Allahabad High CourtProperty and Real Estate LawAdministrative and Public Law

After Status-Quo Blocked Possession, Allahabad HC Orders NOIDA To Hand Over Plot, Grants Zero Period From Allotment And Scraps Restoration Charges

M/S Aloft Solutions Private Limitedv.State Of Uttar Pradesh And 3 Others

After Status-Quo Blocked Possession, Allahabad HC Orders NOIDA To Hand Over Plot, Grants Zero Period From Allotment And Scraps Restoration Charges. M/S Aloft Solutions Private Limited vs State Of Uttar Pradesh And 3 Others. Allahabad High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether NOIDA’s orders dated 23 April 2025, 7 May 2025 and 19 August 2025 were illegal or arbitrary.

The court held

The Court allowed the petition and set aside the impugned orders.

It also directed

It directed that zero period run from 27 July 2007 until actual physical possession; that possession be delivered within two weeks of production of a certified copy of the judgment; and that the premium be recalculated into 16 instalments under a revised payment schedule.

Lease rent would begin only on delivery of possession.

The Court also barred non-development and time-extension charges for the period during which possession had not been given and allowed the petitioner two years from delivery of possession to complete construction.

01Facts

NOIDA allotted the petitioner a commercial plot on 27 July 2007 and executed a lease deed on 4 January 2008.

¶ 3–6, 21

A status quo order was operating over land in Sectors 42 and 43 in litigation involving a third-party society; the petitioner was never given physical possession of the plot.

¶ 3–6, 21

After the petitioner defaulted on instalments, NOIDA cancelled the allotment in 2013 and later demanded restoration charges.

¶ 12, 23–24

In revision under Section 41(3) of the U.P. Urban Planning and Development Act, 1973, read with Section 12 of the U.P. Industrial Area Development Act, 1976, the State Government set aside the cancellation and the restoration-charge demand and directed NOIDA to reconsider the matter, including the effect of the status quo orders.

¶ 12, 23–24

NOIDA subsequently restored the plot but imposed restoration charges and demanded penal interest, lease rent and other amounts.

¶ 13–14

The petitioner challenged those demands and sought zero period from the date of allotment until actual possession.

¶ 13–14

02Issues

i.1. Whether NOIDA’s orders dated 23 April 2025, 7 May 2025 and 19 August 2025 were illegal or arbitrary.

¶ 20(I)

ii.2. Whether zero period should run from the allotment date, 27 July 2007, or from the later status quo order in the Authority’s appeal.

¶ 20(II)

iii.3. Whether the petitioner was entitled to consequential relief, including relief from restoration charges, penal interest and lease rent, and delivery of possession.

¶ 20(III)

03Law Applied

The Court considered Section 41(3) of the U.P. Urban Planning and Development Act, 1973, read with Section 12 of the U.P. Industrial Area Development Act, 1976, under which the State Government had exercised revisional jurisdiction to set aside the cancellation and restoration-charge orders.

¶ 12

It applied the principle that where the cancellation of an allotment has been set aside, the allotment stands restored and restoration charges cannot be imposed on the basis of that cancellation.

¶ 26–28

It further relied on Vision Town Planners Private Limited v. State of U.P. and Others, 2026 (1) ADJ 574, and M/s Silverline Furnishing and Furnitures Private Limited v. State of U.P. and Others, 2023:AHC:207677, for the rule that lease rent is not payable before actual physical possession is handed over.

¶ 35

The Court also applied the lease deed’s instalment terms, holding that the premium remained payable in the stipulated 16 instalments, with the schedule to be recalculated to account for the zero period.

¶ 34

Provisions in the judgment · 2

U.P. Urban Planning and Development Act, 1973 Section 41

U. P. Industrial Area Development Act, 1976 Section 12

04Reasoning

The Authority knew that the status quo orders affected the land and nevertheless allotted the plot and executed the lease without delivering physical possession; possession remained undelivered, as confirmed by its own report.

¶ 21, 30–31

The revisional order setting aside the cancellation and restoration-charge demand had not been challenged, so NOIDA could not treat the allotment as requiring restoration or impose restoration charges.

¶ 23, 26–28

Given the Authority’s knowledge of the litigation and the continuing absence of possession, the Court held that zero period should begin on the allotment date, rather than the later status quo order relied on by NOIDA.

¶ 30–32

That zero period also displaced the basis for penal interest on the earlier instalments.

¶ 33–35

The demand for the entire premium at once was inconsistent with the lease deed’s 16-instalment schedule, and lease rent and interest on it could not be charged before possession.

¶ 33–35

05Holding

The Court allowed the petition and set aside the impugned orders.

¶ 36–41

It directed that zero period run from 27 July 2007 until actual physical possession; that possession be delivered within two weeks of production of a certified copy of the judgment; and that the premium be recalculated into 16 instalments under a revised payment schedule.

¶ 36–41

Lease rent would begin only on delivery of possession.

¶ 36–41

The Court also barred non-development and time-extension charges for the period during which possession had not been given and allowed the petitioner two years from delivery of possession to complete construction.

¶ 36–41
Allahabad High Court

Original Court PDF

M/S Aloft Solutions Private LimitedvsState Of Uttar Pradesh And 3 Others

Allahabad High Court · November 12, 2026