Facts
Dergaon Municipal Board invited bids for a water-network extension project under an NIT dated 29 August 2026.
Source reference: no citationThe petitioner’s technical bid was rejected, while two other bidders qualified.
Source reference: paras. 2–3The petitioner challenged the evaluation, alleging that the Board had incorrectly applied Clause 4.7’s bid-capacity formula to the successful bidders.
Source reference: paras. 4–5, 10The respondents accepted that the value of “N” used for those bidders was incorrect, but relied on certification by an Executive Engineer and also cited deficiencies in the petitioner’s bid, including its bid-capacity statement and site-inspection documents, and non-submission of GST returns.
Source reference: paras. 4–5, 10The Court found that the successful bidders’ documents used an “N” value of 5.0, whereas the 90-day completion period required a value of 2.5 under the tender formula.
Source reference: paras. 22–24Issues
Whether the successful bidders’ technical qualification could stand despite the admitted incorrect application of Clause 4.7’s bid-capacity formula
Source reference: paras. 10–11, 22–26Whether the petitioner’s alleged documentary deficiencies justified its rejection, and whether those requirements were mandatory and uniformly applicable to all bidders
Source reference: paras. 31–39Whether the appropriate relief was a fresh technical evaluation of all bids
Source reference: paras. 40–43Law Applied
In judicial review of public tenders, the Court ordinarily does not substitute its technical assessment for that of the tendering authority; it reviews the legality and fairness of the decision-making process (*Tata Cellular v. Union of India*, (1994) 6 SCC 651).
Source reference: para. 13Interference is warranted where a decision is mala fide, intended to favour a bidder, or so arbitrary and irrational that no responsible authority could have reached it, having regard to public interest (*Jagdish Mandal v. State of Orissa*, (2007) 14 SCC 517).
Source reference: para. 14The tender-authoring authority’s interpretation generally receives deference, but must be supported by the tender’s language and cannot be unfair, perverse, or arbitrary (*Afcons Infrastructure Ltd. v. Nagpur Metro Rail Corporation Ltd.*, (2016) 16 SCC 818; *M/S Mickey Traders v. M/S LRY Labor Contractor*, 2026 INSC 1025).
Source reference: paras. 15–17Tender conditions must be applied consistently and public authorities must adhere to the standards they have prescribed (*Ramana Dayaram Shetty v. International Airport Authority of India*, (1979) 3 SCC 489).
Source reference: paras. 27–29Whether a condition is essential or merely ancillary depends on its language, object, and context (*Poddar Steel Corporation v. Ganesh Engineering Works*, (1991) 3 SCC 273).
Source reference: paras. 37–38Under Clause 4.7, available bid capacity is calculated as A × N × 2 − B, and the bid-capacity statement must be countersigned by an Engineer not below the rank of Executive Engineer.
Source reference: para. 6Reasoning
The Court held that certification of the successful bidders’ statements did not cure an incorrect calculation: authentication and accuracy are distinct, and the Evaluation Committee remained responsible for applying Clause 4.7 correctly.
Source reference: paras. 24–26Because the admitted error could affect eligibility, it was material and rendered the decision to qualify those bidders arbitrary.
Source reference: paras. 20–21, 30The petitioner’s own alleged deficiencies did not validate the erroneous qualification of other bidders, nor did the challenge entitle the petitioner automatically to qualify.
Source reference: para. 40As the character and consequences of the GST-return and site-inspection requirements required interpretation of the tender documents as a whole, the Court left those questions to the Committee on fresh evaluation, requiring a reasoned and uniform approach.
Source reference: paras. 32–39Holding
The petition was allowed.
The technical evaluation under the NIT dated 29 August 2026 was set aside, and the matter remitted for fresh technical evaluation of all participating bidders under the original tender conditions.
Source reference: para. 43(I)–(II)The Committee was directed to apply Clause 4.7 correctly, determine the status of the GST-return, site-inspection, and other requirements by reasoned interpretation, and apply the same standard to all bidders.
Source reference: para. 43(III)–(V)The Court did not direct that the petitioner or any other bidder be declared qualified or awarded the contract; the fresh evaluation was to be completed preferably within two weeks, without precluding a fresh tender where reasonable grounds existed.
Source reference: para. 43(VI)–(VIII)The parties were directed to bear their own costs.
Source reference: para. 44Acts & Sections Cited
5 provisions across 2 statutes referred to in this judgment. Linked provisions open on LawLens.
Tender Document3
Instructions to Bidders2
Original Court PDF
M/S Ashirvad Associates And AnrvsThe Dergaon Municipal Board And 5 Ors
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in