Facts
The Appellant (Operational Creditor), a partnership firm, was engaged by the Respondent (Corporate Debtor) for wind energy projects in Gujarat and Maharashtra.
Source reference: no citationThe Appellant claimed an outstanding debt of ₹42,49,84,942 (including interest) arising from 75 invoices raised between 2018 and 2019.
Source reference: p. 3-4A Section 8 demand notice was issued on 02.07.2019, followed by a Section 9 application under the IBC.
Source reference: p. 4The Corporate Debtor (CD) contested the claim, alleging that the Operational Creditor (OC) caused delays leading to liquidated damages (LD) and third-party losses.
Source reference: p. 21The CD also raised issues regarding the lack of final reconciliation of accounts between projects in different states.
Source reference: p. 22The Adjudicating Authority (NCLT Ahmedabad) rejected the Section 9 application on 13.12.2023.
Source reference: p. 12During the pendency of the appeal, the parties attempted a settlement which was not finalized to the satisfaction of the Appellate Tribunal.
Source reference: p. 37-38Issues
Whether the Section 9 application was maintainable in light of "pre-existing disputes" between the parties.
Source reference: p. 30/para. 37Whether the demand notice was premature based on the specific "default" timelines defined in the Work Order/MoU.
Source reference: p. 23/para. 46Law Applied
The Court primarily applied Section 9 of the Insolvency and Bankruptcy Code (IBC), 2016, regarding the initiation of CIRP by an operational creditor.
Source reference: p. 3It relied on the "plausible contention" test established in Mobilox Innovations Pvt. Ltd. v. Kirusa Software Pvt. Ltd., which requires the Adjudicating Authority to reject an application if a dispute truly exists in fact and is not spurious or moonshine.
Source reference: p. 29, 36It further applied the principle from Sabarmati Gas Ltd. v. Shah Alloys Ltd., holding that communications seeking "reconciliation" or adjustments of accounts constitute evidence of a pre-existing dispute.
Source reference: p. 26, 34Reasoning
The Tribunal observed that a series of emails exchanged between August and December 2018—well before the Section 8 notice—noted significant discrepancies in invoices, quality of work, and tax issues.
Source reference: p. 13-14, 31-32Specifically, an email dated 22.11.2018 noted that invoice acceptance was subject to reconciliation of Liquidated Damages (LD) and generation losses.
Source reference: p. 20, 32The Court found that the CD had suffered substantial LD from project owners like SJVNL, which it sought to set off against the OC’s claims.
Source reference: p. 21-22Applying Mobilox, the Tribunal reasoned that these disputes were not "moonshine" but substantial, as they involved pending arbitration and counter-claims.
Source reference: p. 33Furthermore, the Tribunal analysed Clause 38 of the Work Order, which stipulated that "default" only occurs 365 days after the due date; since many invoices were less than a year old at the time of the demand notice, the notice was deemed premature.
Source reference: p. 23, 34Holding
The NCLAT upheld the Adjudicating Authority's order, holding that the Section 9 petition was not maintainable due to pre-existing disputes and the premature nature of the demand notice.
The Tribunal concluded that the ongoing requirement for reconciliation and the unresolved claims for liquidated damages constituted a "plausible contention" requiring investigation beyond the summary scope of the IBC.
Source reference: p. 33, 36The Appeal was dismissed, and the request to withdraw with liberty to revive was denied as no formal settlement agreement was produced.
Source reference: p. 38Original Court PDF
M/s. Sri Bajrang Wind Park Developers v. M/s Inox Wind Infrastructure Services Limited & Ors. [Company Appeal (AT) (Insolvency) No. 630 of 2024]
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in