01Facts
Gujarat Fibre Grid Network Limited (GFGNL) issued an RFP for selecting a Project Implementing Agency for the Amended BharatNet Program in Gujarat.
¶ 2The RFP disqualified an ISP/TSP licence holder for the Gujarat Licence Service Area and required bidders and consortium partners to submit an affidavit in Format XX, including declarations concerning majority ownership and corporate relationships with such licence holders.
¶ 2, 22–22.2GTPL challenged these conditions, contending that they lacked a rational basis and prevented it from bidding because its wholly owned subsidiary held an ISP licence for Gujarat.
¶ 3, 4.6, 6.2, 25.1GTPL had previously participated in BharatNet Phase-II work and had also been a consortium partner in BSNL tenders for other States containing a similar exclusion.
¶ 3, 4.6, 6.2, 25.1After GFGNL rejected GTPL’s request to amend the conditions, GTPL filed this petition shortly before the extended bid-submission deadline. The deadline was extended during the proceedings.
¶ 4.9–4.11, 502Issues
i.1. Whether the validity of a tender condition may be examined under Article 226 of the Constitution.
¶ 10ii.2. Whether the impugned ISP/TSP exclusion and Format XX affidavit requirement had a rational basis.
¶ 10iii.3. Whether excluding ISP/TSP licence holders in the relevant LSA constituted a reasonable classification under Article 14.
¶ 10iv.4. Whether the impugned condition was actuated by mala fides.
¶ 10v.5. Whether the petition should be declined on grounds of delay and/or acquiescence.
¶ 10vi.6. Whether the impugned condition and Format XX should be quashed and set aside.
¶ 1003Law Applied
Under Articles 14 and 19(1)(g), tender conditions must not be arbitrary, discriminatory, irrational or mala fide, though the tendering authority has substantial discretion to frame eligibility criteria.
¶ 13–18, 20–21Article 226 review is ordinarily confined to the legality and fairness of the decision-making process, not substitution of the court’s view for the authority’s commercial or technical judgment; intervention is warranted for arbitrariness, irrationality, procedural impropriety, favouritism or mala fides, and must account for public interest (Tata Cellular v. Union of India; Air India Ltd. v. Cochin International Airport Ltd.).
¶ 13–18, 20–21A classification satisfies Article 14 where it rests on an intelligible differentia having a rational nexus to the object sought to be achieved (Budhan Choudhry v. State of Bihar).
¶ 23–23.1A challenge to tender eligibility conditions accrues when the conditions are published, and delay in procurement matters is assessed in light of the stage and consequences of disrupting the process; representations do not, by themselves, excuse delay (Utkarsh Enterprises v. Union of India).
¶ 25.4–25.8Acquiescence entails knowing, passive acceptance of the challenged position (Union of India v. N. Murugesan).
¶ 25.9–25.10Provisions in the judgment · 32
RFP dated 04.06.2026 28 provisions
Section 2Section 2.1Section 2.1.1Section 3.1Section 4.38Section 4.49Section 5.6Section 5.15Section 5.19Section 5.19.1.1Section 5.19.1.4Section 5.19.2Section 5.19.3Section 5.23.3Section 5.23.5.1Section 5.23.7Section 5.23.8Section 5.23.9Section 5.23.11Section 5.23.14Section 5.24Section 7.9Section 7.9.2.6Section 7.9.2.14Section 7.9.2.19Section 8.2Section 9.4Section 19draft RFP as finalized by BSNL Committee Section 4ASection 2.1
Foreign Exchange Management (Encashment Of Draft, Cheque, Instrument And Payment Of Interest) Rules, 2000 Section 2.1
Land Acquisition Act, 1894 Section 5
04Reasoning
The Court found a discernible rationale for the exclusion: the PIA would operate and maintain common network infrastructure while having access to provisioning workflows, network capacity, route and fault information, and restoration processes.
¶ 22.6–22.9, 23.15–23.16A PIA affiliated with a downstream ISP/TSP could therefore occupy both an infrastructure-control role and a competing service-provider role, creating a risk to neutrality and non-discriminatory access.
¶ 22.6–22.9, 23.15–23.16The exclusion was limited to the LSA in which the bidder held a licence, and the Court held that this distinction was rationally connected to preventing conflicts of interest; contractual monitoring and penalties did not replace the preventive purpose of the condition.
¶ 23.5–23.14, 23.21It found no mala fides, noting that the condition formed part of the wider ABP procurement approach and was not shown to target GTPL.
¶ 24–24.2The Court also held that GTPL knew of the condition, including through its prior BSNL tender participation, and had delayed challenging GFGNL’s rejection of its request despite repeated extensions of the bid deadline; the petition was therefore also barred by delay and acquiescence.
¶ 25.1–25.11Although GFGNL had incorrectly characterised the condition as mandated by DBN, the Court considered that defect insufficient to invalidate the tender or justify intervention contrary to the larger public interest in timely BharatNet implementation.
¶ 26.4–26.6, 28–3005Holding
The Court upheld the impugned eligibility condition and Format XX, finding no ground to quash them.
¶ 26.1–26.6, 30, 32It rejected the petition, including on grounds of delay and acquiescence.
¶ 26.1–26.6, 30, 32The petitioner’s deposit of ₹5 lakh was retained as costs and ordered to be transferred to the High Court Legal Services Authority.
¶ 31The Court also refused GTPL’s post-judgment request to extend the bid-submission deadline.
¶ 33–34Original Court PDF
GTPL HATHWAY LIMITEDvsGUJARAT FIBRE GRID NETWORK LIMITED
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
