Karnataka High CourtCivil Procedure and EvidenceAdministrative and Public Law

State's administrative lethargy is no sufficient cause for condoning a 651-day delay in appeal.

THE SPECIAL LAND ACQUISITION OFFICERv.LAXMAN

State's administrative lethargy is no sufficient cause for condoning a 651-day delay in appeal.. THE SPECIAL LAND ACQUISITION OFFICER vs LAXMAN. Karnataka High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the appellants, being State instrumentalities, have shown sufficient cause for condonation of a 651-day delay in filing the appeal under Section 74(1) of the 2013 Act.

The court held

The Court held that the appellants failed to show sufficient cause for the 651-day delay and that the explanation was not acceptable.

It also directed

I.A. No. 1/2026 seeking condonation of delay is dismissed, and consequently the Miscellaneous First Appeal No. 207664 of 2025 is dismissed as time-barred.

The judgment and award dated 31.08.2023 in LAC No. 1708/2021 stand unaffected.

01Facts

The appellants, the Special Land Acquisition Officer (UKP, Almatti), the Commissioner for Rehabilitation and Resettlement, and the General Manager, Rehabilitation and Resettlement (Land Acquisition Division), filed this appeal under Section 74(1) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, challenging the judgment and award dated 31.08.2023 in LAC No. 1708/2021.

p. 2

The appeal was filed on 20.09.2025 with a delay of 651 days.

p. 2 · ¶ 1

I.A. No. 1/2026 was filed on 04.08.2026 seeking condonation of that delay.

p. 2 · ¶ 1

The affidavit accompanying the application stated the reasons for delay, but the judgment does not set out their content.

p. 16 · ¶ 4

The Court found that the appellants had not approached it within the stipulated period and had not shown sufficient cause.

p. 16 · ¶ 4

02Issues

i.1. Whether the appellants, being State instrumentalities, have shown sufficient cause for condonation of a 651-day delay in filing the appeal under Section 74(1) of the 2013 Act.

p. 2 · ¶ 1 · p. 16 · ¶ 4

ii.2. Whether, in the absence of condonation, the appeal can be entertained on merits.

p. 16 · ¶ 5

03Law Applied

The Court relied primarily on the principles of limitation as stated in Shivamma v. Karnataka Housing Board, 2025 SCC OnLine SC 1969, which hold that limitation is founded on public policy and that a State is not to receive liberal condonation of delay merely because public interest is invoked.

pp. 2–3 · ¶ 228–229

It treated administrative lethargy as insufficient cause and required the State to show bona fides and vigilance throughout the period.

pp. 11–12 · ¶ 261

It applied the principle of dura lex sed lex from Basawaraj, as quoted in Shivamma, that limitation must be applied with full rigour even where it causes hardship.

pp. 6–8 · ¶ 234

It further relied on State of Odisha v. Managing Committee of Namatara Girls High School, 2026 SCC OnLine SC 191, which held that condonation is a matter of discretion, not of right, and that a bureaucratic explanation amounting to a "lame excuse" does not justify condonation.

pp. 13–15 · ¶ 16–21

The Court also relied on Section 5 of the Limitation Act, 1963, as construed in Shivamma, which requires sufficient cause to be shown before delay is condoned.

pp. 9–10 · ¶ 254, 258 · p. 8 · ¶ 235

Provisions in the judgment · 4 · Linked ones open on LawLens

Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 Section 74

Limitation Act, 1963 Section 5Section 3

Code of Civil Procedure, 1908 Section 100

04Reasoning

The Court first noted the length of delay, 651 days, and the State's status as the appellant.

p. 2 · ¶ 1

Applying Shivamma, it held that the State's institutional status does not relax the requirement of sufficient cause, and that the reasons offered in the affidavit did not satisfy the Court.

p. 16 · ¶ 4

Following Namatara, it treated the explanation as an excuse rather than an explanation, consistent with the Supreme Court's rejection of bureaucratic inertia as a ground for condonation.

pp. 14–15 · ¶ 17–21

Because the delay was not condoned, the appeal was held to be time-barred, and the Court did not reach the merits of the award.

p. 16 · ¶ 5

The judgment does not identify the specific reasons in the affidavit, so the precise factual shortfall is not discernible from the text.

05Holding

The Court held that the appellants failed to show sufficient cause for the 651-day delay and that the explanation was not acceptable.

p. 16 · ¶ 4

I.A. No. 1/2026 seeking condonation of delay is dismissed, and consequently the Miscellaneous First Appeal No. 207664 of 2025 is dismissed as time-barred.

p. 16 · ¶ 5

The judgment and award dated 31.08.2023 in LAC No. 1708/2021 stand unaffected.

p. 16 · ¶ 5
Karnataka High Court

Original Court PDF

THE SPECIAL LAND ACQUISITION OFFICERvsLAXMAN

Karnataka High Court · November 13, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment