Failure to complete licensed riverbed work within time permits cancellation and security forfeiture.

GOVIND BHATT vs STATE OF UTTARAKHAND

Uttarakhand High CourtJUDGMENT: September 30, 20262 MIN READSOURCE JUDGMENT
Failure to complete licensed riverbed work within time permits cancellation and security forfeiture.. GOVIND BHATT vs STATE OF UTTARAKHAND. Uttarakhand High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioner received a licence under the Uttarakhand River Training Policy to remove riverbed material from the Ramganga River in Tehsil Thal, Pithoragarh.

Source reference: no citation

The District Magistrate cancelled the licence and ordered forfeiture of the petitioner’s security deposit on 1 October 2019.

Source reference: no citation

The petitioner argued that the work order was issued only in June 2019, required manual removal by 30 June 2019, and that heavy rains and the swollen river made timely completion impracticable.

Source reference: para. 2–3

The State relied on the tender press note, which required manual removal within two months, and on a work-order clause permitting cancellation without prior notice for non-compliance with the Policy and applicable rules.

Source reference: para. 4–7

It also submitted that the uncompleted work impaired river channelisation and caused loss to adjoining villages and State revenue.

Source reference: para. 4–7
02

Issues

1. Whether the Court should interfere with cancellation of the petitioner’s licence for failure to complete the riverbed-removal work within the stipulated period.

Source reference: para. 9–10

2. Whether forfeiture of the petitioner’s security deposit was justified under the licence and work-order conditions.

Source reference: para. 6, 9
03

Law Applied

The Court applied the conditions of the tender notice, licence and work order, together with the Uttarakhand River Training Policy.

Source reference: para. 9

It held that the licensee was bound by those conditions and that forfeiture of security was referable to the licence and work-order terms.

Source reference: para. 9
04

Reasoning

The petitioner had participated in the tender process subject to the stated requirement that riverbed material be removed manually within two months.

Source reference: para. 4–5

The work order also authorised cancellation without prior notice if the work was not completed in accordance with the Policy and applicable rules.

Source reference: para. 4–5

The Court accepted the State’s submissions concerning the failure to carry out the assigned work and the consequences for river channelisation and adjoining villages.

Source reference: para. 6–8

Because the petitioner was bound by the licence and tender conditions and did not complete the work within the stipulated time, the Court found no sufficient basis to interfere with cancellation or the related forfeiture.

Source reference: para. 9–10
05

Holding

The Court declined to interfere with the cancellation of the licence and upheld the order forfeiting the security deposit.

The writ petition was dismissed.

Source reference: para. 10–11
Uttarakhand High Court

Original Court PDF

GOVIND BHATTvsSTATE OF UTTARAKHAND

Uttarakhand High Court · September 30, 2026