APTEL

Intra-state entities must pay state transmission charges despite using inter-state lines for power evacuation.

Haryana Vidyut Prasaran Nigam Ltd. v. Central Electricity Regulatory Commission & Ors. [Appeal No. 79 of 2017]

APTEL3 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Appellant (HVPNL), a State Transmission Utility (STU) in Haryana, challenged a CERC order dated 29.06.2016.

Source reference: p.2

NTPC (Respondent No. 2) operates the Faridabad Gas Power Station (GPS), which supplies its entire output to Haryana via CTUIL-owned lines (Faridabad-Samaypur and Faridabad-Palla).

Source reference: p.3

NTPC set up a 5 MW Solar Project at the same site to supply power to Odisha (GRIDCO) via the same lines.

Source reference: p.3-4

While these lines are owned by CTUIL, CERC had previously ruled they are "akin to state lines" because Haryana bears their full cost.

Source reference: p.7, 20

In 2014, NTPC signed Connectivity and LTA Agreements with HVPNL and obtained an NOC that stipulated payment of State transmission charges.

Source reference: p.4

Later, NTPC filed a petition before CERC claiming the system was ISTS and the HVPNL agreements were void.

Source reference: no citation

CERC ruled in favor of NTPC, holding that no State network was used and the agreements were non-est.

Source reference: p.17-19
02

Issues

1. Whether the transmission lines and substations (specifically Palla) used for evacuation are ISTS or State assets, and whether HVPNL is entitled to transmission charges.

Source reference: p.17 / para. 36

2. Whether the Connectivity and LTA Agreements entered into between NTPC and HVPNL are legally valid under the Connectivity Regulations.

Source reference: p.18 / para. 36

3. Whether the scope of an NOC from a State Utility for an intra-State entity seeking LTA on ISTS is limited only to metering and scheduling.

Source reference: p.24 / para. 48-49
03

Law Applied

The court applied Section 2(36)(iii) of the Electricity Act, 2003, which defines Inter-State Transmission System (ISTS) to include lines within a State owned or controlled by the CTU.

Source reference: p.10, 20

It referred to the CERC (Grant of Connectivity, Long-term Access and Medium-term Open Access) Regulations, 2009, specifically the 3rd Amendment regarding "Principal Generators".

Source reference: p.22

It relied on the precedent in PTC India Ltd. v. CERC (2010), establishing that statutory regulations override private contracts.

Source reference: p.27-28

It also considered the CERC (Sharing of Inter-State Transmission Charges and Losses) Regulations, 2010, regarding exemptions for solar power.

Source reference: p.13, 28
04

Reasoning

The Tribunal found that CERC made a factual error in claiming the Palla substation belongs to BBMB; it is owned by HVPNL, meaning the State network is indeed utilized.

Source reference: p.19, 30

While the 220 kV lines are technically ISTS under the Act, they are uniquely treated "akin to state lines" for cost recovery.

Source reference: p.21

The Tribunal reasoned that since the Solar Project was treated as an "intra-State entity" (because it connects through a Principal Generator dedicated to the State), it must follow the "Detailed Procedure" which requires an NOC from the STU.

Source reference: p.23-24

This NOC (Format LTA-3) explicitly allows STUs to specify state-level transmission charges.

Source reference: p.25

However, regarding the 2014 Agreements, the Tribunal held that since CTUIL is the designated "Nodal Agency" for ISTS connectivity under the Regulations, HVPNL had no authority to sign independent Connectivity/LTA contracts; thus, those specific contracts were void as they contravened statutory regulations.

Source reference: p.27-28
05

Holding

The Tribunal partly allowed the appeal.

CERC’s finding that no State transmission system was used is set aside, as the Palla substation is a State asset.

Source reference: p.19, 30

The finding that an STU’s NOC is limited only to scheduling/metering is set aside as it contradicts the approved Detailed Procedure.

Source reference: p.26, 30

HVPNL is entitled to receive applicable State transmission charges and losses from the date of commissioning.

Source reference: p.31

It upheld CERC’s view that the specific Connectivity and LTA Agreements signed with HVPNL were non-est in law because only the CTU can grant such access to ISTS.

Source reference: p.28, 31
APTEL

Original Court PDF

Haryana Vidyut Prasaran Nigam Ltd. v. Central Electricity Regulatory Commission & Ors. [Appeal No. 79 of 2017]

APTEL

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment