Engineer lacking contractual authority cannot terminate contract; termination power under Clause 60.1 rests only with Employer or Contractor

Sri Pranab Pathakv.The State Of Assam And 5 Ors

Engineer lacking contractual authority cannot terminate contract; termination power under Clause 60.1 rests only with Employer or Contractor. Sri Pranab Pathak vs The State Of Assam And 5 Ors. Gauhati High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the Executive Engineer (Respondent No. 6), who is defined as the "Engineer" under the GCC, had authority or jurisdiction to cancel/terminate the contract under Clause 60.1, which empowers only the Employer or the Contractor to terminate.

The court held

The Court held that the communication dated 17.01.2026 issued by Respondent No. 6 was without jurisdiction and authority.

It also directed

The NIT dated 02.02.2026 for the same work is also set aside and quashed.

The Court clarified that the setting aside shall not affect the Employer's powers to take action permissible under the contract. The writ petition is disposed of with no costs. The Court did not decide the Petitioner's malice allegations or the delegation plea.

01Facts

The Respondent No. 5 (Additional Chief Engineer-cum-Director, PWD, BTC) issued a Notice Inviting Tender dated 23.07.2025 for 14 works, including construction of a Community Hall at Dakhsin Bijni Degree College, Ananda Bazar, Baksa.

¶ 3–4 · p. 3

The Petitioner's bid was accepted by Letter of Acceptance dated 22.08.2025 at ₹94,99,870.37.

¶ 5 · p. 3

A Notice to Proceed was issued on 26.08.2025, and a contract was executed with Respondent No. 5 as "Employer".

¶ 6 · p. 4

Under the General Conditions of Contract (GCC), the "Employer" is Respondent No. 5, and the "Engineer" is the Executive Engineer (Respondent No. 6).

¶ 7 · p. 4

Clause 60.1 permits either the Employer or the Contractor to terminate for fundamental breach.

¶ 8 · p. 4

On 17.01.2026, Respondent No. 6 issued a communication "cancelling" the contract and directing the Petitioner to leave the site.

¶ 9 · pp. 4–5

A fresh NIT for the same work followed on 02.02.2026.

¶ 9 · p. 5

The Court stayed the re-tender process on 27.02.2026.

¶ 10 · p. 5

The Respondents alleged sub-standard work and non-rectification, relying on letters dated 06.11.2025 and 22.12.2025, and asserted delegation of cancellation power from Respondent No. 5 to Respondent No. 6.

¶ 11 · pp. 5–6

The Petitioner contended that these letters were never served on him.

¶ 12 · p. 6

At the hearing on 09.10.2026, the Court made enquiries on feasibility of performance at the original rate and on maintainability versus a suit for breach of contract.

¶ 13 · pp. 6–7

The Petitioner stated he remained willing to perform at the contracted rate.

¶ 14 · p. 8

02Issues

i.1. Whether the Executive Engineer (Respondent No. 6), who is defined as the "Engineer" under the GCC, had authority or jurisdiction to cancel/terminate the contract under Clause 60.1, which empowers only the Employer or the Contractor to terminate.

¶ 15 · p. 8 · ¶ 22 · p. 11 · ¶ 26 · p. 12

ii.2. Whether the impugned NIT dated 02.02.2026 issued in respect of the same work can stand once the cancellation is set aside.

¶ 27 · p. 12

03Law Applied

The GCC definitions in Clause 1 designate the Employer as Respondent No. 5 and the Engineer as Respondent No. 6, with the Engineer's functions limited to supervision, certification, variations and extensions of time.

¶ 7 · p. 4 · ¶ 22 · p. 11

Clause 60.1 confers the power to terminate for fundamental breach only on the Employer or the Contractor.

¶ 8 · p. 4 · ¶ 22 · p. 11

Cancellation annuls a contract that was never validly formed, whereas a validly subsisting contract can only be terminated for breach.

¶ 24 · pp. 11–12

The Petitioner's reliance on Clause 5 (delegation by the Engineer only, with notice to the Contractor) was noted but not adjudicated.

¶ 19 · p. 10

No precedents were cited in the judgment.

04Reasoning

The Court found the impugned communication was, in substance, a termination, since the contract was admittedly treated as valid throughout.

¶ 24 · pp. 11–12 · ¶ 25 · p. 12

Clause 60.1 vests termination power only in the Employer or the Contractor, and the Engineer is not so empowered.

¶ 26 · p. 12

Because the communication was issued by Respondent No. 6 alone, the Court held it was without authority and jurisdiction, regardless of the merits of the alleged breach.

¶ 26 · p. 12

The Court did not examine the alleged sub-standard work or the disputed letters of 06.11.2025 and 22.12.2025, as the jurisdictional defect was dispositive.

¶ 26 · p. 12

The Court further held that the fresh NIT could not survive, since quashing the cancellation revives the contract between the parties.

¶ 27 · p. 12

The Respondents' plea of delegation of power from the Employer to the Engineer and the maintainability question raised by the Court were not expressly decided.

¶ 13 · p. 7 · ¶ 18–19 · pp. 9–10

05Holding

The Court held that the communication dated 17.01.2026 issued by Respondent No. 6 was without jurisdiction and authority.

¶ 28(i) · p. 13

The NIT dated 02.02.2026 for the same work is also set aside and quashed.

¶ 28(ii) · p. 13

The Court clarified that the setting aside shall not affect the Employer's powers to take action permissible under the contract. The writ petition is disposed of with no costs. The Court did not decide the Petitioner's malice allegations or the delegation plea.

¶ 16 · p. 8 · ¶ 28(iii) · p. 13 · ¶ 28(iv) · p. 13
Gauhati High Court

Original Court PDF

Sri Pranab PathakvsThe State Of Assam And 5 Ors

Gauhati High Court · November 17, 2026