APTEL

Delay in land acquisition due to uncontrollable factors and force majeure warrants condonation of time overruns.

Power Grid Corporation of India Limited vs Central Electricity Regulatory Commission &

APTELJUDGMENT: July 06, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Appellant, Power Grid Corporation of India Limited (PGCIL), was entrusted with the Eastern Region Strengthening Scheme-III (ERSS-III) involving eight transmission assets.

Source reference: para 3-4

The Investment Approval (IA) dated July 7, 2010, set a commissioning schedule of 28 months (by November 6, 2012).

Source reference: para 3-4

Actual commissioning was delayed by 16 to 36 months due to land acquisition hurdles and monsoon-related flooding.

Source reference: para 4, 16

The Central Electricity Regulatory Commission (CERC), via an order dated February 24, 2017, only partially condoned these delays, disallowed a portion of Interest During Construction (IDC) and Incidental Expenditure during Construction (IEDC), and subsequently dismissed a Review Petition on March 13, 2019.

Source reference: para 1, 8

The Appellant challenged these orders before the Appellate Tribunal for Electricity (APTEL).

Source reference: no citation
02

Issues

1. Whether the CERC erred in refusing to condone the time over-run caused by administrative delays in the land acquisition process and unprecedented weather conditions.

Source reference: para 9-10

2. Whether Regulation 12 of the CERC Tariff Regulations, 2014, categorically bars land acquisition issues from being treated as "uncontrollable factors" for the purpose of condoning delays.

Source reference: para 42-43

3. Whether the CERC failed to maintain judicial consistency by ignoring its own precedent in a similar matter (Petition No. 278/TT/2015) involving the same project site.

Source reference: para 18, 40
03

Law Applied

Regulation 11 and 12 of the CERC (Terms and Conditions of Tariff) Regulations, 2014, regarding the capitalization of IDC and IEDC.

Source reference: para 44

The Statement of Reasons (SoR) for Regulation 12 clarifies that delays in land acquisition arising from uncontrollable events may be considered on a case-to-case basis through a "prudence check".

Source reference: para 45-46
04

Reasoning

The Tribunal found that while PGCIL failed to explain the initial delay between August and December 2010, the CERC ignored substantial evidence showing PGCIL’s vigorous tracking of the land acquisition process thereafter, which involved several statutory stages beyond the licensee's control.

Source reference: para 24, 26

Regarding Assets 1-4, the Tribunal noted that the CERC overlooked IMD rainfall data proving September-October 2012 rains were 60% higher than average, constituting a condonable delay.

Source reference: para 30

Regarding Assets 5-8 (Chaibasa), the Tribunal underscored a lack of judicial consistency; the CERC had condoned the entire delay for balance assets at the same site in a different petition (278/TT/2015) based on the same facts, yet reached a contradictory conclusion in the impugned order.

Source reference: para 39-40

The Tribunal held that land acquisition is not a blanket "controllable factor" if the delay results from administrative externalities or Force Majeure.

Source reference: para 46
05

Holding

The Tribunal upheld the non-condonation of 3 months and 23 days for Assets 1-4 but condoned the remaining delays for all assets. For Assets 5-8, it condoned the entire period of time over-run.

The Tribunal allowed the appeal in part and the matter was remanded to the CERC to recompute IDC and IEDC based on the fresh condonation periods within three months.

Source reference: para 49, 50
APTEL

Original Court PDF

Power Grid Corporation of India LimitedvsCentral Electricity Regulatory Commission &

APTEL · July 06, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment