Facts
The Petitioner (PVVNL), a government-owned power distribution company, awarded two turnkey contracts (Supply and Service) to the Respondent in March 2015 for rural electrification in Amroha, Uttar Pradesh
Source reference: p. 2-3While the project was scheduled for completion by October 2016, it was eventually commissioned in February 2019
Source reference: p. 4-5During execution, the Respondent requested several extensions citing site hindrances, which the Petitioner neither formally accepted nor rejected, allowing work to continue
Source reference: para. 8(ii)After issuing a completion certificate in April 2022, the Petitioner unilaterally deducted ₹4,50,68,820 as liquidated damages (LD) from the Respondent’s bills in June 2022
Source reference: p. 10-11The Respondent invoked arbitration, and the Arbitral Tribunal (AT) ordered the refund of the LD amount, finding the Petitioner partly responsible for the delay and noting a lack of evidence regarding "actual loss"
Source reference: para. 11The Petitioner challenged this portion of the award under Section 34 of the Arbitration and Conciliation Act
Source reference: para. 12Issues
1. Whether the Petitioner was justified in unilaterally deducting liquidated damages for the delay in performance without proving actual loss and where the delay was attributable to both parties
Source reference: para. 152. Whether the Arbitral Award, by directing the refund of the liquidated damages, was patently illegal or in conflict with the public policy of India
Source reference: para. 18Law Applied
Section 34 of the Arbitration and Conciliation Act, 1996, which limits judicial interference to awards suffering from patent illegality or those in conflict with the public policy of India
Source reference: para. 1, 14Under Section 74 of the Indian Contract Act, 1872, proof of "actual loss" is a sine qua non for claiming liquidated damages unless such loss is impossible to prove
Source reference: para. 11The Arbitral Tribunal is the sole judge of the quality and quantity of evidence and that courts cannot re-appreciate facts or evidence under Section 34
Source reference: para. 14, 16Reasoning
The court observed that the Arbitral Tribunal’s finding—that the delay was attributable to both parties—was supported by the Petitioner's failure to address numerous hindrance-related communications from the Respondent
Source reference: para. 8, 17The court noted that the Petitioner allowed the work to continue past the deadline without formal extensions and only deducted the LD amount three years after completion without prior notice
Source reference: para. 8, 11Applying the Kailash Nath principle, the court agreed with the AT that the Petitioner failed to establish any "actual loss" resulting from the delay, making the automatic 0.5% deduction untenable
Source reference: para. 11, 22The court emphasized that a unilateral adjustment of LD without adjudication or proof of loss, especially where the employer contributed to the delay, is impermissible in law
Source reference: para. 20, 22Consequently, the court found the AT’s reasoning to be a plausible view that did not shock the conscience of the court or meet the threshold of patent illegality
Source reference: para. 18, 21Holding
The court dismissed the petition and upheld the Arbitral Award
It held that the Petitioner could not recover liquidated damages because it failed to prove actual loss and was itself responsible for part of the delay
Source reference: para. 18, 22The court affirmed the AT's direction to the Petitioner to refund ₹4,50,68,820 to the Respondent along with interest at 8% per annum effective from July 1, 2022
Source reference: para. 11Original Court PDF
Pashchimanchal Vidyut Vitran Nigam LimitedvsIl And Fs Engineering And Construction Company Ltd
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in