Bombay High Court
Arbitration and MediationCivil Procedure and Evidence

Rejecting a loss-of-profit claim despite employer fault and claimant innocence constitutes patent illegality.

Muncipal Corporation Of Gr. Mumbai vs Gammon India Limited

Bombay High CourtJUDGMENT: September 21, 20264 MIN READSOURCE JUDGMENT
Rejecting a loss-of-profit claim despite employer fault and claimant innocence constitutes patent illegality.. Muncipal Corporation Of Gr. Mumbai vs Gammon India Limited. Bombay High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Municipal Corporation of Greater Mumbai (“MCGM”) invited bids in January 1997 for the supply, erection and commissioning of 130 low-speed floating aerators at the Bhandup and Ghatkopar lagoons. M/s Hubert B.V. was the lowest bidder, while Gammon India Limited (“GIL”) was the second-lowest bidder. MCGM initially accepted GIL’s bid on 11 June 1998, although Hubert B.V.’s bid was less than 50% of GIL’s bid. Hubert B.V. challenged the award before the Bombay High Court. Pursuant to the Court’s order, an independent consultant found Hubert B.V.’s bid acceptable, following which MCGM agreed to award the contract to Hubert B.V. and subsequently terminated GIL’s contract by letter dated 6 September 1999

Source reference: pp. 3–4; paras. 5–6

GIL raised several claims before the Arbitral Tribunal, including costs of tendering, staff and establishment expenses, design fees, loss of profits, bank-guarantee charges and interest. The Tribunal rejected Claims 1, 5, 6 and 8, but allowed Claims 4 and 12, awarding Rs. 15,09,515 with interest at 9% per annum from 6 September 1999

Source reference: pp. 4–6; para. 4

GIL filed Arbitration Petition No. 481 of 2006 challenging the rejection of Claims 1, 5, 6 and 8, while MCGM filed Arbitration Petition No. 463 of 2006 challenging the grant of Claims 4 and 12

Source reference: pp. 2–3; paras. 2–4
02

Issues

Whether the Arbitral Tribunal’s rejection of GIL’s Claims 1, 5, 6 and 8 disclosed patent illegality or otherwise warranted interference under Section 34 of the Arbitration and Conciliation Act, 1996?

Source reference: pp. 9–15; para. 9

Whether the Tribunal was justified in rejecting the claim for loss of profits after finding that MCGM was responsible for awarding the contract to GIL and that GIL was not at fault?

Source reference: pp. 10–15; para. 9(c)

Whether the Tribunal’s award of bank-guarantee charges under Claim 4 and interest under Claim 12 was liable to be set aside under Section 34?

Source reference: pp. 15–16; para. 9(e)–(f)

Whether the Court could partially set aside the Arbitral Award in respect of an individual and severable claim?

Source reference: pp. 16–18; paras. 10–11
03

Law Applied

The Court applied Section 34 of the Arbitration and Conciliation Act, 1996, in its pre-2015-amendment form, under which an arbitral award could be set aside for, inter alia, patent illegality.

Source reference: pp. 12–14; para. 9(c)

Relying on Associate Builders v. Delhi Development Authority, the Court held that an award may be interfered with where it is based on no evidence, ignores vital evidence, considers irrelevant material, or adopts an interpretation of the contract that no fair-minded or reasonable person could adopt; however, the Court cannot act as an appellate court or reassess factual findings

Source reference: pp. 12–14; para. 9(c)

The Court further relied on Gayatri Balasamy v. ISG Novasoft Technologies Limited for the principle that an award may be set aside in part where the valid and invalid portions are legally and practically severable

Source reference: pp. 16–17; para. 10

Relying on National Highways Authority of India v. Trichy Thanjavur Expressway Ltd., the Court held that separate claims arising from the same contract may constitute independent, self-contained determinations capable of surviving independently

Source reference: pp. 17–18; para. 11
04

Reasoning

The Court upheld the Tribunal’s rejection of Claims 1, 5 and 6.

Source reference: no citation

Claim 1 was governed by the contractual clause requiring bidders to bear the costs of preparing and submitting bids irrespective of the outcome; the Tribunal’s interpretation of that clause was a permissible contractual interpretation and disclosed no patent illegality

Source reference: p. 9; para. 9(a)

Claim 5 involved staff salaries, travel and establishment expenses, and the Tribunal’s factual finding that the relevant staff was already employed elsewhere could not be reappreciated under Section 34

Source reference: p. 10; para. 9(b)

Claim 6 was rightly rejected because GIL had not paid the design fees claimed from M/s Smith and Loveless

Source reference: p. 15; para. 9(d)

However, the rejection of Claim 8 was inconsistent with the Tribunal’s own findings.

Source reference: pp. 10–15; para. 9(c)

The Tribunal had held that MCGM was responsible for awarding the contract to GIL, that GIL had committed no wrongdoing, and that termination followed from circumstances attributable to MCGM.

Source reference: pp. 10–15; para. 9(c)

Having reached those findings, the Tribunal could not reject the entire loss-of-profit claim merely because the claimed percentage appeared excessive or because the precise quantum had not been established.

Source reference: pp. 10–15; para. 9(c)

The proper course was to determine the extent, if any, of the recoverable loss.

Source reference: pp. 10–15; para. 9(c)

The complete rejection of the claim therefore amounted to patent illegality

Source reference: pp. 10–15; para. 9(c)

As to Claims 4 and 12, the Court found no error in awarding the normal bank-guarantee charges despite the absence of bank receipts.

Source reference: pp. 15–16; para. 9(e)–(f)

The Tribunal considered the claimed rates reasonable and awarded the corresponding interest under Claim 12.

Source reference: pp. 15–16; para. 9(e)–(f)

These determinations were not shown to be perverse or patently illegal

Source reference: pp. 15–16; para. 9(e)–(f)

Since Claim 8 was distinct and severable from the other claims, it could be set aside without disturbing the valid portions of the Award

Source reference: pp. 16–18; paras. 10–11
05

Holding

Arbitration Petition No. 463 of 2006 filed by MCGM was dismissed, and the awards under Claims 4 and 12 were maintained

Arbitration Petition No. 481 of 2006 filed by GIL was partly allowed: the rejection of Claim 8 was set aside for patent illegality, while the rejection of Claims 1, 5 and 6 was upheld

Source reference: pp. 14–15, 18; para. 12

The Court did not quantify or directly award loss of profits; it stated that GIL could pursue such remedies as were available in law concerning Claim 8

Source reference: p. 18; para. 12

MCGM’s request for a stay was refused in both petitions

Source reference: p. 19; para. 13
06

Acts & Sections Cited

3 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.

Arbitration and Conciliation Act, 19963

Bombay High Court

Original Court PDF

Muncipal Corporation Of Gr. MumbaivsGammon India Limited

Bombay High Court · September 21, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment