01Facts
M/s Bafna Global Venture Pvt. Ltd. filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996, seeking, inter alia, restraint against NCERT from invoking or forfeiting a bank guarantee of ₹6,09,20,000, restraint against the issuing bank from making payment under the guarantee, and restraint against debarment or blacklisting of the petitioner.
p. 1During the proceedings, the parties, upon instructions, agreed that the disputes forming the subject matter of the petition should be referred to arbitration.
p. 2The contract contained an arbitration clause providing for reference of disputes to a sole arbitrator appointed by the Director, NCERT, with Delhi as the seat/place of arbitration and Delhi courts having jurisdiction.
pp. 2–3By consent, the parties waived the contractual and formal procedures for appointment and agreed to the appointment of a sole arbitrator by the Court.
p. 302Issues
i.Whether the disputes between the petitioner and NCERT should be referred to arbitration by consent of the parties.
pp. 2–3ii.Whether the Court should appoint a sole arbitrator notwithstanding the contractual mechanism providing for appointment by the Director, NCERT.
p. 3iii.Whether the pending Section 9 petition should be treated as an application under Section 17 of the Arbitration and Conciliation Act, 1996, and whether the interim order should continue until its adjudication by the arbitral tribunal.
pp. 4–503Law Applied
The Court applied Section 9 of the Arbitration and Conciliation Act, 1996, concerning interim measures by a court, and Section 17, concerning interim measures granted by an arbitral tribunal.
pp. 1, 4–5It also applied Section 12(2), requiring disclosures by the proposed arbitrator regarding circumstances affecting independence or impartiality.
p. 4The Court gave effect to the contractual arbitration clause, which required disputes connected with the contract to be referred to arbitration, provided for a reasoned award, and designated Delhi as the place of arbitration and Delhi courts as having jurisdiction.
pp. 2–3Since both parties consented to arbitration and waived the contractual and formal appointment procedure, the Court exercised its authority to appoint a sole arbitrator and directed that the arbitration be conducted under the rules and aegis of the Delhi International Arbitration Centre (DIAC).
p. 304Reasoning
The parties’ unequivocal agreement that the disputes should be arbitrated made referral to arbitration appropriate and avoided further delay in commencing the arbitral proceedings.
pp. 2–3Although the contract contemplated appointment by the Director, NCERT, both parties expressly waived that procedure and consented to appointment by the Court; accordingly, the Court appointed Justice Ravi Shankar Jha (Retd.) as the sole arbitrator.
p. 3The Court preserved the arbitral tribunal’s competence to determine all issues, including arbitrability and jurisdiction, and directed that the disputes, claims, and counterclaims be adjudicated independently and on their merits.
p. 4Since the substantive interim reliefs sought in the Section 9 petition could appropriately be considered by the tribunal under Section 17, the Court converted the petition into a Section 17 application.
pp. 4–5To prevent the interim protection from lapsing before the tribunal could consider that application, the Court continued the interim order dated 24 June 2026 until the Section 17 application was taken up and decided.
pp. 4–505Holding
The Court allowed the parties’ consensual request for arbitration and appointed Mr. Justice Ravi Shankar Jha (Retd.), Former Chief Justice of the Punjab and Haryana High Court, as the sole arbitrator.
p. 3The arbitration was directed to be conducted under the DIAC Rules, subject to the arbitrator furnishing the requisite Section 12(2) disclosures.
p. 4The Section 9 petition was treated as an application under Section 17, to be decided by the learned arbitrator upon entering the reference.
pp. 4–5The interim order dated 24 June 2026 was continued until adjudication of the Section 17 application, and the petition and pending applications were disposed of accordingly.
pp. 4–5Original Court PDF
Ms Bafna Global Venture Pvt LtdvsNational Council Of Educational Research And Training Ncert & Anr.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
