Allahabad High CourtAdministrative and Public LawContract Law

Arbitrary termination of highway project contract without fulfilling site handover obligations and considering engineer’s reports is unsustainable.

Tata Projects Limitedv.Union Of India And 2 Others

Arbitrary termination of highway project contract without fulfilling site handover obligations and considering engineer’s reports is unsustainable.. Tata Projects Limited vs Union Of India And 2 Others. Allahabad High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the National Highway Authority of India effectively fulfilled its contractual obligation to provide unencumbered "Right of Way" and land possession as per Articles 8.1 and 8.2 of the EPC Agreement

The court held

The Court decided both issues in favor of the Petitioner and held that NHAI's actions were arbitrary, irrational, and based on misrepresentation of land availability

It also directed

The Court quashed the termination order dated January 14, 2025, and the fresh tender dated February 3, 2025, directing a joint site inspection and a revised schedule to complete the project within 14 months

01Facts

The National Highway Authority of India (NHAI) awarded Tata Projects Ltd. (Petitioner) a contract on August 26, 2021, for widening NH-709A in Uttar Pradesh

p. 2

Under the EPC Agreement, NHAI was obligated to provide 90% of hindrance-free land in 5km contiguous stretches

¶ 22

Although a "Handover Memorandum" was signed on September 21, 2021, the Petitioner alleged that actual physical possession was not delivered due to pending land acquisition, protests, and structures (mosques, temples, buildings)

¶ 5, 8

NHAI’s own Authority’s Engineer (AE) confirmed significant hindrances in reports dated July 2022 and July 2024

¶ 28-30

Despite these reports, NHAI only granted a 42-day extension and subsequently issued a cure notice for slow progress

¶ 26, 32

On January 14, 2025, NHAI terminated the contract and initiated re-tendering

¶ 35

The Petitioner challenged the termination as arbitrary and a violation of Article 14

¶ 7

02Issues

i.1. Whether the National Highway Authority of India effectively fulfilled its contractual obligation to provide unencumbered "Right of Way" and land possession as per Articles 8.1 and 8.2 of the EPC Agreement

¶ 20(I)

ii.2. Whether the dispute involves complex questions of fact requiring arbitration or if the State's actions are palpably arbitrary, justifying judicial review under Article 226 of the Constitution

¶ 20(II)

03Law Applied

The court applied the principle that even in contractual matters, the State must act fairly and reasonably under Article 14 of the Constitution (ABL International Ltd. v. Export Credit Guarantee Corp.)

¶ 53

The doctrine that the mere existence of a dispute or an arbitration clause does not bar writ jurisdiction if the State's action is arbitrary, involves no complex factual investigation, or affects public interest (M.P. Power Management Co. Ltd. v. Sky Power Southeast Solar India; A.P. Electrical Equipment Corp. v. Tehsildar)

¶ 55, 54

Judicial review is permissible if the decision is so irrational that no responsible authority could have reached it or if public interest is adversely affected (Jagdish Mandal v. State of Orissa)

¶ 59

Provisions in the judgment · 3

National Highways Act, 1956 Section 3DSection 3G

Companies Act, 2013 Section 10

04Reasoning

The Court found that NHAI’s reliance on the 2021 Handover Memorandum was misleading, as NHAI’s own correspondence dated August 8, 2022, admitted that only 29.914 km of the 50.254 km stretch was actually available

¶ 43, 44

The Authority’s Engineer’s reports (specifically July 10, 2024) unequivocally established that substantial portions of the main carriage-way remained encumbered by buildings and religious structures, which were NHAI's responsibility to clear

¶ 29, 30

The Court observed that NHAI failed to perform its reciprocal obligations regarding land procurement yet penalized the contractor for the resulting delays

¶ 43

The Court noted a total non-application of mind in the termination process, as the final order was a verbatim reproduction of the show-cause notice and failed to address the Petitioner's detailed factual reply regarding specific site hindrances

¶ 50, 66

The Court concluded that driving the Petitioner to arbitration would be a "smokescreen" for the State’s procedural failures and that public interest favored completing the project via the existing contractor to avoid massive cost escalations

¶ 61, 72

05Holding

The Court decided both issues in favor of the Petitioner and held that NHAI's actions were arbitrary, irrational, and based on misrepresentation of land availability

¶ 65, 68

The Court quashed the termination order dated January 14, 2025, and the fresh tender dated February 3, 2025, directing a joint site inspection and a revised schedule to complete the project within 14 months

¶ 74-77
Allahabad High Court

Original Court PDF

Tata Projects LimitedvsUnion Of India And 2 Others

Allahabad High Court · July 08, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment