01Facts
The Airports Authority of India (AAI) invited tenders for the development and upgradation of Saharsa Airport, with an estimated cost of ₹35.14 crores
¶ 3The petitioner submitted its bid with an Earnest Money Deposit (EMD) of ₹1,05,42,000 through a Bank Guarantee dated 06.06.2026
¶ 4Due to a clerical error while filling the Bill of Quantities (BOQ), the quoted amount was recorded as ₹24.95 instead of the intended ₹24,95,00,000
¶ 4On opening of financial bids on 14.07.2026, the petitioner was declared L-1
¶ 4By letter dated 21.07.2026, the petitioner disclosed the error, furnished a component-wise price assessment totalling ₹24,95,00,000, and expressed willingness to execute the work at that figure
¶ 5AAI issued a show cause notice dated 03.09.2026 alleging denial of execution at the quoted rates
¶ 6The petitioner replied on 08.09.2026, asserting the error was inadvertent and that it had neither withdrawn nor unilaterally modified its bid
¶ 6On 14.10.2026, AAI cancelled the tender on administrative grounds without hearing the petitioner
¶ 7By notice dated 17.11.2026, AAI rejected the reply, directed forfeiture of the entire EMD, and threatened encashment of the Bank Guarantee within three days
¶ 7AAI contended that the CPP Portal reflects the amount in words, that the letter of 21.07.2026 sought acceptance of a modified amount or, alternatively, withdrawal, and that Clause 36 of the General Guidelines for Bidders (GGB) permits forfeiture of the entire EMD
¶ 8–9, 1302Issues
i.1. Whether the petitioner's self-evident, inadvertent error in quoting ₹24.95 instead of ₹24,95,00,000, promptly brought to AAI's notice, permits forfeiture of the entire EMD.
¶ 11–12, 15ii.2. Whether Clause 36 of the GGB and the judgments in Villayati Ram Mittal and Pooja Ceratech justify forfeiture in the present facts.
¶ 13–14iii.3. Whether forfeiture of the entire EMD is disproportionate in the totality of the circumstances.
¶ 16, 18–2003Law Applied
The Court relied on Clause 36 of the GGB, which permits forfeiture of EMD upon withdrawal or modification of a bid during validity.
¶ 13Such a clause does not mandate forfeiture in every case, and a bona fide, apparent error promptly brought to the authority's notice attracts a proportionate response.
¶ 16ABCI Infrastructures (P) Ltd. v. Union of India, (2025) 6 SCC 813, following W.B. SEB v. Patel Engg. Co. Ltd., (2001) 2 SCC 451, and Omsairam Steels & Alloys (P) Ltd. v. State of Odisha, (2024) 9 SCC 697, holds that equitable relief is available where a bid mistake is patent and self-evident, is promptly communicated upon discovery, and none of the W.B. SEB exceptions applies; and that the doctrine of proportionality applies in contractual matters where the error is writ large.
¶ 17Coimbatore District Central Coop. Bank v. Employees Assn., (2007) 4 SCC 669, as cited in ABCI, supports the principle of proportionality as a check on disproportionate penalties.
¶ 17Villayati Ram Mittal (P) Ltd. v. Union of India, (2010) 10 SCC 532, and Pooja Ceratech Pvt. Ltd. v. ONGC, 2021 SCC OnLine SC 3504, were considered as authorities where bidders sought to vary offers during the validity period.
¶ 13–14Provisions in the judgment · 1 · Linked ones open on LawLens
Indian Contract Act, 1872 Section 20
04Reasoning
The Court found the error self-evident, since a bid of ₹24.95 for an airport upgradation estimated at ₹35.14 crores could not be a genuine offer.
¶ 11The petitioner acted within one week of opening the financial bids, which indicated bona fides.
¶ 12Villayati and Pooja Ceratech were distinguished: in those cases the bidders sought to substitute a higher commercial offer during validity and remained unwilling to stand by the original bid, whereas here the petitioner sought to execute the work at its intended price and sought withdrawal only as an alternative if AAI refused that price.
¶ 14–15The Court accepted that the petitioner was at fault in not entering the correct amount, but held that this fault alone could not justify forfeiture of the entire EMD where the mistake was apparent and promptly reported.
¶ 18AAI itself cancelled the tender on administrative grounds unconnected to any default by the petitioner, the cancellation did not record any withdrawal or obstruction by the petitioner, and AAI showed no actual financial loss or prejudice.
¶ 19Applying proportionality, full forfeiture would be wholly disproportionate in these circumstances.
¶ 2005Holding
The petitioner's bona fide, self-evident bid error, promptly disclosed and unaccompanied by any financial loss or prejudice to AAI, does not justify forfeiture of the entire EMD, and such forfeiture would be disproportionate, particularly where AAI itself cancelled the tender on administrative grounds.
¶ 18–20The petition was allowed and the impugned notice dated 17.11.2026 was set aside.
¶ 21AAI was directed to return the petitioner's Bank Guarantee within three weeks.