01Facts
The petitioner, a contractor, was awarded a contract by the District Forest Officer (DFO), Dindigul, for construction of a Slender Loris Conservation Centre at Sukkampatty Village
¶ 1 · p. 8Disputes arose over the quantity and quality of work executed
¶ 1 · p. 8The petitioner filed three writ petitions seeking remeasurement and restraint on the engagement of third-party contractors. While these were pending, third-party contractors were engaged to execute work the petitioner had not performed
¶ 1 · p. 8Pursuant to the Court's order dated 15.06.2026, a committee of technical experts from Anna University recorded measurements; the petitioner objected to that report
¶ 2 · p. 8Two contempt petitions alleged wilful disobedience of earlier orders in WP(MD) Nos. 6382 and 6995 of 2026
CONT P(MD) Nos. 1042 & 1043 · p. 5The contract's dispute resolution clause (Clause 19) provides for referral of quantity or quality disputes to the Collector at the contractor's requisition, for measurement by a deputed officer in the contractor's presence, and for a Collector's decision on the deputed officer's report
¶ 3 · pp. 8–9At the hearing, the petitioner agreed to refer the quantity and quality dispute to the District Collector. The Special Government Pleader stated that the respondents were willing to pay ₹1,50,00,000 for work done, subject to the petitioner signing a running account bill
¶ 4 · p. 902Issues
i.1. Whether the disputed quantity and quality of work executed under the contract should be adjudicated by the District Collector under Clause 19 of the contract, rather than by the High Court in writ jurisdiction
¶ 4 · p. 9 · ¶ 5(iii) · p. 10ii.2. Whether the admitted value of work executed should be paid to the petitioner pending that adjudication
¶ 4 · p. 9 · ¶ 5(i)–(ii) · p. 10iii.3. Whether the contempt petitions and connected miscellaneous petitions survive once the primary dispute is resolved
¶ 6 · p. 1103Law Applied
Clause 19 of the parties' contract vests the Collector with power to appoint an officer to measure and examine disputed work in the contractor's presence, to decide the matter on the deputed officer's report, and to receive objections to measurements within prescribed time limits
¶ 3 · pp. 8–9The parties' consensual agreement to refer the dispute under Clause 19 was treated as the basis for disposal, without adjudicating the merits
¶ 4 · p. 9 · ¶ 5 · p. 9The petitions' prayers refer to the Tamil Nadu Transparency in Tenders Act, 1998 and Rules, 2000, and to Article 226 of the Constitution, but the order does not analyse or apply either
No precedent is cited
Provisions in the judgment · 1 · Linked ones open on LawLens
Contempt of Courts Act, 1971 Section 11
04Reasoning
The Court noted that the petitioner accepted reference of the quantity and quality dispute to the Collector and that the respondents admitted liability for ₹1.5 crore in work already executed
¶ 4 · p. 9Given the contractual forum and the parties' consent, the Court declined to decide the measurement dispute itself. It instead directed the respondents to prepare a running account bill for the admitted value, made payment conditional on the petitioner's signature, and preserved the petitioner's right to object to measurements taken either by the respondents or by the Anna University committee
¶ 5(i)–(iii) · p. 10To ensure a decision, the Court fixed a three-month period for the Collector, required a personal hearing for both parties, and extended the Collector's jurisdiction to monetary claims linked to quantity and quality
¶ 5(iv)–(v) · pp. 10–11Because the "primary dispute" was resolved through these terms, the Court closed the contempt petitions without costs and disposed of the connected miscellaneous petitions
¶ 6 · p. 1105Holding
The quantity and quality dispute is to be referred to and decided by the District Collector under Clause 19, and the admitted ₹1,50,00,000 is payable on signing a running account bill
¶ 4 · p. 9 · ¶ 5(i)–(iii) · p. 10The writ petitions were disposed of with the following directions: (i) the respondents must prepare a running account bill within one week of receipt of the order; (ii) payment must be released within two weeks of the petitioner signing it; (iii) the petitioner may object to all measurements, including the Anna University committee's; (iv) the Collector must hear both parties and decide within three months; and (v) the Collector must also decide linked monetary claims. The contempt petitions (CONT P(MD) Nos. 1042 and 1043 of 2026) were closed, and the connected miscellaneous petitions were closed, with no order as to costs
¶ 5(i)–(v) · pp. 10–11 · ¶ 6 · p. 11Original Court PDF
Kongu Construction and ContractorsvsThe District Forest Officer
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in