Kerala High CourtConstruction LawAdministrative and Public Law

Statutory Pre-deposit for RERA Appeals Cannot Be Diluted by Substituting Contractual or Market Interest Rates

M R GURU PRASADv.HOYSALA PROJECTS PRIVATE LIMITED

Statutory Pre-deposit for RERA Appeals Cannot Be Diluted by Substituting Contractual or Market Interest Rates. M R GURU PRASAD vs HOYSALA PROJECTS PRIVATE LIMITED. Kerala High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the High Court, through an interim order, can substitute the statutory interest rate (BMPLR + 2%) prescribed under Rule 18 with an alternative benchmark (MCLR) for the purpose of the mandatory pre-deposit under Section 43(5) of the Act.

The court held

The Court held that the pre-deposit must strictly comply with the BMPLR+2% rate prescribed in Rule 18.

It also directed

The Court allowed the appeals, vacated the interim orders of the Single Judge, granted the promoter two weeks to deposit the shortfall, and held that if the promoter fails to deposit the amount as per the statutory rate, the Appellate Tribunal is entitled to dismiss the appeals for non-compliance.

01Facts

The appellants (allottees) entered into agreements in 2013 to purchase apartments in the "Hoysala EVM" project, with a promised completion date of October 2016.

¶ 4(a)

Upon the promoter's failure to complete the project, the Kerala Real Estate Regulatory Authority (RERA) directed the promoter to pay simple interest at 16.85% per annum (SBI's Benchmark Prime Lending Rate (BMPLR) + 2%) as per Rule 18 of the Kerala RERA Rules, 2018.

¶ 4(b)

The promoter appealed to the Appellate Tribunal, which insisted on the mandatory pre-deposit of the entire interest amount under the proviso to Section 43(5) of the RERA Act, 2016.

¶ 4(d)

The promoter challenged this via writ petitions, and a learned Single Judge passed an interim order permitting the promoter to calculate the pre-deposit using the Marginal Cost of Funds based Lending Rate (MCLR) instead of the statutory BMPLR, effectively reducing the deposit amount.

¶ 1, 5

The allottees filed these writ appeals challenging that interim substitution.

¶ 1

02Issues

i.1. Whether the High Court, through an interim order, can substitute the statutory interest rate (BMPLR + 2%) prescribed under Rule 18 with an alternative benchmark (MCLR) for the purpose of the mandatory pre-deposit under Section 43(5) of the Act.

¶ 1, 19

ii.2. Whether the requirement of pre-deposit under the proviso to Section 43(5) is onerous or flexible.

¶ 7(c), 17

iii.3. Whether a Writ Appeal is maintainable against an interim order that substantially affects the jurisdictional requirements of a statutory appeal.

¶ 25, 26

03Law Applied

Section 43(5) of the Real Estate (Regulation and Development) Act, 2016, which mandates a 100% pre-deposit of interest/compensation ordered by RERA before a promoter's appeal can be "entertained".

¶ 13

Rule 18 of the Kerala RERA Rules, 2018, which prescribes the interest rate as SBI’s BMPLR plus 2%.

¶ 12

The Supreme Court precedent in Newtech Promoters and Developers Pvt. Ltd. v. State of UP, which upheld the constitutionality of the pre-deposit condition as a "class in itself" to protect home buyers.

¶ 15-17

The Full Bench decision in K.S. Das v. State of Kerala, permitting appeals against intermediate orders that cause substantial prejudice or touch upon vital rights.

¶ 25

Provisions in the judgment · 12 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 Section 34

Code of Civil Procedure, 1908 Section 100

Micro, Small and Medium Enterprises Development Act, 2006 Section 19

rajasthan stamp act, 1998 Section 65

Real Estate (Regulation and Development) Act, 2016. Section 3Section 18Section 19Section 31Section 43Section 58Section 84

Securitisation and Reconstruction of Financial Assets and Enforcement of Security Interest Act, 2002 Section 18

04Reasoning

The court reasoned that Rule 18 is a piece of delegated legislation and its choice of BMPLR+2% was a conscious policy decision by the State to provide a "deterrent rate" against defaults, despite the existence of the MCLR regime in 2018.

¶ 19, 22

By substituting MCLR for BMPLR via an interim order, the Single Judge effectively amended a statutory rule through judicial intervention, violating the doctrine of separation of powers.

¶ 19, 24

The court noted that the difference in liability (nearly Rs. 20 lakhs per flat in this case) significantly undermined the legislative intent to protect allottees.

¶ 22, 23

The court found the order appealable under the K.S. Das doctrine because it was an "intermediate order" that conferred jurisdiction on the Appellate Tribunal where none existed under the statute, thereby causing final and substantial prejudice to the allottees' statutory safeguards.

¶ 27

05Holding

The Court held that the pre-deposit must strictly comply with the BMPLR+2% rate prescribed in Rule 18.

¶ 28(a)

The Court allowed the appeals, vacated the interim orders of the Single Judge, granted the promoter two weeks to deposit the shortfall, and held that if the promoter fails to deposit the amount as per the statutory rate, the Appellate Tribunal is entitled to dismiss the appeals for non-compliance.

¶ 28(b)-(d)
Kerala High Court

Original Court PDF

M R GURU PRASADvsHOYSALA PROJECTS PRIVATE LIMITED

Kerala High Court · June 02, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment