Karnataka High Court
Arbitration and MediationCivil Procedure and Evidence

Section 37 review cannot exceed Section 34’s narrow grounds for setting aside arbitral awards.

GULBARGA ELECTRICITY SUPPLY COMPANY LIMITED vs M/S POWER GEAR LIMITED AND ANR

Karnataka High CourtJUDGMENT: September 22, 20263 MIN READSOURCE JUDGMENT
Section 37 review cannot exceed Section 34’s narrow grounds for setting aside arbitral awards.. GULBARGA ELECTRICITY SUPPLY COMPANY LIMITED vs M/S POWER GEAR LIMITED AND ANR. Karnataka High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

GESCOM engaged Power Gear Limited under turnkey contracts for substation works, which were to be completed within nine months.

Source reference: para. 4–7, 25–29, 42

After deducting liquidated damages of ₹17,69,022 from the contractor’s bills for delay, GESCOM faced claims for repayment; it filed counterclaims seeking ₹90.90 lakh for alleged losses caused by the delay.

Source reference: para. 4–7, 25–29, 42

The arbitrator awarded the contractor ₹17,69,022 with interest at 18% per annum from the date of the award until realization and rejected GESCOM’s counterclaims.

Source reference: para. 4–7, 25–29, 42

GESCOM’s challenges under Section 34 of the Arbitration and Conciliation Act, 1996 were dismissed by the Principal District Judge, Kalaburagi.

Source reference: para. 8–10

GESCOM then appealed under Section 37 of that Act, read with Section 13 of the Commercial Courts Act, 2015.

Source reference: para. 8–10
02

Issues

1. Whether the Principal District Judge was justified under Section 34 of the Arbitration and Conciliation Act, 1996 in upholding the arbitral awards.

Source reference: para. 21

2. Whether the High Court, exercising appellate jurisdiction under Section 37, had grounds to interfere with the Section 34 judgment and the awards.

Source reference: para. 19, 48–57
03

Law Applied

Section 34 of the Arbitration and Conciliation Act permits interference with an arbitral award only on the statutory grounds, including patent illegality that goes to the root of the matter and denial of natural justice; a reasonable interpretation of the contract by the tribunal is not, by itself, a ground to set aside an award (Associate Builders v. DDA, as quoted at para 48).

Source reference: para. 48

Section 37 review is confined to the limits of Section 34: the appellate court cannot independently reassess the merits of the award or exceed the reviewing court’s authority (MMTC Ltd. v. Vedanta Ltd. and Konkan Railways Corporation Ltd. v. Chenab Bridge Project Undertaking, quoted at paras 48–49).

Source reference: para. 48–49

The court also relied on M/s C & C Construction Ltd. v. Ircon International Ltd. and Somdatt Builders NCC-NEC v. NHAI for the requirement of restraint when an award has been upheld under Section 34.

Source reference: para. 48, 50

S.V. Samudram v. State of Karnataka was cited for the limited options available to a Section 37 court and the need for reasoned findings before interfering with an award.

Source reference: para. 52

The court considered GESCOM’s reliance on ONGC v. Western Geco International Ltd. and Urban Infrastructure Real Estate Fund v. Neelkanth Realty Private Ltd., but held that GESCOM had not demonstrated how the awards violated public policy.

Source reference: para. 53–56
04

Reasoning

The arbitrator’s findings reflected shared responsibility for delay: some issues were decided for GESCOM, while others were decided for the contractor, including findings that GESCOM had delayed certain payments and that the contractor was not entirely responsible for the delay.

Source reference: para. 31–39, 46–47

The agreement also provided for an extension of time where the purchaser’s acts or omissions delayed performance (clause 40.1, reproduced at para 45).

Source reference: para. 45

The High Court concluded that GESCOM’s arguments largely challenged the tribunal’s assessment of the evidence and its conclusions on delay; they did not establish a recognised ground for setting aside the awards.

Source reference: para. 48–57

Its general assertion that the awards were contrary to public policy, without showing how, was insufficient.

Source reference: para. 48–57

Given the limited scope of Section 34 and the still narrower appellate review under Section 37, the Court found no basis to disturb the District Judge’s decision or the awards.

Source reference: para. 48–57
05

Holding

The High Court answered the issues against GESCOM and dismissed all three commercial appeals, leaving the Section 34 judgments and arbitral awards undisturbed.

It permitted Power Gear to withdraw the amount deposited by GESCOM in Court and directed the Registry to release it upon proper identification; pending applications were disposed of.

Source reference: para. 58
06

Acts & Sections Cited

3 provisions across 2 statutes referred to in this judgment. Each provision opens on LawLens.

Commercial Courts Act, 20151

Arbitration and Conciliation Act, 19962

Karnataka High Court

Original Court PDF

GULBARGA ELECTRICITY SUPPLY COMPANY LIMITEDvsM/S POWER GEAR LIMITED AND ANR

Karnataka High Court · September 22, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment