01Facts
The Government of India, through CPWD, engaged J.M. Swamy to construct a sewage treatment plant for ₹1,26,01,150, with completion stipulated by 12 October 2017.
¶ 3–7, 13–16The completion period was extended to 30 November 2019 without levy of compensation.
¶ 3–7, 13–16Swamy claimed that departmental delays and other impediments caused additional costs and losses; the arbitrator partly allowed his claims, awarded interest at 18% per annum, and rejected the Government’s counterclaim for compensation under Clause 2.
¶ 3–7, 13–16The Commercial Court set aside the award under Section 34, finding that substantial claims had not been adequately reconciled with the contract and evidence.
¶ 24–26Swamy appealed, seeking restoration of the award.
¶ 27, 29–3002Issues
i.1. Whether the arbitral award could be sustained in light of the Government’s specific objections under Section 34 of the Arbitration and Conciliation Act, 1996.
¶ 31ii.2. Whether the Commercial Court exceeded the permissible scope of Section 34 by setting aside the award, warranting appellate interference.
¶ 29, 36–3703Law Applied
Section 34 of the Arbitration and Conciliation Act, 1996 permits a court to set aside an award on the statutory grounds, including patent illegality under Section 34(2A); it does not permit a merits review merely because another view of the evidence or contract is possible.
¶ 26, 36Section 31(7)(b) governs post-award interest, which must be considered alongside the parties’ contractual provisions.
¶ 35In an appeal under Section 13(1-A) of the Commercial Courts Act, 2015, the appellate court considers whether the Commercial Court exceeded the permissible limits of intervention.
¶ 1, 37The agreement’s relevant provisions included Clauses 1A, 2, 5, 6A, 7 and 9, and Clause 2(x) of Schedule F.
¶ 25–26, 34–35No judicial precedents were identified in the judgment.
Provisions in the judgment · 12 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 9Section 11Section 31Section 34Section 37
Commercial Courts Act, 2015 Section 13
Indian Contract Act, 1872 Section 51Section 52Section 53Section 54Section 55Section 73
04Reasoning
The Court held that the extension of time, by itself, did not establish that all delay was attributable to the Department or entitle the contractor to every claimed amount.
¶ 32The claimant’s admissions and the record concerning the sequence of work, stoppage, equipment approvals and completion of civil works required the arbitrator to identify the specific departmental hindrances, their duration and their effect; the award did not adequately do so.
¶ 33The Court also found insufficient reconciliation of the overhead and loss-of-profit, idle-resource and escalation claims with the contractual terms, work completed and payments already made.
¶ 34The objections concerning GST, bank-guarantee commission and interest likewise raised issues of contractual entitlement and computation, including the applicable interest clauses and the dates of deduction and release.
¶ 35In the Court’s view, these deficiencies went beyond a disagreement over factual appreciation and disclosed grounds for the Commercial Court’s intervention.
¶ 26, 36–3705Holding
The High Court answered that the award could not be sustained against the specific objections and found no basis to interfere with the Commercial Court’s decision.
¶ 31, 37It dismissed the appeal and affirmed the order dated 19 April 2025 setting aside the arbitral award dated 23 July 2024.
¶ 37 · Order · p. 28Original Court PDF