Facts
Le Chateau Co-operative Housing Society resolved in its EGM dated 24 April 1996 to construct additional floors on the society’s buildings and allot the additional flats to existing members, subject to payment of construction and TDR/FSI costs. Flat Nos. 701 and 702 were allotted to the petitioners, who were husband and wife and existing members of the society.
Source reference: paras. 3–4, 21Jet Speed Developers Pvt. Ltd. was appointed as contractor under an agreement providing for payment of construction and TDR costs at the agreed rate.
Source reference: paras. 22–25The petitioners disputed the society’s demands and did not make the demanded payments, despite repeated correspondence and opportunities.
Source reference: paras. 26–31At the AGM held on 24 July 1998, the society treated the petitioners’ allotment as terminated and allotted Flat Nos. 701 and 702 to Respondent Nos. 4 and 5, who were directors of the contractor and relatives of the Mankani family controlling a substantial portion of the society’s membership.
Source reference: paras. 32–34Subsequently, Flat Nos. 801 and 802 were constructed on the eighth floor of the Shamrock building and allotted to the same respondents.
Source reference: paras. 34–40The petitioners challenged the cancellation and allotment before the Cooperative Court and sought, alternatively, allotment of Flat Nos. 801 and 802. The Cooperative Court dismissed the dispute on 30 January 2017; the Cooperative Appellate Court dismissed the appeal on 11 January 2018 and the review on 13 July 2018.
Source reference: paras. 2, 7Issues
Whether the society’s cancellation of the petitioners’ allotment of Flat Nos. 701 and 702 and their subsequent allotment to the contractor’s directors was arbitrary and legally sustainable?
Source reference: paras. 32–36, 45Whether the society could allot additional flats to persons who were not existing members, contrary to the original resolution restricting allotment to society members?
Source reference: paras. 21, 23, 34–36Whether the petitioners could seek allotment of Flat Nos. 801 and 802 despite the separate proceedings concerning construction and allotment of those flats?
Source reference: paras. 35–44Whether equitable relief could be granted by transferring Flat Nos. 801 and 802 to the petitioners upon payment of ₹2.50 crores, while leaving the allotment of Flat Nos. 701 and 702 undisturbed?
Source reference: paras. 45–52Law Applied
The Court applied the principles governing the fair and non-arbitrary administration of a co-operative housing society, including adherence to resolutions of the general body, equal treatment of society members, and the requirement that society property and development benefits be administered for the benefit of eligible members rather than insiders or non-members.
Source reference: paras. 21, 23, 33–38It treated the contractor’s entitlement as contractual and monetary—namely, recovery of construction and TDR/FSI costs—and held that such entitlement did not confer any proprietary right to obtain flats in the society’s building.
Source reference: para. 36The Court further applied equitable and restorative principles in moulding relief under writ jurisdiction, balancing the petitioners’ membership rights, the respondents’ long occupation of Flat Nos. 701 and 702, and the unfinished and unoccupied status of Flat Nos. 801 and 802.
Source reference: paras. 45–49The Court also held that dismissal of separate proceedings concerning the validity of the eighth-floor construction did not bar adjudication of the petitioners’ independent claim to allotment of those flats, since that relief had not been sought in the separate dispute.
Source reference: paras. 38–40Reasoning
The Court accepted that the petitioners had defaulted in making timely payments for Flat Nos. 701 and 702, but held that this default did not justify the society’s direct and preferential allotment of those flats to the contractor’s directors, particularly when the original scheme contemplated allotment only to existing members and the respondents were close relatives of persons controlling approximately half the society’s flats.
Source reference: paras. 21–24, 33–36If the petitioners’ allotment had to be cancelled, the society ought to have adopted a transparent process, such as auction, rather than transferring the flats to persons connected with the contractor in adjustment of disputed dues.
Source reference: para. 33The contractor’s remedy for unpaid construction costs was recovery from the society, not acquisition of flats.
Source reference: para. 36The Court nevertheless declined to disturb the allotment of Flat Nos. 701 and 702 because the respondents had occupied them for a considerable period and the petitioners had admittedly not paid their contributions.
Source reference: para. 45In contrast, Flat Nos. 801 and 802 remained unfinished and unoccupied. Their allotment to the contractor’s directors was found to be a further arbitrary extension of the original illegality, and the separate dispute did not prevent the Court from granting relief because it concerned the validity of the eighth-floor construction and did not seek allotment of the flats to the petitioners.
Source reference: paras. 34–40To balance the equities, the Court directed transfer of Flat Nos. 801 and 802 to the petitioners upon payment of ₹2.50 crores to Respondent Nos. 4 and 5, rather than requiring payment of market value.
Source reference: paras. 46–51Holding
The writ petition was partly allowed.
The orders of the Cooperative Court, the Cooperative Appellate Court, and the review order were set aside.
Source reference: para. 52(i)The petitioners were declared entitled to Flat Nos. 801 and 802 in the Shamrock building; the society was directed to cancel the respondents’ allotment and enter the petitioners’ names in its membership register.
Source reference: para. 52(ii)–(iii)The petitioners were directed to pay ₹2.50 crores to Respondent Nos. 4 and 5 within six weeks, against which the respondents were to surrender the allotment and hand over possession.
Source reference: para. 52(iv)–(v)If the respondents refused payment, the petitioners could deposit the amount with the society and obtain possession with police assistance.
Source reference: para. 52(vi)The petitioners would be liable for maintenance only from the date of possession, and failure to pay within the stipulated period would revive the respondents’ allotment.
Source reference: para. 52(vii)–(viii)The allotment of Flat Nos. 701 and 702 was not disturbed owing to the respondents’ long occupation and the petitioners’ admitted non-payment.
Source reference: para. 45Acts & Sections Cited
1 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.
Maharashtra Co-operative Societies Act, 19601
Original Court PDF
Dr. Omprakash Bankatlal Soniminde And AnrvsLe Chateau Co-Op Hsg. Soc. Ltd. And Ors
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
