Chhattisgarh High Court

Blacklisting order issued without specific show cause notice contemplating debarment is arbitrary and legally unsustainable.

M/S. H R K SOLUTIONS LIMITED vs THE UNION OF INDIA

Chhattisgarh High CourtJUDGMENT: May 07, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Petitioner, a railway facility management company, was awarded a contract on 13.09.2024 for cleaning and watering trains under SECR Bilaspur

Source reference: p. 3

On 07.07.2025, Respondent No. 5 issued a 7-day notice alleging deficiencies and stating that failure to improve would result in the contract being rescinded under Clause 7.4 of the GCC (Service) 2018

Source reference: p. 3, 6

Following the notice period, the Respondents issued the impugned order dated 24.07.2025, which not only terminated the contract and forfeited the Performance Guarantee but also debarred the Petitioner from participating in future tenders for two years

Source reference: p. 3-4

The Petitioner challenged this order, primarily arguing that no specific show-cause notice for debarment was ever issued

Source reference: p. 4
02

Issues

1. Whether the order of debarment/blacklisting is legally sustainable if the preceding show-cause notice did not specifically contemplate such action

Source reference: p. 6-7

2. Whether the court should adjudicate on disputed questions of fact regarding contractual performance and termination when an arbitration clause exists

Source reference: p. 8-9
03

Law Applied

Gorkha Security Services v. Government (NCT of Delhi) (2014), which established that blacklisting must be preceded by a show-cause notice because it is stigmatic and precludes participation in government contracts

Source reference: para. 7

UMC Technologies (P) Ltd. v. Food Corporation of India (2021), which held that a valid show-cause notice for blacklisting must be "particularized and unambiguous" and must clearly spell out the intention to blacklist to afford a meaningful opportunity to the noticee

Source reference: para. 3, 8, 9
04

Reasoning

The court observed that the 7-day notice dated 07.07.2025 only mentioned the rescission of the contract and forfeiture of the performance guarantee under the GCC; it contained no mention of potential debarment or blacklisting

Source reference: para. 6

The court reasoned that since the notice did not disclose a proposal for blacklisting, the Petitioner was denied a meaningful opportunity to respond to that specific consequence

Source reference: para. 6, 9

Applying the UMC Technologies precedent, the court found that the Respondents' action of debarring the Petitioner for two years travelled beyond the scope of the original notice and was, therefore, a violation of natural justice and passed without jurisdiction

Source reference: para. 3, 9

Regarding the termination of the contract and forfeiture of dues, the court determined these were "disputed questions of facts" and highlighted that Clause 8.2 of the GCC provided for an arbitration mechanism, which is the appropriate forum for such disputes

Source reference: para. 10
05

Holding

The court held that the impugned order dated 24.07.2025, specifically regarding the blacklisting/debarment of the Petitioner for two years, was illegal and thus quashed that portion of the order

The court partly allowed the petition; it declined to adjudicate on the termination of the contract or the refund of dues, directing the Petitioner to take recourse through the arbitration provision provided under Clause 8.2 of the GCC

Source reference: para. 10, 11
Chhattisgarh High Court

Original Court PDF

M/S. H R K SOLUTIONS LIMITEDvsTHE UNION OF INDIA

Chhattisgarh High Court · May 07, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment