban Planning and Development Act, 1973, read with Section 12 of the U.P. Industrial Area Development Act, 1976, the State Government set aside the cancellation and the restoration-charge demand and directed NOIDA to reconsider the matter, including the effect of the status quo orders.
¶ 12, 23–24NOIDA subsequently restored the plot but imposed restoration charges and demanded penal interest, lease rent and other amounts.
¶ 13–14The petitioner challenged those demands and sought zero period from the date of allotment until actual possession.
¶ 13–1402Issues
i.1. Whether NOIDA’s orders dated 23 April 2025, 7 May 2025 and 19 August 2025 were illegal or arbitrary.
¶ 20(I)ii.2. Whether zero period should run from the allotment date, 27 July 2007, or from the later status quo order in the Authority’s appeal.
¶ 20(II)iii.3. Whether the petitioner was entitled to consequential relief, including relief from restoration charges, penal interest and lease rent, and delivery of possession.
¶ 20(III)03Law Applied
The Court considered Section 41(3) of the U.P. Urban Planning and Development Act, 1973, read with Section 12 of the U.P. Industrial Area Development Act, 1976, under which the State Government had exercised revisional jurisdiction to set aside the cancellation and restoration-charge orders.
¶ 12It applied the principle that where the cancellation of an allotment has been set aside, the allotment stands restored and restoration charges cannot be imposed on the basis of that cancellation.
¶ 26–28It further relied on Vision Town Planners Private Limited v. State of U.P. and Others, 2026 (1) ADJ 574, and M/s Silverline Furnishing and Furnitures Private Limited v. State of U.P. and Others, 2023:AHC:207677, for the rule that lease rent is not payable before actual physical possession is handed over.
¶ 35The Court also applied the lease deed’s instalment terms, holding that the premium remained payable in the stipulated 16 instalments, with the schedule to be recalculated to account for the zero period.
¶ 34Provisions in the judgment · 2
U.P. Urban Planning and Development Act, 1973 Section 41
U. P. Industrial Area Development Act, 1976 Section 12
04Reasoning
The Authority knew that the status quo orders affected the land and nevertheless allotted the plot and executed the lease without delivering physical possession; possession remained undelivered, as confirmed by its own report.
¶ 21, 30–31The revisional order setting aside the cancellation and restoration-charge demand had not been challenged, so NOIDA could not treat the allotment as requiring restoration or impose restoration charges.
¶ 23, 26–28Given the Authority’s knowledge of the litigation and the continuing absence of possession, the Court held that zero period should begin on the allotment date, rather than the later status quo order relied on by NOIDA.
¶ 30–32That zero period also displaced the basis for penal interest on the earlier instalments.
¶ 33–35The demand for the entire premium at once was inconsistent with the lease deed’s 16-instalment schedule, and lease rent and interest on it could not be charged before possession.
¶ 33–3505Holding
The Court allowed the petition and set aside the impugned orders.
¶ 36–41It directed that zero period run from 27 July 2007 until actual physical possession; that possession be delivered within two weeks of production of a certified copy of the judgment; and that the premium be recalculated into 16 instalments under a revised payment schedule.
¶ 36–41Lease rent would begin only on delivery of possession.
¶ 36–41The Court also barred non-development and time-extension charges for the period during which possession had not been given and allowed the petitioner two years from delivery of possession to complete construction.
¶ 36–41Original Court PDF
M/S Aloft Solutions Private LimitedvsState Of Uttar Pradesh And 3 Others
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
