Karnataka High CourtEnvironmental LawAdministrative and Public Law

Show-cause notice alleging buffer-zone construction must be re-verified factually under the amended buffer-distance provision before enforcement

M/S PAN SYNTHETICS PVT LTDv.STATE OF KARNATAKA

Show-cause notice alleging buffer-zone construction must be re-verified factually under the amended buffer-distance provision before enforcement. M/S PAN SYNTHETICS PVT LTD vs STATE OF KARNATAKA. Karnataka High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether, in light of the amended Section 12(3) of the Karnataka Act No. 19 of 2026 and the Government Notification dated 18.02.2026, the question of whether the petitioner's construction falls within the prohibited buffer zone can be decided without a factual verification by the competent authority.

The court held

The court did not finally decide whether the construction is within the buffer zone. It held that the question requires factual verification under the amended Section 12(3) and the Notification dated 18.02.2026.

It also directed

The petitioner was granted liberty to file detailed objections to the show cause notice, with supporting documents showing that the construction lies beyond the 6-metre buffer.

R-7 is directed to afford a personal hearing, examine the applicability of the amended provision and notification, verify the property's location relative to the revenue boundary, consider the intervening Survey No. 23 and the grants made therein, and pass a reasoned order on whether the notice warrants further proceedings or ceases to survive.

Until that enquiry is concluded, no precipitative action may be taken against the petitioner. The writ petition is disposed of in these terms.

01Facts

The petitioner, a private limited company holding land in Survey No. 24, Peddanapalya Village, Bengaluru South Taluk, challenged a show cause notice dated 05.11.2019 issued by the Tahsildar (R-7) under which it was called upon to show cause why an allegedly unauthorised construction should not be removed.

¶ 2

The petitioner sought quashing of the notice and an injunction against demolition or fencing without a hearing.

¶ 1

During the hearing, the petitioner placed on record a Government Notification dated 18.02.2026, which re-determined the tank buffer zone using a graded classification based on the tank's extent, measured from the revenue boundary.

¶ 3

The petitioner also produced additional documents asserting that Survey No. 24 is separated from the lake by Survey No. 23, that the State has made grants in Survey No. 23, and that the validity of those grants is under enquiry pursuant to orders in other writ petitions.

¶ 4

The respondent-BMRDA contended that the impugned notice was only a show cause notice and that the petitioner should first submit its objections before the competent authority.

¶ 5

The learned Additional Government Advocate, on instructions, conceded that for a lake of more than 5 acres but less than 10 acres, the applicable buffer is 6 metres from the revenue boundary.

¶ 6

02Issues

i.1. Whether, in light of the amended Section 12(3) of the Karnataka Act No. 19 of 2026 and the Government Notification dated 18.02.2026, the question of whether the petitioner's construction falls within the prohibited buffer zone can be decided without a factual verification by the competent authority.

¶ 8 · ¶ 9

ii.2. Whether the petitioner should be relegated to submitting objections to the show cause notice before the competent authority, rather than obtaining a determination in writ jurisdiction at this stage.

¶ 5 · ¶ 10

03Law Applied

Section 12(3) of the Karnataka Act No. 19 of 2026, which amended Section 12, prohibits any construction or commercial, recreational or industrial activity within the buffer zone of specified tanks, save for listed public utility services carried out with prior approval of the Authority and without obstructing the natural inflow or outflow of water.

¶ 7

The buffer is fixed by a table linking tank area to buffer distance, with 6 metres prescribed for tanks above 1.00 to 10.00 acres.

¶ 7

The Government Notification dated 18.02.2026 adopts a graded classification based on tank extent, with buffer distances measured from the revenue boundary.

¶ 3 · ¶ 6

The court invoked its jurisdiction under Articles 226 and 227 of the Constitution of India.

Writ relief is discretionary and may be withheld where the authority has yet to decide disputed facts.

Provisions in the judgment · 1 · Linked ones open on LawLens

KARNATAKA (ABOLITION OF CASH GRANTS) ACT, 1967 Section 2

04Reasoning

The court treated the amended statutory provision and the fresh notification as a subsequent development materially affecting the dispute.

¶ 7 · ¶ 8

Read with the photographs and additional documents, the material prima facie showed that Survey No. 23 intervenes between the lake and the petitioner's Survey No. 24, and that the construction may lie beyond the 6-metre buffer.

¶ 8

The court held that whether the construction falls within the prohibited zone could not be determined on the earlier prescription or without factual verification under the amended provision.

¶ 9

The matter therefore required the competent authority's assessment of distance from the revenue boundary and of the Survey No. 23 grants, which are themselves under judicial enquiry.

¶ 4 · ¶ 12

Since the authority had not yet considered the objections, the court declined to adjudicate the merits and preferred to let the petitioner place its material before R-7.

¶ 10

To protect the petitioner meanwhile, the court restrained precipitative action pending the enquiry, and all contentions were expressly kept open.

¶ 13

05Holding

The court did not finally decide whether the construction is within the buffer zone. It held that the question requires factual verification under the amended Section 12(3) and the Notification dated 18.02.2026.

¶ 9

The petitioner was granted liberty to file detailed objections to the show cause notice, with supporting documents showing that the construction lies beyond the 6-metre buffer.

¶ 10 · ¶ 11

R-7 is directed to afford a personal hearing, examine the applicability of the amended provision and notification, verify the property's location relative to the revenue boundary, consider the intervening Survey No. 23 and the grants made therein, and pass a reasoned order on whether the notice warrants further proceedings or ceases to survive.

¶ 12 · ¶ 13

Until that enquiry is concluded, no precipitative action may be taken against the petitioner. The writ petition is disposed of in these terms.

¶ 13
Karnataka High Court

Original Court PDF

M/S PAN SYNTHETICS PVT LTDvsSTATE OF KARNATAKA

Karnataka High Court · November 18, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment