01Facts
The Petitioner, a proprietary civil contractor, was awarded a subcontract by the Respondent (HCC) for work on NH-34 under a Work Order dated 21 September 2010, which reduced the completion period to six months and the contract value to ₹5.72 crore.
¶ 3(iii)–(v)Work was idle from March to July 2011 due to a Jharkhand stone-mining ban.
¶ 3(x)On 12 July 2011 the Petitioner furnished a fresh performance bank guarantee (PBG) of ₹10 lakh.
¶ 3(xiv)After a joint inspection on or about 15 July 2011, the parties agreed to short-close the contract on a "No-Claim" basis.
¶ 3(xv)On 25 July 2011 the Petitioner signed a Work Completion and No-Claim Certificate (NCC), which confirmed full and final payment, no balance due, and that the certificate was given "voluntarily and without any compulsion".
¶ 3(xvi) · ¶ 24The Respondent released the PBG on 21 September 2011 and paid the final bill of ₹34 lakh in December 2011.
¶ 3(xviii)–(xix)The Petitioner first raised a claim for damages by demand notice dated 7 May 2012.
¶ 3(xx)The Petitioner's statement of claim (₹3.17 crore) did not mention the NCC or allege coercion, although the Respondent's counterclaim (₹2.49 crore) and its defence relied on the NCC.
¶ 3(xxvi) · ¶ 19Before the sole arbitrator, the Tribunal framed Issue No. 1 on coercion, took evidence, found the NCC voluntary, and dismissed the claim with ₹1 lakh costs, without deciding Issues 2–4 on merits.
¶ 3(xxvii) · ¶ 2 · ¶ 7 · ¶ 17The Petitioner challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996 (the "Act").
¶ 1The Petitioner did not press a limitation ground under Section 34(3).
¶ 2802Issues
i.1. Whether the arbitrator's finding that the NCC was voluntarily executed, and not obtained under coercion, is open to interference under Section 34 of the Act.
¶ 17 · ¶ 36ii.2. Whether the arbitrator was obliged to decide Issues 2–4 on merits, and whether the failure to do so, and to explain why Issue 1 made them unnecessary, vitiates the award.
¶ 7 · ¶ 9 · ¶ 27 · ¶ 29iii.3. Whether the NCC operates as a bar to the Petitioner's claims for damages, losses or compensation for short closure or extra work.
¶ 6 · ¶ 22iv.4. Whether the award is perverse or suffers from patent illegality warranting interference under Section 34.
¶ 25–26 · ¶ 34v.5. Whether the Respondent's plea of suppression of material facts is an independent ground for dismissal.
¶ 15 · ¶ 3503Law Applied
The Court applied the limited scope of review under Section 34 of the Act, under which re-appreciation of evidence is impermissible and interference is confined to patent illegality or perversity as laid down in Ssangyong Engineering v. NHAI (2019) 15 SCC 131 and Associate Builders v. DDA (2015) 3 SCC 49.
¶ 26 · ¶ 34For discharge or no-claim certificates, the Court followed Boghara Polyfab v. National Insurance (2009) 1 SCC 267, under which the tribunal first decides whether the discharge was vitiated by coercion; if it was voluntary, the claim may be rejected without merits.
¶ 29 · ¶ 27The Court relied on Master Construction v. Union of India (2011) 12 SCC 357, requiring a coercion plea to be raised promptly and substantiated, and New India Assurance v. Genus Power (2015) 2 SCC 424, holding a bald plea insufficient.
¶ 32–33The Court applied ONGC Mangalore Petrochemicals v. ANS Constructions (2018) 3 SCC 373, holding that a belated coercion plea cannot be taken once no coercion is established.
¶ 30The Court applied Grasim Industries v. Agarwal Steel (2010) 1 SCC 83, presuming that a signatory has read and understood a signed document absent force or fraud.
¶ 31The Court relied on Dyna Technologies and Rishabh Kumar, which treat the arbitrator as master of the quality and quantity of evidence.
¶ 34The Court accepted that CPC principles are not strictly binding in arbitration and distinguished Mongia Realty v. Manik Sethi (2022) 11 SCC 572.
¶ 27The Court noted the clean-hands and suppression authorities relied on by the Respondent (Ramjas Foundation, Dalip Singh, Bhaskar Laxman Jadhav).
¶ 15Provisions in the judgment · 3 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 34Section 10Section 11
04Reasoning
The Court held that the arbitrator's determination of Issue 1 was a reasoned finding of fact, which was the threshold question on which the whole dispute turned.
¶ 17On the evidence, the Petitioner's proprietor admitted in oral evidence that he had been fully paid for the work done, and the Court treated this as an admission that bars a later claim.
¶ 18The Tribunal found that the Petitioner accepted the final bill, did not raise any damages claim after the NCC, PBG release, or final payment, and first alleged coercion in May 2012, about nine to ten months later.
¶ 18–19 · ¶ 21The Petitioner's own oral evidence was contradictory on whether the NCC was pre-typed or signed on a blank letterhead, and it did not explain why it sought a copy of the NCC only verbally and in writing.
award paras. 31–34, quoted in para. 19The NCC's express recital of voluntary execution and indemnity also supported that conclusion.
¶ 24Because the Petitioner led no substantive evidence of coercion, the presumption of Grasim applied and the plea was treated as a bald and belated assertion.
¶ 25 · ¶ 31–33Applying Boghara and ONGC Mangalore, the Tribunal was therefore justified in not deciding Issues 2–4, since the NCC was a complete bar once voluntariness was found.
¶ 27 · ¶ 29–30The Court rejected the perversity and patent illegality challenge, noting that the arbitrator did not base its finding on "no evidence" or ignore vital evidence, and that a plausible view on the evidence cannot be substituted.
¶ 25–26 · ¶ 34The Court found the Respondent's suppression argument academic once the coercion finding was upheld.
¶ 3505Holding
The Court held that the arbitrator's finding that the NCC was voluntarily executed, and not obtained by coercion or duress, is a plausible finding of fact that does not warrant interference under Section 34.
¶ 17 · ¶ 34Consequently, the arbitrator correctly applied Boghara and was justified in not deciding Issues 2–4 on merits.
¶ 29The Respondent's suppression plea was rendered academic and was not decided.
¶ 35The Court found no perversity or patent illegality.
¶ 26 · ¶ 36The Section 34 petition is dismissed without interference, with no costs. Interim applications are disposed of accordingly. Any amount deposited in Court is to be released within one month of the judgment's upload on the Court's website.