01Facts
The Respondent No. 5 (Additional Chief Engineer-cum-Director, PWD, BTC) issued a Notice Inviting Tender dated 23.07.2025 for 14 works, including construction of a Community Hall at Dakhsin Bijni Degree College, Ananda Bazar, Baksa.
¶ 3–4 · p. 3The Petitioner's bid was accepted by Letter of Acceptance dated 22.08.2025 at ₹94,99,870.37.
¶ 5 · p. 3A Notice to Proceed was issued on 26.08.2025, and a contract was executed with Respondent No. 5 as "Employer".
¶ 6 · p. 4Under the General Conditions of Contract (GCC), the "Employer" is Respondent No. 5, and the "Engineer" is the Executive Engineer (Respondent No. 6).
¶ 7 · p. 4Clause 60.1 permits either the Employer or the Contractor to terminate for fundamental breach.
¶ 8 · p. 4On 17.01.2026, Respondent No. 6 issued a communication "cancelling" the contract and directing the Petitioner to leave the site.
¶ 9 · pp. 4–5A fresh NIT for the same work followed on 02.02.2026.
¶ 9 · p. 5The Court stayed the re-tender process on 27.02.2026.
¶ 10 · p. 5The Respondents alleged sub-standard work and non-rectification, relying on letters dated 06.11.2025 and 22.12.2025, and asserted delegation of cancellation power from Respondent No. 5 to Respondent No. 6.
¶ 11 · pp. 5–6The Petitioner contended that these letters were never served on him.
¶ 12 · p. 6At the hearing on 09.10.2026, the Court made enquiries on feasibility of performance at the original rate and on maintainability versus a suit for breach of contract.
¶ 13 · pp. 6–7The Petitioner stated he remained willing to perform at the contracted rate.
¶ 14 · p. 802Issues
i.1. Whether the Executive Engineer (Respondent No. 6), who is defined as the "Engineer" under the GCC, had authority or jurisdiction to cancel/terminate the contract under Clause 60.1, which empowers only the Employer or the Contractor to terminate.
¶ 15 · p. 8 · ¶ 22 · p. 11 · ¶ 26 · p. 12ii.2. Whether the impugned NIT dated 02.02.2026 issued in respect of the same work can stand once the cancellation is set aside.
¶ 27 · p. 1203Law Applied
The GCC definitions in Clause 1 designate the Employer as Respondent No. 5 and the Engineer as Respondent No. 6, with the Engineer's functions limited to supervision, certification, variations and extensions of time.
¶ 7 · p. 4 · ¶ 22 · p. 11Clause 60.1 confers the power to terminate for fundamental breach only on the Employer or the Contractor.
¶ 8 · p. 4 · ¶ 22 · p. 11Cancellation annuls a contract that was never validly formed, whereas a validly subsisting contract can only be terminated for breach.
¶ 24 · pp. 11–12The Petitioner's reliance on Clause 5 (delegation by the Engineer only, with notice to the Contractor) was noted but not adjudicated.
¶ 19 · p. 10No precedents were cited in the judgment.
04Reasoning
The Court found the impugned communication was, in substance, a termination, since the contract was admittedly treated as valid throughout.
¶ 24 · pp. 11–12 · ¶ 25 · p. 12Clause 60.1 vests termination power only in the Employer or the Contractor, and the Engineer is not so empowered.
¶ 26 · p. 12Because the communication was issued by Respondent No. 6 alone, the Court held it was without authority and jurisdiction, regardless of the merits of the alleged breach.
¶ 26 · p. 12The Court did not examine the alleged sub-standard work or the disputed letters of 06.11.2025 and 22.12.2025, as the jurisdictional defect was dispositive.
¶ 26 · p. 12The Court further held that the fresh NIT could not survive, since quashing the cancellation revives the contract between the parties.
¶ 27 · p. 12The Respondents' plea of delegation of power from the Employer to the Engineer and the maintainability question raised by the Court were not expressly decided.
¶ 13 · p. 7 · ¶ 18–19 · pp. 9–1005Holding
The Court held that the communication dated 17.01.2026 issued by Respondent No. 6 was without jurisdiction and authority.
¶ 28(i) · p. 13The NIT dated 02.02.2026 for the same work is also set aside and quashed.
¶ 28(ii) · p. 13The Court clarified that the setting aside shall not affect the Employer's powers to take action permissible under the contract. The writ petition is disposed of with no costs. The Court did not decide the Petitioner's malice allegations or the delegation plea.
¶ 16 · p. 8 · ¶ 28(iii) · p. 13 · ¶ 28(iv) · p. 13Original Court PDF
Sri Pranab PathakvsThe State Of Assam And 5 Ors
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
