Delhi High Court

COURT MAY EXTEND ARBITRAL MANDATE UNDER SECTION 29A UPON FINDING SUFFICIENT CAUSE ARISING FROM MEDICAL EMERGENCIES.

Ms Maruti Infracreation Pvt Ltd vs The Chief Engineer Nh Division Up Pwd

Delhi High CourtJUDGMENT: July 01, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Petitioner and Respondent entered into an Engineering, Procurement and Construction (EPC) Contract on November 11, 2021, for the Pratapgarh Bypass Project in Uttar Pradesh.

Source reference: p. 1

Disputes arose regarding reciprocal obligations, Right of Way (ROW), and project delays, leading to the constitution of a three-member Arbitral Tribunal on July 7, 2024.

Source reference: p. 1-2

The proceedings progressed through pleadings, evidence, and oral arguments, with written submissions filed on January 24, 2026.

Source reference: p. 2

The tribunal’s mandate, previously extended by six months under Section 29A(3) of the Arbitration and Conciliation Act, was set to expire on July 4, 2026.

Source reference: p. 2

Due to a medical emergency involving arbitrator Shri Bhawani Dutt Joshi, the tribunal directed the parties to seek a further extension from the Court.

Source reference: p. 2-3
02

Issues

1. Whether sufficient cause exists under Section 29A of the Arbitration and Conciliation Act to grant a further extension of the Arbitral Tribunal’s mandate.

Source reference: p. 3, para. 10-11

2. Whether an extension of six months is necessary given that the proceedings have reached the stage of final award publication.

Source reference: p. 4, para. 14
03

Law Applied

Section 29A of the Arbitration and Conciliation Act, 1996, which empowers the Court to extend the mandate of an Arbitral Tribunal upon the showing of "sufficient cause".

Source reference: p. 3, para. 10

Rohan Builders (India) Pvt. Ltd. v. Berger Paints India Ltd., which established that extensions are not granted as a matter of course and require judicial satisfaction of sufficient cause, noting that delays by the tribunal itself should generally be avoided.

Source reference: p. 3, para. 10
04

Reasoning

The Court found that sufficient cause was established due to the medical emergency of an arbitrator (angioplasty), which constituted a delay not attributable to a lack of diligence by the parties or the tribunal.

Source reference: p. 3, para. 11-12

The Court reasoned that refusing an extension at this advanced stage—where only the publication of the award remains—would frustrate the legislative intent of Section 29A and render the completed proceedings futile.

Source reference: p. 3-4, para. 13

The Court observed that since oral arguments and written submissions were already concluded by January 2026, a six-month extension was excessive; a three-month period was deemed sufficient to maintain the momentum of the "expeditious" scheme of the Act.

Source reference: p. 4, para. 14
05

Holding

The Court answered the issues by holding that while sufficient cause existed for an extension, the duration should be limited to three months.

The Court granted the petition in part, extending the mandate of the Arbitral Tribunal for a period of three months effective from July 4, 2026. The petition and related applications were disposed of accordingly.

Source reference: p. 4, para. 15-16
Delhi High Court

Original Court PDF

Ms Maruti Infracreation Pvt LtdvsThe Chief Engineer Nh Division Up Pwd

Delhi High Court · July 01, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment